20-Section 01153 - Change Order Procedures 031826.pdf

PDF 151 KB Posted

Attached to
Rehabilitation of Manholes, Sanitary Stations and Wet Wells - Phased Projects
Solicitation number
ITB No.: 26-403/DL
Issued by
Palm Beach County, Florida

About this file

This is a Section 01153 Change Order Procedures document for a Florida state and local contract opportunity (ITB No. 26-403/DL 01153) for the Rehabilitation of Manholes, Sanitary Stations and Wet Wells - Phased Projects. The proposed work includes rehabilitation of twenty-six (26) manholes, thirteen (13) Detection Stations, two (2) Pump Stations, replacement of eleven (11) Manhole Covers and Rims in Class I and Class III landfill leachate collection systems, and five (5) Sanitary Lift Stations, with work encompassing cleaning and protective coatings. The contractor must be a licensed and authorized Warren Environmental products applicator with a minimum of five (5) years' experience and shall provide all labor, materials, equipment, and incidentals required. This is a phased project with an initial two (2) year contract period and an option to renew for an additional one (1) year at the Authority's sole discretion. Bidders must submit responses electronically through Bonfire by the date and time specified in the solicitation, and all questions or clarification inquiries must be submitted through Bonfire by the deadline specified in the bid document.

The Change Order Procedures section establishes the framework for managing modifications to the contract scope. The contractor must designate authorized personnel in writing to accept changes and inform others of authorization, while the Owner will designate an authorized person to execute Change Orders and Work Change Directives (WCD). Changes may be initiated by either the Owner through a Request for Proposal or by the contractor through written notice. Documentation requirements are extensive and include detailed labor, equipment, product, and cost information; time records; receipts and invoices; and justification for any changes to Contract Time. Change Orders may be structured as lump-sum/fixed price, unit price, or time-and-material/force account arrangements, with the Owner preparing all Change Orders, Field Orders, and WCDs. The contractor must maintain detailed records, periodically revise the Schedule of Values and Construction Schedule to reflect changes, and enter pertinent changes in Project Record Documents upon completion.

View the file

Other files

File Type Posted
5-Section 01370 - Schedule of Values 031826.pdf PDF
13-Section 01200 - Project Meetings 031826.pdf PDF
9-Section 01111- Permits 031826.pdf PDF
23-MANHOLE AND WET WELL REHABILITATION RECORD DWG CDM FEB 2014 7.pdf PDF
12-Section 01310 - Progress Schedules 031826.pdf PDF
30-ITB 26-403 - Project Experience Forms.pdf PDF
2-Section 01095 - Reference Standards 031826.pdf PDF
11-Section 02767 - Monolithic Lining System 031826.pdf PDF
25-SHT C-2 - Class III Leachate Piping Site Plan.pdf PDF
24-SHT C-1 - Class I Leachate Piping Site Plan.pdf PDF
19-Section 01700 - Contract Closeout 031826.pdf PDF
8-Section 01152 - Applications for Payment 031826.pdf PDF
1-Section 01005 - General Requirements 031826.pdf PDF
22-Class I and III Leachate Collection System Details.pdf PDF
15-Section 01010 - Summary of Work 031826.pdf PDF
33-ITB 26-403 - Vendor Acknowledgement Form.pdf PDF
27-ITB 26-403 - Bid Bond.pdf PDF
29-ITB 26-403 - Insurance Requirement Checklist.pdf PDF
16-Section 01100 - Special Project Procedures 031826.pdf PDF
7-Section 01610 - Material and Equipment 031826.pdf PDF
21-Section 01110 - Environmental Protection Procedures 031826.pdf PDF
31-ITB 26-403 - Section 00300 - Bid Form - Price.pdf PDF
10-Section 01300 - Submittals 031826.pdf PDF
4-Section 01102 - Safety Health and Emerg Response Requirements 031826.pdf PDF
26-ITB 26-403 - Authority to Execute Contract.pdf PDF
6-Section 01025 - Measurement and Payment 031826.pdf PDF
18-Section 01740 - Warranties and Bonds 031826.pdf PDF
3-Section 01014 - Construction Sequence 031826.pdf PDF
14-Section 01710 - Cleaning 031826.pdf PDF
34-ITB 26-403 - Rehab of Manholes, Sanitary Stations and Wet Wells - Phased Projects.pdf PDF
28-ITB 26-403 - Bidders Qualifications Statement.pdf PDF
32-ITB 26-403 - Trench Safety Act.pdf PDF
17-Section 01041 - Project Coordination 031826.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITB No.: 26-403/DL 01153 - 1 Rehab of Manholes, Sanitary Stations and Wet Wells - Phased Projects.

