8-Section 01152 - Applications for Payment 031826.pdf

PDF 133 KB Posted

Attached to
Rehabilitation of Manholes, Sanitary Stations and Wet Wells - Phased Projects
Solicitation number
ITB No.: 26-403/DL
Issued by
Palm Beach County, Florida

About this file

Summary

This is a specification document for Applications for Payment procedures related to ITB No. 26-403/DL 01152 for the Rehabilitation of Manholes, Sanitary Stations and Wet Wells - Phased Projects in Florida. The project involves a licensed and authorized contractor with a minimum of five years' experience to rehabilitate twenty-six (26) manholes, thirteen (13) Detection Stations, two (2) Pump Stations, five (5) Sanitary Lift Stations, and replace eleven (11) Manhole Covers and Rims in the Class I and Class III landfill leachate collection systems. All work includes cleaning and protective coatings. The contract is structured as an initial two (2) year period with an option to renew for an additional one (1) year at the Authority's sole discretion. This is a phased project requiring submission of bid responses electronically through Bonfire by the specified deadline.

The Applications for Payment procedures require contractors to submit typed applications on forms provided by the Owner using the accepted Schedule of Values as the basis for payment requests. Contractors must provide three (3) copies of each application with itemized data on continuation sheets formatted according to the Schedule of Values, rounded to the nearest dollar. Progress payments require updated record drawings for review by the Owner as a prerequisite for monthly payments, and material stored on-site requires copies of original paid invoices. Final payment applications must include a final statement of accounting as specified in the Contract Closeout section. Substantiating data must be submitted when required by the Owner, with a cover letter identifying the project, application number, date, and detailed list of enclosures. The Authority will not consider bid responses received by any means other than the Bonfire platform, making electronic submission the sole acceptable method.

View the file

Other files

File Type Posted
5-Section 01370 - Schedule of Values 031826.pdf PDF
20-Section 01153 - Change Order Procedures 031826.pdf PDF
13-Section 01200 - Project Meetings 031826.pdf PDF
9-Section 01111- Permits 031826.pdf PDF
23-MANHOLE AND WET WELL REHABILITATION RECORD DWG CDM FEB 2014 7.pdf PDF
12-Section 01310 - Progress Schedules 031826.pdf PDF
30-ITB 26-403 - Project Experience Forms.pdf PDF
2-Section 01095 - Reference Standards 031826.pdf PDF
11-Section 02767 - Monolithic Lining System 031826.pdf PDF
25-SHT C-2 - Class III Leachate Piping Site Plan.pdf PDF
24-SHT C-1 - Class I Leachate Piping Site Plan.pdf PDF
19-Section 01700 - Contract Closeout 031826.pdf PDF
1-Section 01005 - General Requirements 031826.pdf PDF
22-Class I and III Leachate Collection System Details.pdf PDF
15-Section 01010 - Summary of Work 031826.pdf PDF
33-ITB 26-403 - Vendor Acknowledgement Form.pdf PDF
27-ITB 26-403 - Bid Bond.pdf PDF
29-ITB 26-403 - Insurance Requirement Checklist.pdf PDF
16-Section 01100 - Special Project Procedures 031826.pdf PDF
7-Section 01610 - Material and Equipment 031826.pdf PDF
21-Section 01110 - Environmental Protection Procedures 031826.pdf PDF
31-ITB 26-403 - Section 00300 - Bid Form - Price.pdf PDF
10-Section 01300 - Submittals 031826.pdf PDF
4-Section 01102 - Safety Health and Emerg Response Requirements 031826.pdf PDF
26-ITB 26-403 - Authority to Execute Contract.pdf PDF
6-Section 01025 - Measurement and Payment 031826.pdf PDF
18-Section 01740 - Warranties and Bonds 031826.pdf PDF
3-Section 01014 - Construction Sequence 031826.pdf PDF
14-Section 01710 - Cleaning 031826.pdf PDF
34-ITB 26-403 - Rehab of Manholes, Sanitary Stations and Wet Wells - Phased Projects.pdf PDF
28-ITB 26-403 - Bidders Qualifications Statement.pdf PDF
32-ITB 26-403 - Trench Safety Act.pdf PDF
17-Section 01041 - Project Coordination 031826.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITB No.: 26-403/DL 01152 - 1 Rehab of Manholes, Sanitary Stations and Wet Wells - Phased Projects.

