590-20-903 IFB_Specs.pdf

PDF 9 MB Posted

Attached to
Y1DZ--Correct FCA Deficiencies Steam 590-20-903 Distribution System
Solicitation number
36C24624R0045
Issued by

About this file

This document package includes specifications for a federal construction contract opportunity with the Department of Veterans Affairs to correct deficiencies in the steam distribution system at the Hampton VA Medical Center in Hampton, Virginia. The project scope involves replacing approximately 1,250 feet of return steam piping located in underground tunnels and within Building 110, along with removing and replacing various mechanical equipment. Bidders must submit responses by November 14, 2023, and the construction period is estimated at 550 calendar days following award.

View the file

Other files

File Type Posted
36C24624R0045 0013.docx DOCX document
59020903_Addendum_2_08082024 AMEND 0012.pdf PDF
36C24624R0045 0012.docx DOCX document
20240628_SteamT Investigation_AMcD.pdf PDF
36C24624R0045 0011.docx DOCX document
36C24624R0045 0010.docx DOCX document
RFI 011 for Mech work.pdf PDF
36C24624R0045 0009.docx DOCX document
36C24624R0045 0008.docx DOCX document
Attach 1 RFI 009 - CO comments Amend 0008.pdf PDF
RFI 010 a Amend 0008.pdf PDF
Attachment I - RFI 010.pdf PDF
Attachment J - 59020903_Addendum_1_05302024_W RFI10.pdf PDF
36C24624R0045 0007.docx DOCX document
Attach 1 RFI 009 - Revision 3 - BAE Response_Redacted.pdf PDF
36C24624R0045 0006.docx DOCX document
Attach 2 RFI 009 Specification Appendix 2.pdf PDF
ATTENDANCE LOG - PRE PROPOSAL SITE VISIT Steam.pdf PDF
36C24624R0045 0005.docx DOCX document
BAE Response - RFI 005 04.12.24_Redacted.pdf PDF
BAE Response - RFI 007 04.12.24_Redacted.pdf PDF
BAE Response - RFI 008 04.15.24_Redacted.pdf PDF
36C24624R0045 0004.docx DOCX document
BAE Field Report additional photos Part 3.pdf PDF
Attachment J - Bonding Information.docx DOCX document
BAE Field Report additional photos Part 1.pdf PDF
BAE Field Report additional photos Part 4.pdf PDF
36C24624R0045 0003.docx DOCX document
BAE Field Report additional photos Part 2.pdf PDF
Portion of BOD.pdf PDF
20240315_M001.pdf PDF
36C24624R0045 0002.docx DOCX document
20240315_A102_N.pdf PDF
36C24624R0045 0001.docx DOCX document
Attachment B - Corp Experience Form.docx DOCX document
Attachment D - EMR Certification Form 2024.docx DOCX document
Attachment C - Past Performance Questionnaire.docx DOCX document
Attachment E - RFI Form R0045.doc DOC document
Attachment F - Cost Breakdown with Schedule of Values.xlsx XLSX spreadsheet
Attachment H - Boiler Plant and Site Visit.pdf PDF
590-20-903_Dwg Pkg.pdf PDF
Appendix E_Hampton-Asb LBD Report.pdf PDF
Attachment G - Contractor Training Requirements 590-20-903_11-2-2023.pdf PDF
Attachment I - Construction Safety Pamphlet for Dist.pdf PDF
Attachment A - Wage Determination VA20240022 Mod 1 Dated 02232024.pdf PDF
36C24624R0045_RFP.docx DOCX document
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Specifications

