About this file

This is a Required Bid Schedule for the City of Tallahassee's Pump Station 182 Redundant Power project, an Invitation for Bid (IFB 043-26-RM) for general construction and electrical work. The project involves constructing a redundant underground power supply from the City of Tallahassee Electric Department's distribution system to Pump Station 182. The Contractor's scope includes supply and installation of two 4-inch electrical conduits via horizontal directional drilling from Engineering Way to the pump station, coordination with the Electric Utility for transformer and primary conductor installation, supply and installation of a 2000-amp Main Breaker, installation of an Automatic Transfer Switch (ATS), and associated conduit and cable work. The bid schedule contains 13 line items structured as lump sum components, including mobilization, erosion and sedimentation control, permitting fees, conduit and termination cabinet installation, transformer connection work, main breaker installation, ATS installation, wiring connections, and start-up and testing.

Bidders must provide labor, material, and fees costs for each line item. Measurement and payment terms vary by item: Items 1 and 2 follow the City of Tallahassee's Pay Item Manual for Water and Sewer Construction; Item 3 (permitting fees) is paid 50 percent upon approved permit and 50 percent upon certificate of completion; and Items 4 through 12 are paid incrementally with materials valued at 25 percent each upon submittal acceptance, site delivery, installation, and final acceptance, while labor is paid 50 percent upon complete installation and 50 percent upon inspection and acceptance. Item 13 (start-up and testing) is paid 100 percent upon completion and Owner acceptance. The bid schedule notes that grounding, as-built drawings, GPS data, record drawings, and site restoration are incidental to other items with costs included in respective bid items and no separate payment provided.

View the file

Other files

File Type Posted
32-APPENDIX G - Pump Station 182 Redundant Power - Survey SS.pdf PDF
31-APPENDIX F - COT Specifications for Installation of Conduits and Electrical Equipment for Power Delivery.pdf PDF
4-4. REQUIRED DEBARMENT CERTIFICATION Attachment H - HMGP GRANT 4399-081-A.pdf PDF
8-8. IFB 043-26-RM GENERAL PROVISIONS Pump Station 182 Redundant Power .pdf PDF
17-APPENDIX B - Pump Station 182 Redundant Power - COT Right of Way Permit.pdf PDF
19-APPENDIX D - Pump Station 182 Redundant Power Electrical Specifications.pdf PDF
18-APPENDIX C - Pump Station182 Redundant Power - FDOT Approved Utility Permit Package.pdf PDF
5-5. IFB 043-26-RM SUPPLEMENTAL SPECIFICATIONS .pdf PDF
14-14. REQUIRED HUMAN TRAFFICKING AFFIDAVIT.pdf PDF
33-APPENDIX H - COT Transformer Specifications.pdf PDF
6-6. IFB 043-26-RM SPECIAL PROVISIONS Pump Station 182 Redundant Power SPECIAL PROVISIONS.docx DOCX document
16-APPENDIX A - COT Environmental Management General Permit (TEM220057).pdf PDF
11-11. REQUIRED Non Collusion Affidavit of Respondent.docx DOCX document
20-APPENDIX E - COT Gas and Electric General Construction Specifications.pdf PDF
21-APPENDIX F - COT Specifications for Installation of Conduits and Electrical Equipment for Power Delivery.pdf PDF
7-7. IFB 043-26-RM PS-12-182 PLANS Redundant Power - Final Plans SS.pdf PDF
23-APPENDIX H - COT Transformer Specifications.pdf PDF
13-13. DRAFT CONTRACT CONSTRUCTION (from IFB) 1.2024.doc DOC document
25-15. IFB 043-26-RM SUPPLEMENTAL INFORMATION.docx DOCX document
9-9. REQUIRED Responsible Vendor Review Form.docx DOCX document
34-APPENDIX I - WEG TRANSFORMER DATA SHEETS.pdf PDF
22-APPENDIX G - Pump Station 182 Redundant Power - Survey SS.pdf PDF
15-15. IFB 043-26-RM SUPPLEMENTAL INFORMATION.docx DOCX document
28-APPENDIX C - Pump Station182 Redundant Power - FDOT Approved Utility Permit Package.pdf PDF
10-10. REQUIRED Vendor Conflict of Interest.docx DOCX document
27-APPENDIX B - Pump Station 182 Redundant Power - COT Right of Way Permit.pdf PDF
29-APPENDIX D - Pump Station 182 Redundant Power Electrical Specifications.pdf PDF
24-APPENDIX I - WEG TRANSFORMER DATA SHEETS.pdf PDF
1-2. REQUIRED Performance and Bid Bond Trench Safety Act Form.docx DOCX document
26-APPENDIX A - COT Environmental Management General Permit (TEM220057).pdf PDF
12-12. REQUIRED IFB Representations Certifications.docx DOCX document
2-1. REQUIRED IFB 043-26-RM section 123 Pump Station 182 Redundant Power.docx DOCX document
30-APPENDIX E - COT Gas and Electric General Construction Specifications.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

