14-Section 01710 - Cleaning 031826.pdf
PDF 120 KB Posted
- Solicitation number
- ITB No.: 26-403/DL
- Issued by
- Palm Beach County, Florida
About this file
This is a Technical Specifications document for Section 01710 - Cleaning, part of a Florida rehabilitation project for Manholes, Sanitary Stations, and Wet Wells. The overall project involves rehabilitation of twenty-six (26) manholes, thirteen (13) Detection Stations, two (2) Pump Stations, replacement of eleven (11) Manhole Covers and Rims in Class I and Class III landfill leachate collection systems, and five (5) Sanitary Lift Stations. The contractor must be a licensed and authorized Warren Environmental products applicator with a minimum of five (5) years' experience. The contract term is an initial two (2) year period with an option to renew for an additional one (1) year at the Authority's sole discretion. This is a phased project, and bidders must submit responses electronically through Bonfire by specified deadlines, with the Authority providing a designated period for bidders to submit questions and seek clarifications.
The cleaning section specifies that the contractor shall execute cleaning during construction progress and at completion of work, with daily cleaning required to maintain the site and adjacent properties free from waste materials, rubbish, and debris. The contractor must provide onsite containers for waste collection and disposal, ensure all waste materials are disposed of daily in approved onsite containers, and separate and store materials in approved areas in compliance with applicable codes, ordinances, regulations, and anti-pollution laws. Final cleaning requires skilled workmen to broom clean exterior paved surfaces and rake clean other ground surfaces, with the contractor conducting a pre-substantial completion inspection of all sight-exposed interior and exterior surfaces to verify cleanliness to the Owner's satisfaction. No Small Business Enterprise (SBE) participation is required for this solicitation.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid No.: 26-403/DL 01710 - 1 Rehab of Manholes, Sanitary Stations & Wet Wells - Phased Projects.
SECTION 01710
CLEANING
PART 1 – GENERAL
1.01 REQUIREMENTS INCLUDED
A. Contractor shall execute cleaning, during progress of the Work, and at completion of the Work.
1.02 DISPOSAL REQUIREMENTS
A. Conduct cleaning and disposal operations to comply with codes, ordinances, regulations, and anti-pollution laws.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION
3.01 DURING CONSTRUCTION
A. Execute daily cleaning to keep the Work, the site and adjacent properties free from accumulations of waste materials, rubbish and windblown debris, resulting from construction operations.
B. Provide onsite containers for the collection of waste materials, debris and rubbish. All waste materials including containers, food debris and other miscellaneous materials must be disposed of daily in onsite containers.
C. Waste materials, debris and rubbish from the construction site shall be separated and stored on site in an approved area.
3.02 FINAL CLEANING
A. Employ skilled workmen for final cleaning.
B. Broom clean exterior paved surfaces; rake clean other surfaces of the grounds.
C. Prior to substantial completion, or OWNER acceptance, Contractor shall conduct an inspection of sight-exposed interior and exterior surfaces, and all work areas, to verify that the entire Work is clean to the satisfaction of OWNER.
END OF SECTION