Hampton Veterans Affairs

Medical Center

100 Emancipation Drive, Hampton VA 23667

Correct FCA Deficiencies Steam Distribution System

VA Project No. 590-20-903

VA Contract No. 36C24622C0070

Bancroft-AE Project No. 22-118

Divisions 00-33

CONSTRUCTION DOCUMENTS

November 14, 2023

Hampton Veterans Affairs Medical Center

Hampton, Virginia 23667

Bancroft Architects + Engineers

12-01-22

Contract No. 36C24622C0070

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 00 01 10-1

Table of Contents

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 10 Table of Contents 12-22

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-21

01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build) 11-21

01 33 23 Shop Drawings, Product Data, and Samples 09-22

01 33 24 Electronic Submittal Procedures (Web-based Service) 01-21

01 35 26 Safety Requirements 10-22

01 42 19 Reference Standards 11-20

01 45 00 Quality Control 02-21

01 45 29 Testing Laboratory Services 11-18

01 57 19 Temporary Environmental Controls 01-21

01 58 16 Temporary Interior Signage 07-15

01 74 19 Construction Waste Management 04-22

01 81 13 Sustainable Construction Requirements 10-17

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

02 83 33.13 Lead-Based Paint Removal and Disposal 01-21

DIVISION 03 – CONCRETE

03 30 53 (Short-Form) Cast-in-Place Concrete 01-21

DIVISION 04 – MASONRY (NOT USED)

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 11-18

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES (NOT USED)

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 00 01 10-2

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 84 00 Firestopping 01-21

07 92 00 Joint Sealants 04-22

DIVISION 08 – OPENINGS (NOT USED)

DIVISION 09 – FINISHES

09 91 00 Painting 01-21

DIVISION 10 – SPECIALTIES (NOT USED)

DIVISION 11 – EQUIPMENT (NOT USED)

DIVISION 12 – FURNISHINGS (NOT USED)

DIVISION 13 - SPECIAL CONSTRUCTION (NOT USED)

DIVISION 14– CONVEYING EQUIPEMENT (NOT USED)

DIVISION 21- FIRE SUPPRESSION (NOT USED)

DIVISION 22 – PLUMBING (NOT USED)

22 05 11 Common Work Results for Plumbing 12-22

22 05 23 General-Duty Valves for Plumbing Piping 09-20

22 07 11 Plumbing Insulation 09-19

22 11 00 Facility Water Distribution 05-21

22 40 00 Plumbing Fixtures 12-22

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 10 Common Work Results for Boiler Plant and Steam

Generation

04-20

23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment

02-20

23 05 51 Noise and Vibration Control for Boiler Plant 03-22

23 07 11 HVAC and Boiler Plant Insulation 02-20

23 08 00 Commissioning of HVAC Systems 04-22

23 08 11 Demonstrations and Tests for Boiler Plant 04-20

23 09 11 Instrumentation and Control for Boiler Plant 03-22

23 09 23 Direct-Digital Control System for HVAC 09-11

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 00 01 10-3

23 10 00 Facility Fuel Systems 04-20

23 21 11 Boiler Plant Piping Systems 09-22

23 21 13 Hydronic Piping 02-20

23 21 23 Hydronic Pumps 02-20 23 22 13 Steam and Condensate Heating Piping 10-22

23 22 23 Steam Condensate Pumps 04-20

23 25 00 HVAC Water Treatment 02-20

23 50 11 Boiler Plant Mechanical Equipment 03-22

DIVISION 25 – INTEGRATED AUTOMATION (NOT USED)

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 11-22

26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22

26 05 26 Grounding and Bonding for Electrical Systems 11-22

26 24 16 Panelboards 11-22

26 27 26 Wiring Devices 11-22

26 29 11 Motor Controllers 11-22

26 29 21 Enclosed Switches and Circuit Breakers 11-22

26 43 13 Surge Protective Devices 11-22

DIVISION 27 – COMMUNICATIONS (NOT USED)

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY (NOT USED)

DIVISION 31 – EARTHWORK

31 20 11 Earthwork (Short Form) 10-12

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 90 00 Planting

DIVISION 33 – UTILITIES

33 63 00 Steam Energy Distribution 09-17

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 00 01 10-4

DIVISION 34 – TRANSPORTATION (NOT USED)

DIVISION 48 – Electrical Power Generation (NOT USED)

APPENDIX 1 – Hampton-Asb LBD Report

Hampton VA Medical Center

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

05-01-20

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023

00 01 15 - 1

`SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

00-GENERAL

G001 GENERAL - COVER SHEET

G002 GENERAL - SHEET INDEX

GI001 GENERAL - CONTRACTOR AND BOD PROTOCOL NOTES

GI002 GENERAL - PROTECTION PROTOCOL, SCOPE OF WORK AND MISC.