SECTION 01152

APPLICATIONS FOR PAYMENT

PART 1 – GENERAL

1.01 REQUIREMENTS INCLUDED:

A. The CONTRACTOR shall submit Applications for Payment to the OWNER in accordance with the schedule established by Conditions of the Contract and Agreement between OWNER and CONTRACTOR.

B. The accepted Schedule of Values, Section 01370, shall be used as the basis for the CONTRACTOR’s Application for Payment.

1.02 RELATED REQUIREMENTS:

A. The Contract Documents include, but are not limited to, the following related sections:

1. Agreement between OWNER and CONTRACTOR.

2. Standard General Conditions of the Construction Contract is included in Section 00700.

3. Schedule of Values are included in Section 01370.

4. Construction Photographs are included in Section 01300.

5. Contract Closeout is included in Section 01700.

1.03 SUBMITTALS:

A. Submit applications typed on forms provided by the OWNER.

Application for Payment, with itemized data typed on 8-1/2-in by 11-in or 8-1/2-in by 14-in white paper continuation sheets.

B. Provide itemized data on continuation sheet:

1. Format, schedules, line items and values: Those of the Schedule of Values accepted by the OWNER.

C. Provide construction photographs in accordance with Section 01300.

1.04 PREPARATION OF APPLICATION FOR EACH PROGRESS PAYMENT:

A. Application Form:

1. Fill in required information, including that for Change

Orders executed prior to date of submittal of application.

2. Fill in summary of dollar values to agree with respective totals indicated on continuation sheets.

3. Execute certification with signature of a responsible officer of Contract firm.

B. Continuation Sheets:

1. Fill in total list of all scheduled component items of Work, with item number and scheduled dollar value for each item.

2. Fill in dollar value in each column for each scheduled line item when work has been performed or products stored.

ITB No.: 26-403/DL 01152 - 2 Rehab of Manholes, Sanitary Stations and Wet Wells - Phased Projects.

a. Round off values to nearest dollar, or as specified for Schedule of Values.

3. List each Change Order executed prior to date of submission, at the end of the continuation sheets.

a. List by Change Order Number and description, as for an original component item of work.

4. To receive approval for payment on component material stored on site, submit copies of the original paid invoices with the application for payment.

1.05 SUBSTANTIATING DATA FOR PROGRESS PAYMENTS:

A. When the OWNER requires substantiating data, CONTRACTOR shall submit suitable information, with a cover letter identifying:

1. Project.

2. Application number and date.

3. Detailed list of enclosures.

4. For stored products:

a. Item number and identification as shown on application.

b. Description of specific material.

B. Submit one (1) copy of data and cover letter for each copy of application.

C. The CONTRACTOR is to maintain an updated set of drawings to be used as record drawings in accordance with Section 01720. As a prerequisite for monthly progress payments, the CONTRACTOR is to exhibit the updated record drawings for review by the OWNER.

1.06 PREPARATION OF APPLICATION FOR FINAL PAYMENT:

A. Fill in Application form as specified for progress payments.

B. Use continuation sheet for presenting the final statement of accounting as specified in Section 01700 – Contract Closeout.

1.07 SUBMITTAL PROCEDURE:

A. Submit Applications for Payment to the OWNER at the times stipulated in the Agreement.

B. Number: Three (3) copies of each Application.

C. When the OWNER finds Application properly completed and correct, they will transmit certificate of payment to OWNER, with copy to CONTRACTOR.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION (NOT USED)

END OF SECTION