3-Section 01014 - Construction Sequence 031826.pdf
PDF 128 KB Posted
- Solicitation number
- ITB No.: 26-403/DL
- Issued by
- Palm Beach County, Florida
About this file
This is a Construction Sequence specification document for ITB No. 26-403/DL 01014, issued by a Florida authority for the Rehabilitation of Manholes, Sanitary Stations and Wet Wells - Phased Projects. The project encompasses rehabilitation of twenty-six (26) manholes, thirteen (13) Detection Stations, two (2) Pump Stations, five (5) Sanitary Lift Stations, and replacement of eleven (11) Manhole Covers and Rims within Class I and Class III landfill leachate collection systems. The work includes cleaning and protective coatings and will be performed in phases. The contract term is an initial two (2) year period with an option to renew for an additional one (1) year at the Authority's sole discretion. The contractor must be a licensed and authorized Warren Environmental products applicator with a minimum of five (5) years' experience and must provide all labor, materials, equipment, and incidentals necessary for construction as detailed in the contract documents. Bidders must submit responses electronically through Bonfire by the date and time specified in the solicitation, and the Authority will not consider responses received by other means.
The specification document establishes critical construction constraints and coordination requirements that the contractor must manage throughout the project. The contractor is required to submit a coordination schedule within ten (10) days of notice to proceed for approval by the Owner, including plans for utilizing common areas and coordinating with other on-site contractors and landfill operations. The contractor must provide forty-eight (48) hours' notice before beginning work on pump stations, manholes, or wet wells and is responsible for system shutdown, flow diversion, and bypass pump units to maintain continuous flow during rehabilitation. All debris must be disposed of at the landfill, and temporary access roads must be maintained at two-way minimum twenty (20) feet wide capacity to ensure continued access to the Class I landfill area and compost facility for all vehicles, including semi-trailer trucks, throughout the construction period. The contractor bears full responsibility for any damage to existing equipment, which must be repaired and restored to original condition or replaced at no cost to the Owner.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITB No.: 26-403/DL 01014 - 1 Rehab of Manholes, Sanitary Stations and Wet Wells - Phased Projects
SECTION 01014
CONSTRUCTION SEQUENCE
PART 1 – GENERAL
1.01 SITE CONDITIONS:
A. Several areas of construction under this Contract may need to be coordinated with other contractors doing work near the limits of construction and must be coordinated with the ongoing landfill operations of the OWNER to allow construction to be completed within the time allowed by Contract Documents.
B. CONTRACTOR is required to coordinate all activities in the interface or common areas with other contractors and/or the OWNER. CONTRACTOR must submit to the OWNER within ten (10) days after notice to proceed a description and schedule for review and approval by the OWNER as to how the common areas will be utilized, recognizing the required coordination with other contractors and/or the OWNER.
C. Where water is required in large quantity for preparational testing or other use, CONTRACTOR should make provisions with the OWNER for use of Industrial Supply Well (ISW) water.
D. During testing, CONTRACTOR should make available the manpower, equipment, and MANUFACTURER’s representatives required to make any necessary adjustments.
1.02 SUBMITTALS:
A. Schedule as specified in 01014 1.01B.
1.03 CONSTRUCTION CONSTRAINTS:
A. The following is a list of constraints which CONTRACTOR should consider in developing their overall plan of construction. This list is not intended to release CONTRACTOR from the responsibility to coordinate the work in any manner which will ensure project completion within the time allowed. The following areas are not necessarily listed in their required sequence of construction, nor is it intended to be a complete list of work items.
1. Coordination
a. CONTRACTOR shall coordinate the work with other on-site contractors (refer to Section 01100).
b. CONTRACTOR shall coordinate all work with OWNER to avoid or minimize disruption of solid waste landfilling and solid waste processing operations. CONTRACTOR shall provide OWNER forty-eight (48) hours’ notice before work begins on any pump stations, manholes/wet well.
ITB No.: 26-403/DL 01014 - 2 Rehab of Manholes, Sanitary Stations and Wet Wells - Phased Projects
c. CONTRACTOR shall coordinate with the OWNER (SWA Utilities) for system shutdown. All inverts shall be plugged and CONTRACTOR shall provide means to store/divert/pump flow until pump station or manhole rehabilitation is complete.
CONTRACTOR is responsible for removing pumps and equipment in order to perform the rehabilitation work. Any damage to existing equipment shall be repaired and restored to original condition/replaced at no cost to the OWNER.
d. CONTRACTOR shall coordinate with the OWNER (SWA Utilities) when isolating pump stations, manholes for repair. All inverts shall be plugged on the pump stations and manholes requiring rehabilitation and the flow shall be diverted from the upstream manhole to the downstream manhole.
e. CONTRACTOR shall provide by-pass pump units to isolate the manhole or pump station chamber to maintain continuous flow. (see 01041 for more details).
f. CONTRACTOR shall coordinate with the OWNER (SWA Utilities) when disposing waste water, debris and washdowns resulting from project activity. All debris resulting from the project activity shall be disposed on the landfill.
2. Access
a. Temporary access roads shall be provided in all areas where the contract work impacts existing access. The CONTRACTOR must coordinate his work with the existing landfill operations and provide temporary access roads with similar capacity and safety as existing access roads which are impacted.
b. Two-way (20 feet wide minimum) access to the Class I landfill area and to the compost facility must be maintained for all vehicles including semi-trailer trucks throughout the construction period.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION (NOT USED)
END OF SECTION