NOTES

GC100 GENERAL – OVERALL SITE PLAN

02-STRUCTURAL

S200 STRUCTURAL - BLDG. 110 - FLOOR PLAN - BASEMENT

S201 STRUCTURAL - BLDG. 15 - FLOOR PLAN

S202 STRUCTURAL - BLDG. 15 - SECOND FLOOR PLAN

S300

STRUCTURAL - SECTION AT STEAM TUNNEL @ BLACK AVE AND

MCCLELLAN AVE

S301

STRUCTURAL - SECTION AT STEAM TUNNEL @ BLACK AVE AND

MCCLELLAN AVE

S302

STRUCTURAL - SECTION AT STEAM TUNNEL @ BLACK AVE AND

MCCLELLAN AVE

03-ARCHITECTURAL

A000 ARCHITECTURAL - ABBREV. & SYMBOL LEGENDS

AD100 ARCHITECTURAL - DEMOLITION SITE PLAN - STEAM TUNNEL

AD201 ARCHITECTURAL - SECTIONS

B15-AD101 ARCHITECTURAL - BLDG 15 - DEMOLITION FLOOR PLANS

B15-AD102 ARCHITECTURAL - DEMOLITION PLAN - OUTDOOR FUEL TANKS

B110-AD101 ARCHITECTURAL - BLDG 110 - DEMOLITION PLANS – BASEMENT

AREA 1 & 2

B110-AD102 ARCHITECTURAL - BLDG 110 - DEMOLITION PLANS – BASEMENT

AREA 3

B15-A101 ARCHITECTURAL - BLDG 15 - FLOOR PLANS

B15-A102 ARCHITECTURAL - FLOOR PLAN - OUTDOOR FUEL TANKS

B110-A101 ARCHITECTURAL - BLDG 110 - FLOOR PLAN – BASEMENT AREA 1 &

B110-A102 ARCHITECTURAL - BLDG 110 - FLOOR PLAN - AREA 3

09-MECHANICAL

M001 MECHANICAL - GENERAL NOTES, SYMBOLS AND ABBREVIATIONS

MD100 MECHANICAL - SITE PLAN OVERALL - DEMOLITION

B15-MD101 MECHANICAL - BLDG. 15 - DEMOLITION - FLOOR PLANS

B15-MD102 MECHANICAL - BLDG. 15 - DEMOLITION - OUTDOOR FUEL TANKS

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

05-01-20

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023

00 01 15 - 2

B15-MD401 MECHANICAL - BLDG. 15 - DEMOLITION - ENLARGED PLANS

B110-MD101 MECHANICAL - BLDG. 110 - DEMOLITION - FLOOR PLAN

B110-MD102 MECHANICAL – BLDG. 110 – DEMOLITION – CRAWL SPACE PLAN

MD301 MECHANICAL - BOILER CONDENSATE PIIPING RISER DIAGRAM -

DEMOLITION

MD302 MECHANICAL - FUEL OIL RISER DIAGRAM - DEMOLITION

M100 MECHANICAL - SITE PLAN OVERALL - NEW WORK

M101 MECHANICAL - SITE PLAN AREA A - NEW WORK

M102 MECHANICAL - SITE PLAN AREA B - NEW WORK

M103 MECHANICAL - SITE PLAN AREA C - NEW WORK

M104 MECHANICAL - SITE PLAN AREA D - NEW WORK

M100T MECHANICAL - SITE PLAN OVERALL - PHASING

B15-M101 MECHANICAL - BLDG. 15 - FLOOR PLANS

B15-M102 MECHANICAL - BLDG. 15 - OUTDOOR FUEL TANKS

B15-M401 MECHANICAL - BLDG. 15 - ENLARGED PLANS

M-B110-101 MECHANICAL - BLDG. 110 - FLOOR PLAN

M301 MECHANICAL - BOILER CONDENSATE PIPING RISER DIAGRAM - NEW

WORK

M501 MECHANICAL - DETAILS

M502 MECHANICAL - DETAILS

M503 MECHANICAL - DETAILS

10-ELECTRICAL

E001 ELECTRICAL - GENERAL NOTES

E002 ELECTRICAL - SYMBOLS AND ABBREVIATIONS

B15-EPD100 ELECTRICAL - POWER DEMOLITION PLAN - BLDG. 15 - BASEMENT

B15-EPD101 ELECTRICAL - POWER DEMOLITION PLAN - BLDG. 15 - FIRST

FLOOR

ED501 ELECTRICAL - DEMOLITION SINGLE LINE DIAGRAM

B15-EP100 ELECTRICAL - POWER PLAN - BLDG. 15 - BASEMENT

B15-EP101 ELECTRICAL - POWER PLAN - BLDG. 15 - FIRST FLOOR

EPT100 ELECTRICAL - POWER PLAN - TEMP. BOILERS

E501 ELECTRICAL - SINGLE LINE DIAGRAM

- - - END - - -

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

05-01-20

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023

00 01 15 - 3

DIVISION 01

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -1

SECTION 01 00 00

GENERAL REQUIREMENTS

