AMD 00001 TSFS Drydock 2025 Questions and Answers.pdf

PDF 155 KB Posted

Attached to
TRAINING VESSEL FREEDOM STAR(TVFS) FY25 DRY DOCK
Solicitation number
6933A225Q000001
Issued by

About this file

This is a Questions & Answers document (Amendment 0001) for the TSFS Drydock 2025 contract opportunity. The document addresses eight contractor questions regarding technical specifications and requirements for various items related to the Training Vessel Freedom Star drydock repairs.

Key clarifications include: confirmation that the Crane Diesel Operations & Maintenance Manual is onboard the vessel, specifications about window replacements with acceptable Plexiglas material, corrections to reference numbers (1427-802 instead of 1316-802), and the provision of additional documentation for Mitsubishi HVAC files. A significant clarification was made regarding Work Item 306, where MARAD indicated they would accept a weight estimate instead of a full inclining experiment for a 36,000 lb change, and provided a digital copy of the Trim and Stability Booklet. Multiple referenced files are noted as being attached to supplement the answers, including HVAC documentation, File 1547-4411, and a referenced photo for Item 225.

View the file

Other files

File Type Posted
Crane rope cert.pdf PDF
1547 4411 Rev 5 Machinery Arrgmt.pdf PDF
Tow Winch Pic 2.jpg JPG image
1547L F 54 Rev 4 Barge Towing Arr and Det.pdf PDF
Sullair Compressor Pic.jpg JPG image
1547L P72 Rev 2 Towing winch Power and controls.pdf PDF
AMD 0002 Drydock 2025 Questions and Answers 2.pdf PDF
P00002 6933A225Q000001 .pdf PDF
crane cab rough dimensions.pdf PDF
Tow Winch Pic 1.jpg JPG image
AMD0001 6933A225Q000001 .pdf PDF
Item 225 Photo.jpg JPG image
Item 226 Fassmer FRB.pdf PDF
DB Design PURY P T Y S KMU A BS MEES17K096 201802.pdf PDF
Item 225 SH PLFY P NCMU E OCH410D Parts OCB410D 1.pdf PDF
Item 226 Global Davit Catalogue 2016.pdf PDF
Item 225 DB PUHY P T Y S KMU A BS U11 E2 3.pdf PDF
FREEDOM STAR ON 629627 Trim and Stability Booklet Rev D.pdf PDF
1547 4411 Rev 5 Machinery Arrgmt.pdf PDF
1547-4701 Rev 3 Rudder Arr 3.pdf PDF
MA-57 Dry dock Report 3.pdf PDF
1547-4420 Rev 3 Bow Thruster Arr 3.pdf PDF
FREEDOM STAR ON 629627 Trim and Stability Booklet Rev D 1.pdf PDF
Stern Thruster Mechanical manual G569W G570W 32HJP 4.pdf PDF
TSFS 2023 Anchor Chain Gauging Report 2.pdf PDF
Shaft Liners 2.pdf PDF
TSFS Wartsila Tailshaft Parts 2024 1.pdf PDF
Stern Thruster 2768WG-D 32HJP SECTIONAL ARRANGEMENET 1.pdf PDF
TSFS 2023 Motor Megger Report 3.pdf PDF
Sherwin Williams Coating Spec 04-12-2024 2.pdf PDF
1316-901 Kings Pointer Docking Plan 3.pdf PDF
FREEDOM STAR MEGGER READINGS blank 1.docx DOCX document
2018 Bow Thruster Maintenance - Final Service Report 1.pdf PDF
1780-4419 Stern Thruster Compt Arrangement1of1 3.pdf PDF
TV KINGS POINTER Docking Calculations 2.pdf PDF
Crane Diesel Manual 1.pdf PDF
TSFS FY25 CSS 6933A225Q000001 FINAL.pdf PDF
1547-1420 Docking Plan 3.pdf PDF
1547-2510 Rev 7 Long l Struct Sections 3.pdf PDF
Sullair ES6 2.pdf PDF
1547-4801 Rev 4 Shafting Arr and Det 2.pdf PDF
2020 Bow Thruster Maintenance Report 1.pdf PDF
ABS Rules Part 7 Chapter 6 4.pdf PDF
TSFS 2023 Anode Locations 2.pdf PDF
TS FREEDOM STAR - Signed CFR 014 Tailshaft Bearing Clearances WI 202 1.pdf PDF
2023 Freedom Star Gauge Calibration List 1.xls XLS spreadsheet
4163B-M20 Bow Thruster Arrangement Omega OCP-400 1.pdf PDF
TSFS Gauge Calibration Final Report 2023 1.pdf PDF
Attmt II TSFS VENDOR PRICE SHEET (SECTION B) .xlsx XLSX spreadsheet
ABS Rules Part 7 Chapter 5 Sections 1 and 2 3.pdf PDF
Show 40 more

Latest 50 of 71 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TSFS Drydock 2025 Questions & Answers

Amendment 0001

1. ITEM 220 – NO REF. RECEIVED Crane Diesel Ops & Maintenance Manual. Onboard vessel

2. ITEM 220 – 5-1 IS IT THE INTENT TO REPLACE EXSISTING WINDOWS WITH A NEW CONSTRUTION

WINDOW, BOLT IN W /SHATTER PROOF GLASS? THERE ARE NO SIZES OR A COUNT OF

WINDOWS. REF. PROVIDED, HAS NO INFO ON THAT. Do you have an example? Please provide any additional information that is available. The sizes are: and Plexiglas is an acceptable window material

3. ITEM 223 – NO REF. RECEIVED 1316-802. 1427-802 is the correct reference, see attached.

4. ITEM 225 – NO REF. RECEIVED See three attached Mitsubishi HVAC files.

5. ITEM 226 – NO REF. RECEIVED See two attached files.

6. ITEM 307 – NO REF. RECEIVED 1547-4411 File 1547-4411 attached.

7. WI 306 -- Would MARAD consider a weight estimate and corrected light ship vice a full inclining experiment? As per our engineering subcontractor, a full inclining experiment is generally not required for a 36,000 lb change. If an inclining experiment is required, can MARAD provide the original modeling done in GHS? Is the conditions booklet in an electronic form so edits can be made rather than creating something new? If neither of these is available, please provide a lines plan and structural plans detailing the exact extents of the tanks in the boat and a copy of the stability test report. MARAD would consider a weight estimate vice a full inclining experiment.

Also attached digital copy of the Trim and Stability Booklet.

8. ITEM 225 – Paragraph 5 references a photo attached. Can you please provide the photo? Photo Attached