SECTION 01153

CHANGE ORDER PROCEDURES

PART 1 – GENERAL

1.01 REQUIREMENTS INCLUDED:

A. The CONTRACTOR shall promptly implement change order procedures.

1. Provide full written data required to evaluate changes.

2. Maintain detailed records of work done on a time-and-material/force account basis.

3. Provide full documentation to OWNER on request.

B. Designate in writing the member of CONTRACTOR’s organization:

1. Who is authorized to accept changes in the work.

2. Who is responsible for informing others in the CONTRACTOR’s employ of the authorization of changes in the work.

C. OWNER will designate in writing the person who is authorized to execute Change Orders and Work Change Directives (WCD).

1.02 RELATED REQUIREMENTS:

A. The Contract Documents include, but are not limited to, the following related sections:

1. Agreement: The amounts of established unit prices.

2. Section 00700: General Conditions.

a. Methods of determining cost or credit to OWNER resulting from changes in Work made on a time and material basis.

b. CONTRACTOR’s claims for additional costs.

3. Section 01152: Applications for Payment

4. Section 01310: Construction Schedules

5. Section 01370: Schedule of Values

6. Section 01720: Project Record Documents

1.03 DEFINITIONS:

A. Change Order: See General Conditions

B. Work Change Directive: See General Conditions

C. Field Order: A written order to the CONTRACTOR, signed by the

OWNER and the CONTRACTOR, which is issued to interpret/clarify the Contract Documents, order minor changes in the work and/or memorialize trade-off agreements. The work described by a Field Order is to be accomplished without change to the Contract Sum, Contract Time, and/or claims for other costs.

D. Work Change Directive (WCD): See Section 00800

ITB No.: 26-403/DL 01153 - 2

1.04 PRELIMINARY PROCEDURES:

A. OWNER may initiate changes by submitting a Request for Proposal (RFP) to CONTRACTOR. Request will include:

1. Detailed description of the Change, Products, and location of the change in the Project.

2. Supplementary or revised Drawings and Specifications.

3. The projected time span for making the change, and a specific statement as to whether overtime work is, or is not, authorized.

4. A specific period of time during which the requested price will be considered valid.

5. Such request is for information only, and is not an instruction of execute the changes, nor to stop work in progress.

B. CONTRACTOR may initiate changes by submitting a written notice to OWNER containing:

1. Description of the proposed changes.

2. Statement of the reason for making the changes.

3. Statement of the effect on the Contract Sum and the Contract

Time.

4. Statement of the effect on the work of separate contractors.

5. Documentation supporting any change in Contract Sum or

Contract Time, as appropriate.

1.05 WORK CHANGE DIRECTIVE AUTHORIZATION:

A. In lieu of a Request for Proposal (RFP), OWNER may issue a Work Change Directive Authorization of CONTRACTOR to proceed with a change for subsequent inclusion in a Change Order.

B. Authorization will describe changes in the Work, both additions and deletions, with attachments of revised Contract Documents to define details of the change and will designate the method of determining any change in the Contract Sum and any change in Contract Time.

C. OWNER will sign and date the Work Change Directive Authorization as authorization for the CONTRACTOR to proceed with the changes.

D. CONTRACTOR may sign and date the Work Change Directive

Authorization to indicate agreement with the terms therein.

1.06 DOCUMENTATION OF PROPOSALS AND CLAIMS:

A. Support each quotation for a lump-sum proposal, and for each unit price which has not previously been established, with sufficient substantiating data to allow OWNER to evaluate the quotation.

ITB No.: 26-403/DL 01153 - 3

B. On request, provide additional data to support time and cost computations.

1. Labor required.

2. Equipment required.

3. Products required.

a. Recommended source of purchase and unit cost.

b. Quantities required.