GENERAL

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations and furnish labor and materials and perform work for the demolition and replacement of return steam piping, removal and replacement of mechanical equipment, repair of exterior fuel tanks, new piping support assemblies, and repairs to and replacement of concrete equipment pads as required by the drawings and specifications.

B. Visits to the site by Bidders may be made only by appointment with the Medical Center Engineering Officer.

C. Offices of Bancroft Architects + Engineers (BAE), as

Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: BASE BID: Scope of Work includes vacuum/gravity/pumped steam condensate return piping replacement located in steam tunnels from the Boiler plant, building 15 on

Harris Avenue, east underneath Black Avenue, north underneath

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -2

McClellan Avenue to the north end of the tunnel Chapel Building

48, which is approximately 1,250 ft. in length. Steam piping replacement within Building 110/110A/110B crawlspace continuing north from Building 110 Basement level mechanical room to the northern wall of Building 110B Steam piping replacement includes the removal, replacement and installation of new pipe supports, guides and anchors within the tunnel. Scope of work includes replacement of the following equipment within Building 15 and

Building 110 basement level mechanical room: condensate transfer pump replacement and repairs to associated piping and valves, fuel oil pump set replacement and repairs to associated piping and valves, fuel oil tank repairs, encapsulation and preservation, fuel oil piping, blowoff tank replacement, backup boiler feedwater pump replacement and motive pump replacement and associated condensate return piping within Building 110 basement level mechanical room. Work includes general construction, alterations as required to accommodate the above, repairs to and

/ or replacement of concrete equipment pads and certain other, necessary items related to the above. Construction period services are 550 calendar days from construction award date.

B. ALTERNATE NO.1 (ALT-1): BASE BID except demolition and replacement of return steam piping continuing north from Building

110 Basement Level mechanical room to the northern wall of

Building 110B (approx. 300’). Work includes the replacement of associated structural supports, fasteners, valves and connecters as necessary. Work within Building 110 Basement level mechanical room is not included in BID ALTERNATE NO. 1 (ALT-1). Construction period services are 550 calendar days from construction award date.

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -3

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at

Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without the appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. After award, General Contractor shall contact Contraction

Officers Representative (COR) and request badging forms and training instructions. At a minimum, the Site Superintendent and Quality Control Manager shall undergo fingerprinting / background checks prior to starting work.

