6-6. IFB 043-26-RM SPECIAL PROVISIONS Pump Station 182 Redundant Power SPECIAL PROVISIONS.docx
DOCX document 18 KB Posted
- Attached to
- Re-Bid Pump Station 182 Redundant Power
- Solicitation number
- IFB-043-26-RM
- Issued by
- Leon County, Florida
About this file
This is a Special Provisions document for Invitation for Bid (IFB) 043-26-RM issued by the City of Tallahassee for the Pump Station 182 Redundant Power Project in Florida. The project involves construction of a redundant underground power supply from the City of Tallahassee Electric Department's distribution system to Pump Station 182. The Contractor's scope of work includes supplying and installing two 4-inch electrical conduits via horizontal directional drilling from an existing termination cabinet on Engineering Way to Pump Station 182, installing termination cabinets along the conduit route, coordinating with the Electric Utility for transformer and primary conductor installation, and supplying and installing a Main Breaker (2000 amps) and Automatic Transfer Switch with associated conduit and cable work. The project is subject to multiple permits already secured by the City, including a City Underground Utilities General Utility Permit (TEM 220057), Permit to Work in the Right Of Way (ROW2022-155), and FDOT Utility Permit (2023-H-392-00029), all of which bidders must examine, understand, and comply with during execution.
Construction operations are restricted to 7:30 a.m. to 7:00 p.m. Monday through Friday and 8:00 a.m. to 6:00 p.m. on Saturday, with no work permitted on Sundays or Saturdays if operations would disrupt water, sewer, gas, or electric services. The Contractor is solely responsible for identifying and pre-approving offsite staging areas through the City's Growth Management Department and for all associated leasing, restoration, and traffic control costs. Bidders must document existing deficiencies at staging areas with photographs prior to construction; failure to do so may require the Contractor to correct deficiencies at no additional cost to the City. The City reserves the right to modify work and lane closure hours at any time without additional compensation to the Contractor, though time extensions may be granted for delays caused by the City's decisions.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL PROVISIONS
I. PERMITS
The following permit(s) have been secured by the City (unless otherwise noted) and apply to this Contract.
1. NPDES Permit (Not Required, Not Provided by COT).
2. City of Tallahassee Underground Utilities - General Utility Permit, (Appendix A, TEM 220057)
3. City of Tallahassee, Permit to Work in the Right Of Way Permit, (Appendix B, ROW2022-155)
4. FDOT, Utility Permit, (Appendix C, 2023-H-392-00029) Bidders shall examine the permits, review and understand all permit conditions, and abide by same during execution of the work, and anticipate all costs associated with doing so. No claims for project delays or unanticipated work associated with those tasks will be considered.
In addition to the permit conditions, bidders are advised that the Contractor will be solely responsible for determining what, if any, offsite staging areas will be used, and shall be responsible to the owner of such areas regarding leasing, restoration, traffic control, etc. All staging areas to be used must be pre-approved by the City’s Growth Management Department prior to their use.
The Contractor shall abide by these requirements before final payment will be released. Photographs of deficient areas existing prior to construction shall be produced by the Contractor to document such deficiencies. Otherwise, the Contractor may be required to correct such deficiencies as part of the restoration work at no extra cost to the City.
Appendices A-C on Bonfire
II. ELECTRICAL SPECIFICATIONS
The attached “Electrical Specifications for Pump Station 182 Redundant Power,” “City of Tallahassee Gas & Electric Operations General Construction Specifications” and “Specifications for the Installation of Conduits and Electrical Equipment for Power Delivery” shall be considered the governing specifications for the work of this contract. For items of work not addressed by these specifications, the City of Tallahassee Technical Specifications for Water and Sewer Construction, the FDOT Stand Specifications or City of Tallahassee Supplemental Specifications shall govern, as applicable.
1. Electrical Specifications for Pump Station 182 Redundant Power (Appendix D)
2. City of Tallahassee Gas & Electric Operations General Construction Specifications (Appendix E)
3. Specifications for the Installation of Conduits and Electrical Equipment for Power Delivery (Appendix F) Appendices D-F on Bonfire
III. PROSECUTION AND PROGRESS
Subarticle 8-3.4 of the Standard Specifications is expanded by the following:
All construction operations shall be scheduled to begin no earlier than 7:30 am and to end no later than 7:00 pm Monday through Friday, and to begin no earlier than 8:00 am and to end no later than 6:00 pm on Saturday. No construction operations are to be scheduled on Sundays. No construction operations are to be scheduled on Saturdays if construction would cause a disturbance to water, sewer, gas, or electric services.
The City reserves the right to limit the Contractor’s work and/or lane closure hours at any time during the project duration from those hours identified within these documents. The Contractor agrees to make no claim for additional compensation as a result of this decision by the City. However, the Contractor may be entitled to an extension of time for such acts by the City, only for the number of days which the City determines to be due to such acts.