This document is the Bonding Information attachment for a federal contract opportunity. It outlines the bidding and bonding requirements for the contract:

The bid guarantee (bid bond) is required to be 20% of the bid price, up to a maximum of $3 million. The bid bond must be submitted in the form of Standard Form 24 with original wet ink signatures. Acceptable bid security forms are detailed per FAR 28.203-2.

For contracts over $35,000, a Payment Bond (SF 25A) is required. For contracts over $150,000, both a Payment Bond and Performance Bond (SF 25) are required. Bonds must be submitted within 10 days of award notification and provided with original wet ink signatures.

The related federal contract opportunity is Solicitation #36C24624R0045 for Correct FCA Deficiencies Steam 590-20-903 Distribution System, issued by the Department of Veterans Affairs, Veterans Health Administration, Veterans Integrated Service Network 6.

View the file

Other files

File Type Posted
36C24624R0045 0013.docx DOCX document
59020903_Addendum_2_08082024 AMEND 0012.pdf PDF
36C24624R0045 0012.docx DOCX document
20240628_SteamT Investigation_AMcD.pdf PDF
36C24624R0045 0011.docx DOCX document
36C24624R0045 0010.docx DOCX document
RFI 011 for Mech work.pdf PDF
36C24624R0045 0009.docx DOCX document
36C24624R0045 0008.docx DOCX document
Attach 1 RFI 009 - CO comments Amend 0008.pdf PDF
RFI 010 a Amend 0008.pdf PDF
Attachment I - RFI 010.pdf PDF
Attachment J - 59020903_Addendum_1_05302024_W RFI10.pdf PDF
36C24624R0045 0007.docx DOCX document
Attach 1 RFI 009 - Revision 3 - BAE Response_Redacted.pdf PDF
36C24624R0045 0006.docx DOCX document
Attach 2 RFI 009 Specification Appendix 2.pdf PDF
ATTENDANCE LOG - PRE PROPOSAL SITE VISIT Steam.pdf PDF
36C24624R0045 0005.docx DOCX document
BAE Response - RFI 005 04.12.24_Redacted.pdf PDF
BAE Response - RFI 007 04.12.24_Redacted.pdf PDF
BAE Response - RFI 008 04.15.24_Redacted.pdf PDF
36C24624R0045 0004.docx DOCX document
BAE Field Report additional photos Part 3.pdf PDF
BAE Field Report additional photos Part 1.pdf PDF
BAE Field Report additional photos Part 4.pdf PDF
36C24624R0045 0003.docx DOCX document
BAE Field Report additional photos Part 2.pdf PDF
Portion of BOD.pdf PDF
20240315_M001.pdf PDF
36C24624R0045 0002.docx DOCX document
20240315_A102_N.pdf PDF
36C24624R0045 0001.docx DOCX document
Attachment B - Corp Experience Form.docx DOCX document
Attachment D - EMR Certification Form 2024.docx DOCX document
Attachment C - Past Performance Questionnaire.docx DOCX document
Attachment E - RFI Form R0045.doc DOC document
Attachment F - Cost Breakdown with Schedule of Values.xlsx XLSX spreadsheet
Attachment H - Boiler Plant and Site Visit.pdf PDF
590-20-903_Dwg Pkg.pdf PDF
Appendix E_Hampton-Asb LBD Report.pdf PDF
Attachment G - Contractor Training Requirements 590-20-903_11-2-2023.pdf PDF
Attachment I - Construction Safety Pamphlet for Dist.pdf PDF
Attachment A - Wage Determination VA20240022 Mod 1 Dated 02232024.pdf PDF
36C24624R0045_RFP.docx DOCX document
590-20-903 IFB_Specs.pdf PDF
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BONDING INFORMATION

BID GUARANTEE: A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, shall require rejection of the bid in all cases except those listed in Federal Acquisition Regulation (FAR) 28.101-4. Bid Bonds must be provided using Standard Form 24 (see FAR 28.106-1) and the form must be provided in original (no white outs, faxed or copied signatures, seals) with ‘wet ink’ signatures and contain the proper solicitation number, bid opening date, and be from a corporate surety listed in Department of Treasury Circular 570. Individual sureties shall be determined acceptable to the Contracting Officer (see FAR 28.203) and be accompanied by Standard Form 28 Affidavit of Individual Surety. Other forms of bid security may be acceptable as denoted in FAR Part 28.203-2.

PERFORMANCE AND PAYMENT BONDS: In accordance with Contract Clause 52.228-15, and FAR 28.102, Contractors are reminded that any amount awarded over $35,000.00 shall require a Payment Bond (SF 25A), and awards exceeding $150,000.00 shall require both Payment and Performance Bonds (SF 25). Payment and Performance bonds are due no later than 10 days after notification of award. Bonds must be provided with original ‘wet ink’ signatures - no white-outs or other corrections are allowable. Copies and facsimiles of bonds shall not be accepted.