3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the

Contracting Officer.

C. Key Control:

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -4

The General Contractor shall provide duplicate keys and lock combinations to the Contracting Officer’s Representative (COR) for the purpose of security inspections of every area of project including toolboxes and parked machines and take any emergency action.

D. Document Control:

1. Before starting any work, the General Contractor/Sub

Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for the safekeeping of all drawings, project manual and other project information.

This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or

“Sensitive Unclassified”. Secure such information in separate containers and limit access to only those who will need it for the project. Return the information to the Contracting

Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of

Contracting Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the

VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in a specified location following VA standards and procedures using an

Engineering Document Management Software (EDMS).

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -5

Security, access and maintenance of all project drawings, both scanned and electronic, shall be performed and tracked through the EDMS system.

“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted

24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. No onsite parking is available to contractors. They may be able to park in Hampton University lot along Martin Luter King

Drive. The Superintendent may park in a lot on the west end of the VA facility. Contractor to coordinate with the VA Medical

Center COR or Facility Manager.

1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the

Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the

Contractor at its expense upon completion of the work. With the

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -6 written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the

Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the

Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. Working space and space available for storing materials shall be as determined by the COR.

E. Workers are subject to rules of Medical Center applicable to their conduct.

F. Execute work in such a manner as to interfere as little as possible with work being done by others.

G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Provide unobstructed access to Medical Center areas required to remain in operation.

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -7

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR .

All such actions shall be coordinated with the COR or Utility

Company involved:

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

I. Phasing:

1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:

2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the

Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -8 of starting work in each specific area of site, building or portion thereof.

J. Building 110, 110A, 110B and Building 15 will be occupied during performance of work. Areas adjacent to the work area will also be occupied by Medical Center Personnel.

1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical

Centers operations will not be hindered. Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access. Coordinate alteration work in areas occupied by

Department of Veterans Affairs so that Medical Center operations will continue during the construction period.

2. Immediate areas of alterations not mentioned in preceding

Subparagraph 1 will be temporarily vacated while alterations are performed.

K. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m

(seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum

375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR.

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -9

L. When a building and/or construction site is turned over to

Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C

(40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company

(Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.

M. Utilities Services: Maintain existing utility services for

Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval through the

COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan and the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS for additional requirements.

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -10

2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical

Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

N. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

O. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -11

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

P. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF

ROADWAYS.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply

Service, of buildings and areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by all three, to the Contracting

Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of the COR, to be in such condition that their use is

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -12 impossible or impractical, shall be furnished and/or replaced by

Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled

"DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR

52.243-4).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by

Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -13 protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are noted on drawings or in specifications. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

a) Copies of the following listed CFR titles may be obtained from the Government Printing Office:

40 CFR 261 ...... Identification and Listing of Hazardous

Waste

40 CFR 262 ...... Standards Applicable to Generators of

Hazardous Waste

40 CFR 263 ...... Standards Applicable to Transporters of

Hazardous Waste

40 CFR 761 ...... PCB Manufacturing, Processing, Distribution in Commerce, and use Prohibitions

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -14

49 CFR 172 ...... Hazardous Material tables and Hazardous

Material Communications Regulations

49 CFR 173 ...... Shippers - General Requirements for

Shipments and Packaging

49 CRR 173 ...... Subpart A General

49 CFR 173 ...... Subpart B Preparation of Hazardous Material for Transportation

49 CFR 173 ...... Subpart J Other Regulated Material;

Definitions and Preparation

TSCA ............ Compliance Program Policy Nos. 6-PCB-6 and

6-PCB-7

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS (FAR 52.236-9)

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The

Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -15 the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and

"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant

Discharge Elimination System (NPDES) permit is required for this project. The Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:

1. Designating areas for equipment maintenance and repair;

2. Providing waste receptacles at convenient locations and provide regular collection of wastes;

3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;

4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials;

and

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -16

5. Providing adequately maintained sanitary facilities.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems

(including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS"

(FAR 52.236-2).

