MB05 75H70125R00026 Amendment 11.pdf
PDF 576 KB Posted
- Attached to
- Pueblo Pintado Health Center Construction
- Solicitation number
- 75H70125R00026
About this file
This document is an Amendment (Number 11) to a federal solicitation for the Pueblo Pintado Health Center Construction project. The amendment extends the proposal due date from 21 March 2025 to 28 March 2025 at 5 PM MDT, updates the Davis Bacon Wage Determination, and provides responses to submitted questions. Key changes include: no additional RFIs will be accepted, Attachment J09 Wage Determination is replaced with a dated version from 03/07/2025, and answers are provided to technical questions about access control hardware devices, lagoon construction details, and site lease documentation. The questions and responses primarily address system compliance with HSPD-12 and FIPS-201-3 standards for PIV card access, confirm construction specifications, and clarify land lease arrangements with the Navajo Nation.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
A000011
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The reason for this amendment is to provide responses to questions submitted, update the Davis Bacon Wage Determination, and to extend the due date for receipt of proposals.
A. Extend the proposal due date in block 13a of the SF1442 from 21 March 2025 to 28 March 2025, 5 PM MDT.
B. No additional RFIs will be accepted or answered for this solicitation.
C. Replace Attachment J09 Wage Determination dated 01/03/2025 with J09 Wage Determination dated 03/07/2025.
D. See page 2 for list of final questions and answers.
Division of Eng. Services Seattle 701 Fifth Avenue, Suite 1600 Seattle WA 98104
See block 6
75H70125R00026
131154
1 2
03/18/2025
01/06/2025
QUESTIONS AND REPONSES
1. Description/Question: ACCESS CONTROL HARDWARE DEVICES RFI QUESTIONS:
Part 1 General,
1.01 Summary
B. Is the system going to be required to process PIV cards in accordance with HSPD‐12 and FIPS‐201‐3 when installed or will this be a potential change to compliance at a later date?
1.04 6. a. Electronic key management system, how many sets of keys are you requiring management of? This determines the size and cost of the cabinet.
Part 2 Products,
2.01 A. Proximity Reader for Card, Fob, or Smartphone.
NFC, fob and or smartphone as a credential is not compliant with HSPD‐12 and FIPS‐201‐1‐2‐3 regulations. Is there a design that requires PIV credentials for perimeter entry and then access by lesser means within the facility? Hence, PIV at the entry gate and then normal access card, fob or smartphone for access within the facility? Please provide the use case(s) A. 4.a Accessories Long‐range receiver module What is the use case? Is the plan to have a reader remotely connected to the system via radio link? Or is this for use in a handheld mustering situation? Please define the scope.
Part 3 EXECUTION
3.01 DEPLOYMENT OF CREDENTIALS
B. Third Party issuing of Access Control Credentials B.1.a Initial Issuance:
Please provide number of credentials to be produced in the initial run.
B.1.b Ongoing Issuance:
Is entity is going to use PIV credentials, in accordance with FIPS standards?
If entity is not going to use PIV credentials, then we can supply Camera, printer and badging software integrated in the solution to create access badges at the site.
Which method is intended for the site?
Response: System is intended to be PIV cards in accordance with HSPD‐12 and FIPS‐201‐3. NFC, fob and or smartphone will not be used. PIV cards will be provided by the government and are not required to be provided by the access control provided.
2. Description/Question: CG503‐confirm lagoon interior is not concrete.
Response: Lagoon interior is NOT concrete. The pattern shown in the anchor trench detail is only showing the prepared subgrade as labeled.
3. Description/Question: Is IHS providing ownership or lease documentation for this project as it relates to running electricity to the site?
Response: IHS has leases with the Navajo Nation for the site. IHS will provide the leases to the contractor after award.
File details come from the government source that posted it. Updated .