02336-imported_fill.docx

DOCX document 18 KB Posted

Attached to
CONSTRUCT HEAVY TIMBER LOG RECREATION SHELTER AT AMOLE CANYON Federal contract opportunity
Solicitation number
AG-83A7-10-S-0013
Issued by
Department of Agriculture Forest Service R3-Southwestern Region

About this file

Attachment - Specification

View the file

Other files for this federal contract opportunity

Other files attached to CONSTRUCT HEAVY TIMBER LOG RECREATION SHELTER AT AMOLE CANYON, newest first.
File Type Posted
SF 30.pdf PDF
Sf 30 modification 1.docx DOCX document
09900.doc DOC document
01410-Testing_Quality.doc DOC document
03-SiteDetails 11X17(2) —
06100-carpentry.rtf RTF text file
01200_Mobilization.doc DOC document
07-Shelter2 11X17(2) —
03200-qrs.doc DOC document
02310_Grading.doc DOC document
02230_Clearing_ _Grubbing.doc DOC document
CONSTRUCTION rfq amole canyon.docx DOCX document
05-ShelterDetails 11X17(2) —
06-Shelter 11X17(2) —
Wage Det NM100001 6-4-10 NM1.docx DOCX document
02725_agg_base_surface.rtf RTF text file
02-SitePlan 11X17(2) —
01330-submittal_procedure.rtf RTF text file
05120-qrs.doc DOC document
03100-qrs.doc DOC document
04-Sections Dtls 11X17(2) —
02317_Excavation_ _Backfill_Structures.doc DOC document
01101-Abbrevaitions.doc DOC document
02845-wheel_stops.docx DOCX document
06131-Log_Shelter.doc DOC document
03350_Concrete_Finishing.docx DOCX document
07900_-_joint_sealers.docx DOCX document
07410-metal_roofing.rtf RTF text file
Response Pkg Amole Canyon.docx DOCX document
07130_-_underlaymentr.rtf RTF text file
01-TitleSheet 11X17(2) —
03300-qrs.doc DOC document
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 02336

IMPORTED STRUCTURAL FILL

PART 1 - GENERAL

1.1 - Description A. This section specifies imported structural fill to be furnished, placed and compacted to meet grades that are shown on the drawings for the concrete walks, concrete slabs and other miscellaneous concrete items.

1.2 - Related Work Specified Elsewhere 01410 – Testing and Quality Control

02230 - Clearing and Grubbing
02310 – Grading

02317 – Excavation and Backfill for Structures

02725 – Agreggate Base and Surface Course
03300 - Concrete

PART 2 - PRODUCTS

2.1 - Fill Material

A. Materials shall not contain organic, frozen, or other unsuitable material. Materials must be approved by the COR prior to use.

1. Structural Fill Material. Material containing no rock larger than 3 inches in greatest dimension; 15% Maximum passing the No. 200 Sieve, ASHTO T 27 and T 11; a 30% Maximum Liquid Limit, ASSHTO T 89.

PART 3 - EXECUTION

3.1 – Foundation Excavation and Preparation

A. Footing Keyed into Undisturbed Material: Excavate the foundation to the limits of the footing and compact foundation. Where material does not stand vertically, fill all space between the limits of the footing and the remaining undisturbed material with concrete.

B. Excavation shall be made to the required depth and to a width that will permit the installation and bracing of forms REGARDLESS OF THE NATURE OF MATERIAL ENCOUNTERED.

C. All soft and yielding material shall be removed and replaced with imported Structural Fill Material.

D. The foundation shall be shaped and compacted to a firm even surface conforming to the section shown in the drawings.

3.2 – Structural Fill Construction

A. Where fill construction is required to bring the grades to the elevations shown on the drawings, the fill shall be placed in uniform lifts. Maximum lift thickness shall be 8 inches loose unless otherwise specified. Each lift shall be compacted to a minimum of 95% of maximum density per ASTM D 1557.

B. Deposit crushed aggregate as specified in Section 02725 as the final lift underneath the slabs/sidewalks as shown on the drawings and on the outside edge of concrete slab where applicable.

3.3 – Compaction of Imported Structural Fill.

A. Determine optimum Moisture content and maximum density according to AASHTO T 99, Method C. Adjust the moisture content of the backfill material to a moisture content suitable for compaction.

B. Compact material placed in all layers to at least 95% of the maximum density. Determine in place density and moisture content according to AASHTO T 310 or other approved test procedures.

3.4 - Grading

A. Grade exterior surfaces uniformly to blend with adjacent ground.

3.5 - Excess or Unsuitable Excavated Material

A. Remove all excess material from the site, and stockpile in designated areas as designated in field by the COR.

3.6 - Excavated Rock

A. Excavated rock shall be disposed of in the designated area as designated in field by the COR.

PART 4 - MEASUREMENT AND PAYMENT

4.1 - Method of Measurement

A. Measurement will be for cubic yards of structural fill material furnished, placed and compacted. Excavation for footings shall be considered incidental to item .

4.2 - Basis of Payment

A. Payment for this item shall be made as follows:

Pay Item Description Pay Unit

02336(01) Imported Structural Fill, In Place CY For Shelter Slab

02336(02) Imported Structural Fill, In Place CY For Parking Slab and Sidewalk Slab