09900.doc

DOC document 33 KB Posted

Attached to
CONSTRUCT HEAVY TIMBER LOG RECREATION SHELTER AT AMOLE CANYON Federal contract opportunity
Solicitation number
AG-83A7-10-S-0013
Issued by
Department of Agriculture Forest Service R3-Southwestern Region

About this file

Attachment - Specification

View the file

Other files for this federal contract opportunity

Other files attached to CONSTRUCT HEAVY TIMBER LOG RECREATION SHELTER AT AMOLE CANYON, newest first.
File Type Posted
SF 30.pdf PDF
Sf 30 modification 1.docx DOCX document
02336-imported_fill.docx DOCX document
01410-Testing_Quality.doc DOC document
03-SiteDetails 11X17(2) —
06100-carpentry.rtf RTF text file
01200_Mobilization.doc DOC document
07-Shelter2 11X17(2) —
03200-qrs.doc DOC document
02310_Grading.doc DOC document
02230_Clearing_ _Grubbing.doc DOC document
CONSTRUCTION rfq amole canyon.docx DOCX document
05-ShelterDetails 11X17(2) —
06-Shelter 11X17(2) —
Wage Det NM100001 6-4-10 NM1.docx DOCX document
02725_agg_base_surface.rtf RTF text file
02-SitePlan 11X17(2) —
01330-submittal_procedure.rtf RTF text file
05120-qrs.doc DOC document
03100-qrs.doc DOC document
04-Sections Dtls 11X17(2) —
02317_Excavation_ _Backfill_Structures.doc DOC document
01101-Abbrevaitions.doc DOC document
02845-wheel_stops.docx DOCX document
06131-Log_Shelter.doc DOC document
03350_Concrete_Finishing.docx DOCX document
07900_-_joint_sealers.docx DOCX document
07410-metal_roofing.rtf RTF text file
Response Pkg Amole Canyon.docx DOCX document
07130_-_underlaymentr.rtf RTF text file
01-TitleSheet 11X17(2) —
03300-qrs.doc DOC document
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 09900

PAINTING

PART 1 - GENERAL CONDITIONS

1.01 SUMMARY

A. Provide staining and surface preparation for exterior unfinished surfaces, exposed interior items, exposed roof elements and other accessories,

1.02 STANDARDS

A. National Paint and Coatings Association.

1.03 SUBMITTALS

A. Submit product data, samples, 4’ x 4’ mockup of each paint and stain color, warranties.

PART 2 - PRODUCTS

2.01 PRODUCTS

A. Products: Sherwin-Williams Company, Glidden Paint Company, Pratt and Lambert, Inc., Valspar Paint Company, Olympic Stain

Company.

B.

Regulations: Compliance with VOC and environmental regulations.

C.

First-line commercial-quality for all coating systems.

PART 3 - EXECUTION

3.01 INSTALLATION

A. This Section to comply with all requirements of Division 1.

B.

Protect hardware and adjacent surfaces.

C.

Sand before painting or staining until smooth and flat and sand between coats.

D.

Apply paint/stain to achieve manufacturer’s recommended dry film thicknesses.

F.

Recoat areas which show bleed-through or defects.

G.

Touch-up damaged surfaces at completion of construction.

H.

Clean paint/stain splatter from adjacent surfaces including slab.

I.

All work shall performed when exterior temperature is above 45 Degrees Fahrenheit.

3.02 SCHEDULE

A. Exterior surfaces:

1.

Zinc Coated (Galvanized) Metal – One coat of dust-zinc oxide primer coating, two coats of oil-based exterior paint.

2.

Ferrous Metal – One coat of base paint, two coats of oil-based exterior paint.

3.

Wood – Two coats of exterior oil-based semi-transparent wood stain.

4.

Concrete – Transparent sealer – Two coats HB-150 Water Repellent.

PART 4 - MEASUREMENT AND PAYMENT

4.01

MEASUREMENT

The work specified herein will not be measured for payment.

4.02

PAYMENT

This work is incidental to related pay items

END OF SECTION