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -17

1.11 PHYSICAL DATA – SOIL CONDITIONS (NOT USED)

1.12 PROFESSIONAL SURVEYING SERVICES (NOT USED)

1.13 LAYOUT OF WORK (NOT USED)

1.14 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.15 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of

Construction in at least 30 days before the planned pre-warranty conference, submit four sets of the warranty management plan.

Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved.

Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -18 to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

4. A list for each warranted equipment item, feature of construction or system indicating:

a. Name of item.

b. Model and serial numbers.

c. Location where installed.

d. Name and phone numbers of manufacturers and suppliers.

e. Name and phone numbers of manufacturers or suppliers.

f. Names, addresses and phone numbers of sources of spare parts.

g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -19 warranties must be indicated with separate warranty expiration dates.

h. Starting point and duration of warranty period.

i. Summary of maintenance procedures required to continue the warranty in force.

j. Cross-reference to specific pertinent Operation and

Maintenance manuals.

k. Organizations, names and phone numbers of persons to call for warranty service.

l. Typical response time and repair time expected for various warranted equipment.

5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

6. Procedure and status of tagging of all equipment covered by extended warranties.

7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the

Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the

Government while performing the work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expense, the Contracting Officer will have the right to recoup expenses from the bonding company.

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -20

3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the

Contracting Officer to proceed against the Contractor.

C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section.

Communication procedures for Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the

Contractor. This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the

Contractor of any of its responsibilities in conjunction with other portions of this provision.

D. Contractor’s Response to Construction Warranty Service

Requirements:

E. Following oral or written notification by the Contracting

Officer, the Contractor shall respond to construction warranty service requirements in accordance with the “Construction

Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -21 that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the

Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.

1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.

2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.

3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.

4. The “Construction Warranty Service Priority List” is as follows:

a) Code 1-Life Safety Systems

Fire suppression systems.

Fire alarm system(s).

b) Code 1-Air Conditioning Systems

Air conditioning leak in part of the building, if causing damage.

Air conditioning system not cooling properly.

c) Code 1 Doors

Overhead doors not operational, causing a security, fire or safety problem.

1) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.

d) Code 3-Doors

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -22

Overhead doors not operational.

Interior/exterior personnel doors or hardware not functioning properly.

e) Code 1-Electrical

Power failure (entire area or any building operational after 1600 hours).

Security lights.

Smoke detectors.

f) Code 2-Electrical

Power failure (no power to a room or part of building).

Receptacle and lights not operational (in a room or part of building).

g) Code 3-Electrical

Exterior lights not operational.

h) Code 1-Gas

Leaks and pipeline breaks.

i) Code 1-Heat

Power failure affecting heat.

j) Code 1-Plumbing

Hot water heater failure.

2) Leaking water supply pipes

k) Code 2-Plumbing

Flush valves not operating properly

Fixture drain, supply line or any water pipe leaking.

Toilet leaking at base.

l) Code 3- Plumbing

Leaky faucets.

m) Code 3-Interior

Floors damaged.

Paint chipping or peeling.

Casework damaged.

n) Code 1-Roof Leaks

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -23

Damage to property is occurring.

o) Code 2-Water (Exterior)

No water to facility.

p) Code 2-Water (Hot)

No hot water in portion of building listed.

q) Code 3

All work not listed above.

F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the

Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.

Warranty Tags

Type of product/material

Model number

Serial number

Contract number

Warranty period from/to

Inspector’s signature

Construction Contractor

Address

Telephone number

Warranty Contact

Address

Telephone number

Warranty response time priority code

Correct FCA Deficiencies Steam Distribution System

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621N2815

Station Project No. 590-20-903

Bancroft-AE Project No. 22-118 11/14/2023 01 00 00 -24

1.16 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on

Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense.

When necessary to cross curbing, sidewalks, or similar construction,…

This is the start of the file's text. The full file is on GovTribe.