This is a Project Meetings specification document for ITB No. 26-403/DL, issued by a Florida authority for the Rehabilitation of Manholes, Sanitary Stations and Wet Wells - Phased Projects. The scope of work encompasses rehabilitation of twenty-six manholes, thirteen detection stations, two pump stations, replacement of eleven manhole covers and rims in Class I and Class III landfill leachate collection systems, and five sanitary lift stations, including cleaning and protective coatings. The contractor must be a licensed and authorized Warren Environmental products applicator with a minimum of five years' experience. The contract will be structured as a phased project with an initial two-year term and an option to renew for an additional one-year period at the authority's sole discretion. Bidders must submit responses electronically through Bonfire by specified deadlines, with all questions and clarifications submitted through the same platform.

The specification establishes mandatory meeting protocols throughout the project lifecycle, including a pre-construction meeting scheduled no later than ten calendar days after the effective agreement date, regular progress meetings every thirty days following the pre-construction meeting or notice to proceed, and weekly construction progress meetings. The pre-construction and progress meeting agendas must address construction progress, deliveries, subcontractor activities, work schedules, submittals, design and permitting issues, potential change orders, and payment applications. Contractor representatives attending meetings must be qualified and authorized to act on behalf of their respective entities, and the owner will prepare agendas, arrange facilities, preside over meetings, and distribute minutes within fifteen working days of each meeting. The contractor is responsible for providing current submittal logs and updated construction schedules at each progress meeting in accordance with Sections 01300 and 01310 of the contract documents.

View the file

Other files

File Type Posted
5-Section 01370 - Schedule of Values 031826.pdf PDF
20-Section 01153 - Change Order Procedures 031826.pdf PDF
9-Section 01111- Permits 031826.pdf PDF
23-MANHOLE AND WET WELL REHABILITATION RECORD DWG CDM FEB 2014 7.pdf PDF
12-Section 01310 - Progress Schedules 031826.pdf PDF
30-ITB 26-403 - Project Experience Forms.pdf PDF
2-Section 01095 - Reference Standards 031826.pdf PDF
11-Section 02767 - Monolithic Lining System 031826.pdf PDF
25-SHT C-2 - Class III Leachate Piping Site Plan.pdf PDF
24-SHT C-1 - Class I Leachate Piping Site Plan.pdf PDF
19-Section 01700 - Contract Closeout 031826.pdf PDF
8-Section 01152 - Applications for Payment 031826.pdf PDF
1-Section 01005 - General Requirements 031826.pdf PDF
22-Class I and III Leachate Collection System Details.pdf PDF
15-Section 01010 - Summary of Work 031826.pdf PDF
33-ITB 26-403 - Vendor Acknowledgement Form.pdf PDF
27-ITB 26-403 - Bid Bond.pdf PDF
29-ITB 26-403 - Insurance Requirement Checklist.pdf PDF
16-Section 01100 - Special Project Procedures 031826.pdf PDF
7-Section 01610 - Material and Equipment 031826.pdf PDF
21-Section 01110 - Environmental Protection Procedures 031826.pdf PDF
31-ITB 26-403 - Section 00300 - Bid Form - Price.pdf PDF
10-Section 01300 - Submittals 031826.pdf PDF
4-Section 01102 - Safety Health and Emerg Response Requirements 031826.pdf PDF
26-ITB 26-403 - Authority to Execute Contract.pdf PDF
6-Section 01025 - Measurement and Payment 031826.pdf PDF
18-Section 01740 - Warranties and Bonds 031826.pdf PDF
3-Section 01014 - Construction Sequence 031826.pdf PDF
14-Section 01710 - Cleaning 031826.pdf PDF
34-ITB 26-403 - Rehab of Manholes, Sanitary Stations and Wet Wells - Phased Projects.pdf PDF
28-ITB 26-403 - Bidders Qualifications Statement.pdf PDF
32-ITB 26-403 - Trench Safety Act.pdf PDF
17-Section 01041 - Project Coordination 031826.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITB No.: 26-403/DL 01200 - 1 Rehab of Manholes, Sanitary Stations and Wet Wells - Phased Projects.