BID ITEM NO.ITEM DESCRIPTIONQUANTITYUNIT MEASURELABOR UNIT COSTMATERIAL UNIT COSTFEES UNIT COSTTOTAL COST
PUMP STATION 182 REDUNDANT POWER
GENERAL CONTRACT ITEMS
1MOBILIZATION1LS$ - 0$ - 0$ - 0
2EROSION & SEDIMENTATION CONTROL1LS$ - 0$ - 0$ - 0
3PERMITTING FEES1LS$ - 0$ - 0
15KV CIRCUIT FROM ENGINEERING WAY TO PS-182
4CONDUIT AND TERMINATION CABINET INSTALLATION1LS$ - 0$ - 0$ - 0
REDUNDANT 480V SERVICE - PADMOUNTED TRANSFORMER TO NEW MAIN
5U/G TO CT ENCLOSURE (SUPPLY AND INSTALL CONDUIT AND WIRING FROM TRANSFORMER TO MAIN BREAKER)1LS$ - 0$ - 0$ - 0
6SUPPLY AND INSTALL CT ENCLOSURE (COORDINATE WITH COT ELECTRIC)1LS$ - 0$ - 0$ - 0
7CONNECTION TO NEW MAIN BREAKER (2000 A)1LS$ - 0$ - 0$ - 0
8CONNECTION TO NEW MAIN-TO-MAIN ATS1LS$ - 0$ - 0$ - 0
MAIN BREAKER (2000 AMP)
9SUPPLY AND INSTALL MAIN BREAKER1LS$ - 0$ - 0$ - 0
10SUPPLY AND INSTALL CONDUIT AND WIRING FROM MAIN BREAKER TO MAIN-TO-MAIN1LS$ - 0$ - 0$ - 0
MAIN-TO-MAIN ATS TO EXISTING GENERATOR ATS
11SUPPLY AND INSTALL ATS1LS$ - 0$ - 0$ - 0
12WIRING FROM LOAD CONNECTION ON MAIN-TO-MAIN ATS TO GENERATOR ATS1LS$ - 0$ - 0$ - 0
13START-UP AND TESTING1LS$ - 0$ - 0$ - 0
TOTAL BASE BID$ - 0
NOTES:1. The Fees Unit Cost is only applicable to Item 3. Permit Fees. All other bid items should be split into lump sum labor and material costs.
2. Measurement and Payment for Items 1 and 2 shall be in accordance with the City of Tallahassee's Pay Item Manual for Water and Sewer Construction, 2018
3. Item 3 is for payment of permitting fees for building/electrical construction permits, staging area permits, or other permits through the City of Tallahassee's Growth
Management or other permitting agency, as required. Measurement and payment for Item 3 shall be 50% for Approved permit and the remaining 50% for Certificate of
completion.
4. Grounding, as specified in Appendix D - Pump Station 182 Redundant Power Electrical Specifications, is incidental to other items of work. No separate bid item is
provided for grounding, and the cost of labor, materials, and equipment needed to provide the specified grounding should be included in other bid items.
5. As-built Drawings, GPS Data and Record drawings shall be provided per the Plans, per Appendix E, Section A-21 and per Appendix D, Section 16010(1.5) and are
incidental to other items of work. No separate bid item is provided, and the cost of producing acceptable as-built drawings, GPS Data and Record Drawings should be
included in other bid items.
6. Restoration of grassed areas with sod to match existing is part of the Contractor's work and is incidental to other items of work. No separate payment will be
made for seed or sod, and the cost to restore bore pits and other areas disturbed by the Contractor shall be included in other bid items.
7. For Bid Items 4-12, refer to Appendix D - Pump Station 182 Redundant Power Electrical Specification and accompanying Scope of Supply - Division of Responsibility for
specific items of work to be paid under each item. Measurement and Payment for the materials for these items shall be 25% upon acceptance of submittals, 25% upon
delivery of the materials to the site, 25% for installation of the materials, and 25% after inspection and acceptance of installed materials. Measurement and payment
for the labor for these items shall be 50% for complete installation and 50% for complete installations that have been inspected and accepted.
8. Refer to Appendix D - Pump Station 182 Redundant Power Electrical Specification and accompanying Scope of Supply - Division of Responsibility, Section16010(1.3.3) for
elaboration of work related to Bid Item 13. Measurement and payment for this item shall be 100% upon completion of the work and acceptance by the Owner, including
submission of all close-out documentation.