4. Taxes, insurance and bonds.

5. Credit for work deleted from Contract, similarly documented.

6. Overhead and profit.

7. Justification for any change in Contract Time.

C. Support each claim for additional costs, and for work done on a time-and-material/force account basis, with documentation as required for a lump sum proposal, plus additional information.

1. Name of OWNER’s authorized agent who ordered the work, and the date of the order.

2. Dates and times work was performed, and by whom.

3. Time record, summary of hours worked, and hourly rates paid.

4. Receipts and invoices for:

a. Equipment used, listing dates and times of use.

b. Products used, listing of quantities.

c. Subcontracts

1.07 PREPARATION OF CHANGE ORDER AND FIELD ORDERS AND WORK CHANGE

DIRECTIVE (WCD):

A. OWNER will prepare each Change Order, Field Order and WCD.

B. Forms: See Section 00800 for forms.

C. Change Order will describe changes in the Work, both additions and deletions, with attachments of revised Contract Documents to define details of the change.

D. Change Order will provide an accounting of the adjustment in the

Contract Sum and in the Contract Time.

E. Field Order will describe interpretations or clarifications of

Contract Documents, approve minor changes in the Work, and/or memorialize trade-off agreements.

F. Field Order work will be accomplished without change in the

Contract Sum, Contract Time, and/or claims for other costs.

1.08 LUMP-SUM/FIXED PRICE CHANGE ORDER:

A. Content of Change Orders will be based on, either:

1. OWNER’s Proposal Request and CONTRACTOR’s responsive Proposal as mutually agreed between OWNER and CONTRACTOR.

ITB No.: 26-403/DL 01153 - 4

2. CONTRACTOR’s Proposal for a change, as recommended by OWNER.

B. OWNER will sign and date the Change Order as authorization for the CONTRACTOR to proceed with the changes.

C. CONTRACTOR will sign and date the Change Order to indicate agreement with the terms therein.

1.09 UNIT PRICE CHANGE ORDER:

A. Content of Change Orders will be based on, either:

1. OWNER’s definition of the scope of the required changes.

2. CONTRACTOR’s Proposal for a change, as recommended by OWNER.

3. Survey of complete work.

B. The amounts of the unit prices to be:

1. Those stated in the Agreement.

2. Those mutually agreed upon between OWNER and CONTRACTOR.

C. When quantities of each of the items affected by the Change

Order can be determined prior to start of the work:

1. OWNER will sign and date the Change Order as authorization for CONTRACTOR to proceed with the changes.

2. CONTRACTOR will sign and date the Change Order to indicate agreement with the terms therein.

D. When quantities of the items cannot be determined prior to start of the work:

1. The OWNER will issue a work change directive directing

CONTRACTOR to proceed with the change on the basis of unit prices and will cite the applicable unit prices.

2. At completion of the change, OWNER will determine the cost of such work based on the unit prices and quantities used.

a. CONTRACTOR shall submit documentation to establish the number of units of each item and any claims for a change in Contract Time.

3. OWNER will sign and date the Change Order to establish the change in Contract Sum and in Contract Time.

4. OWNER and CONTRACTOR will sign and date the Change Order to indicate their agreement with terms herein.

1.10 TIME AND MATERIAL/FORCE ACCOUNT CHANGE ORDER/WORK CHANGE DIRECTIVE

AUTHORIZATION:

A. The OWNER will issue a Work Change Directive Authorization directing CONTRACTOR to proceed with the changes.

B. At completion of the change, CONTRACTOR shall submit itemized accounting and supporting data as provided in the Article “Documentation of Proposals and Claims” of this Section.

ITB No.: 26-403/DL 01153 - 5

C. OWNER will determine the allowable cost of such work, as provided in General Conditions and Supplementary Conditions.

D. OWNER will sign and date the Change Order to establish the change in Contract sum and in Contract Time.

E. OWNER and CONTRACTOR will sign and date the Change Order to indicate their agreement therewith.

1.11 CORRELATION WITH CONTRACTOR’S SUBMITTALS:

A. Periodically revise Schedule of Values and Application Payment forms to record each change as a separate item of Work, and to record the adjusted Contract Sum.

B. Periodically revise the Construction Schedule to reflect each change in Contract Time.

1. Revise sub-schedules to show changes for other items of work affected by the changes.

C. Upon completion of work under a Change Order, enter pertinent changes in Project Record Documents.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION (NOT USED)

END OF SECTION