SECTION 01200

PROJECT MEETINGS

PART 1 – GENERAL

1.01 REQUIREMENTS INCLUDED:

A. The OWNER shall schedule and administer the pre-construction meeting, periodic progress meetings, and specifically called meetings throughout progress of the Work. The OWNER shall:

1. Prepare agenda for meetings.

2. Make physical arrangements for meetings.

3. Preside at meetings.

4. Record the minutes; include significant proceedings and decisions.

5. Reproduce and distribute copies of minutes within fifteen

(15) working days after each meeting.

a. To participate in the meeting.

b. To parties affected by decisions made at the meeting.

B. Representatives of CONTRACTOR, subcontractors and suppliers attending meetings shall be qualified and authorized to act on behalf of the entity each represents.

C. The CONTRACTOR shall attend meetings to ascertain that work is expedited consistent with Contract Documents and construction schedules.

1.02 RELATED REQUIREMENTS:

A. The Contract Documents include, but are not limited to, the following related sections:

1. Instructions to Bidders

2. Section 01300: Submittals

3. Section 01310: Construction Schedules

1.03 PRE-CONSTRUCTION MEETING:

A. Schedule a pre-construction meeting no later than ten (10) calendar days after effective date of Agreement.

B. The location shall be at a central site, convenient for all parties, designated by the OWNER.

C. Attendance:

1. OWNER’s representative

2. Resident Project Representative

3. CONTRACTOR’s Superintendent

4. Major Subcontractors

5. Others as appropriate

ITB No.: 26-403/DL 01200 - 2

D. Suggested Agenda:

1. Comments, corrections, or additions to the notes of the previous meeting.

2. Review of work performed since last meeting.

a. Construction

b. Deliveries

c. Subcontractors on site

d. Work force/schedule

e. OWNER’s comments

3. Contractor’s forecast or work projected.

a. Construction

b. Major deliveries

c. Subcontractors scheduled on site.

d. Work force/schedule

4. Review of contractor’s construction schedule

a. Milestones

b. Problems which may impact schedule.

c. Corrective measures

d. Critical and long-lead items

5. Submittals

6. Issues, concerns, and action items

a. Design issues

b. Permitting issues

c. Potential change orders

d. Action items

e. Other issues

7. Applications for payment and construction photos

8. Other business

a. Next meeting

1.04 PROGRESS MEETINGS:

A. Schedule regular periodic meetings. The progress meetings will be held every thirty (30) days with the first meeting thirty

(30) days after the pre-construction meeting or thirty (30) days after the date of Notice to Proceed.

B. Hold called meetings as required by progress of the Work.

C. Location of the meetings: Project field office of ENGINEER or other location designated by the OWNER.

D. Attendance:

1. OWNER or his representative

2. CONTRACTOR’s Project Manager and Superintendent

3. Subcontractors as appropriate to the agenda

4. Suppliers as appropriate to the agenda

5. Others as appropriate.

ITB No.: 26-403/DL 01200 - 3

E. Suggested Agenda:

1. Comments, corrections, or additions to the notes of the previous meeting

2. Review of work performed since last meeting.

a. Construction

b. Deliveries

c. Subcontractors on site

d. Work force/schedule

e. OWNER’s comments

3. Contractor’s forecast or work projected.

a. Construction

b. Major deliveries

c. Subcontractors scheduled on site.

d. Work force/schedule

4. Review of Contractor’s construction schedule

a. Milestones

b. Problems which may impact schedule

c. Corrective measures

d. Critical and long-lead items

5. Submittals

6. Issues, concerns, and action items

a. Design issues

b. Permitting issues

c. Potential change orders

d. Action items

e. Other issues

7. Applications for payment and construction photos

8. Other business

a. Next meeting

b. Warranties

F. The CONTRACTOR is to attend progress meetings and is to study previous meeting minutes and current agenda items, in order to be prepared to discuss pertinent topics such as deliveries of materials and equipment, progress of the Work over the past thirty (30) days, and work forecast for next thirty (30) days.

G. The CONTRACTOR is to provide a current submittal log at each progress meeting in accordance with Section 01300, and an updated construction schedule in accordance with Section 01310.

1.05 WEEKLY MEETINGS:

A. Schedule weekly construction progress meetings.

B. Attendance:

1. OWNER or his representative

2. CONTRACTOR’s Project Manager and Superintendent

3. Subcontractors as appropriate

4. Suppliers as appropriate

5. Others as appropriate

ITB No.: 26-403/DL 01200 - 4

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION (NOT USED)

END OF SECTION