14-Section 01710 - Cleaning 031826.pdf

PDF 120 KB Posted

Attached to
Rehabilitation of Manholes, Sanitary Stations and Wet Wells - Phased Projects
Solicitation number
ITB No.: 26-403/DL
Issued by
Palm Beach County, Florida

About this file

This is a Technical Specifications document for Section 01710 - Cleaning, part of a Florida rehabilitation project for Manholes, Sanitary Stations, and Wet Wells. The overall project involves rehabilitation of twenty-six (26) manholes, thirteen (13) Detection Stations, two (2) Pump Stations, replacement of eleven (11) Manhole Covers and Rims in Class I and Class III landfill leachate collection systems, and five (5) Sanitary Lift Stations. The contractor must be a licensed and authorized Warren Environmental products applicator with a minimum of five (5) years' experience. The contract term is an initial two (2) year period with an option to renew for an additional one (1) year at the Authority's sole discretion. This is a phased project, and bidders must submit responses electronically through Bonfire by specified deadlines, with the Authority providing a designated period for bidders to submit questions and seek clarifications.

The cleaning section specifies that the contractor shall execute cleaning during construction progress and at completion of work, with daily cleaning required to maintain the site and adjacent properties free from waste materials, rubbish, and debris. The contractor must provide onsite containers for waste collection and disposal, ensure all waste materials are disposed of daily in approved onsite containers, and separate and store materials in approved areas in compliance with applicable codes, ordinances, regulations, and anti-pollution laws. Final cleaning requires skilled workmen to broom clean exterior paved surfaces and rake clean other ground surfaces, with the contractor conducting a pre-substantial completion inspection of all sight-exposed interior and exterior surfaces to verify cleanliness to the Owner's satisfaction. No Small Business Enterprise (SBE) participation is required for this solicitation.

View the file

Other files

File Type Posted
5-Section 01370 - Schedule of Values 031826.pdf PDF
20-Section 01153 - Change Order Procedures 031826.pdf PDF
13-Section 01200 - Project Meetings 031826.pdf PDF
9-Section 01111- Permits 031826.pdf PDF
23-MANHOLE AND WET WELL REHABILITATION RECORD DWG CDM FEB 2014 7.pdf PDF
12-Section 01310 - Progress Schedules 031826.pdf PDF
30-ITB 26-403 - Project Experience Forms.pdf PDF
2-Section 01095 - Reference Standards 031826.pdf PDF
11-Section 02767 - Monolithic Lining System 031826.pdf PDF
25-SHT C-2 - Class III Leachate Piping Site Plan.pdf PDF
24-SHT C-1 - Class I Leachate Piping Site Plan.pdf PDF
19-Section 01700 - Contract Closeout 031826.pdf PDF
8-Section 01152 - Applications for Payment 031826.pdf PDF
1-Section 01005 - General Requirements 031826.pdf PDF
22-Class I and III Leachate Collection System Details.pdf PDF
15-Section 01010 - Summary of Work 031826.pdf PDF
33-ITB 26-403 - Vendor Acknowledgement Form.pdf PDF
27-ITB 26-403 - Bid Bond.pdf PDF
29-ITB 26-403 - Insurance Requirement Checklist.pdf PDF
16-Section 01100 - Special Project Procedures 031826.pdf PDF
7-Section 01610 - Material and Equipment 031826.pdf PDF
21-Section 01110 - Environmental Protection Procedures 031826.pdf PDF
31-ITB 26-403 - Section 00300 - Bid Form - Price.pdf PDF
10-Section 01300 - Submittals 031826.pdf PDF
4-Section 01102 - Safety Health and Emerg Response Requirements 031826.pdf PDF
26-ITB 26-403 - Authority to Execute Contract.pdf PDF
6-Section 01025 - Measurement and Payment 031826.pdf PDF
18-Section 01740 - Warranties and Bonds 031826.pdf PDF
3-Section 01014 - Construction Sequence 031826.pdf PDF
34-ITB 26-403 - Rehab of Manholes, Sanitary Stations and Wet Wells - Phased Projects.pdf PDF
28-ITB 26-403 - Bidders Qualifications Statement.pdf PDF
32-ITB 26-403 - Trench Safety Act.pdf PDF
17-Section 01041 - Project Coordination 031826.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid No.: 26-403/DL 01710 - 1 Rehab of Manholes, Sanitary Stations & Wet Wells - Phased Projects.

SECTION 01710

CLEANING

PART 1 – GENERAL

1.01 REQUIREMENTS INCLUDED

A. Contractor shall execute cleaning, during progress of the Work, and at completion of the Work.

1.02 DISPOSAL REQUIREMENTS

A. Conduct cleaning and disposal operations to comply with codes, ordinances, regulations, and anti-pollution laws.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION

3.01 DURING CONSTRUCTION

A. Execute daily cleaning to keep the Work, the site and adjacent properties free from accumulations of waste materials, rubbish and windblown debris, resulting from construction operations.

B. Provide onsite containers for the collection of waste materials, debris and rubbish. All waste materials including containers, food debris and other miscellaneous materials must be disposed of daily in onsite containers.

C. Waste materials, debris and rubbish from the construction site shall be separated and stored on site in an approved area.

3.02 FINAL CLEANING

A. Employ skilled workmen for final cleaning.

B. Broom clean exterior paved surfaces; rake clean other surfaces of the grounds.

C. Prior to substantial completion, or OWNER acceptance, Contractor shall conduct an inspection of sight-exposed interior and exterior surfaces, and all work areas, to verify that the entire Work is clean to the satisfaction of OWNER.

END OF SECTION