Attachment J - 59020903_Addendum_1_05302024_W RFI10.pdf
PDF 2 MB Posted
- Solicitation number
- 36C24624R0045
About this file
This document appears to be an addendum to a contract for the Correct FCA Deficiencies Steam Distribution System project at the Hampton VA Medical Center (Solicitation Number: 36C24624R0045). The addendum provides supplemental instructions and drawings related to the construction phasing plan and additional pipe support details. Key details include:
The phasing plan outlines specific requirements for the contractor during construction, such as coordinating mechanical service outages, modifying existing piping, adhering to OSHA/VA requirements for confined space access, and sequencing construction to maintain uninterrupted service to critical buildings. The addendum also includes details on temporary equipment the contractor must provide, such as condensate coolers, make-up water systems, vacuum pumps, and fuel pump systems, to maintain operations during the construction phases. The drawings M002 and S301 are newly included in the construction documents to support the phasing plan and provide additional pipe support details.
View the file
Other files
Show all 46
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TO: Anna Bernas-Kelly (COR) Hampton VA Medical Center
100 Emancipation Drive Hampton, VA 23667
PROJECT NAME: Correct FCA Deficiencies Steam Distribution System
CONTRACT NO: 36C24624R0045
STATION PROJECT NO: 590-20-903
A/E PROJECT NO: 22-118
ADDENDUM NO. #1
ISSUE DATE: 05/30/2024
The following instructions and the listed documents below are hereby created to be incorporated as part of the contract documents.
SUPPLEMENTAL INSTRUCTIONS:
1. This Addendum is being submitted to provide phasing plan for construction and additional pipe support details for pipes located inside building crawlspaces.
SPECIFICATIONS INCLUDED AS PART OF THIS ASI:
NONE.
DRAWINGS INCLUDED AS PART OF THIS ASI:
1. M002 (This drawing is new to the construction documents and provides phasing instructions.)
2. S301 (This drawing adds additional details for pipe supports.)
END OF ADDENDUM #1
SEW
ELL
AVENUE
AVENUE
AM
ES
S
TR
EE
T
ST
RE
ET
KN
OX
S
TR
EE
T
W
OO
DF
IN
TH
O
M
PS
O N
S
TR
EE
T
BLACK
FRANKLIN BOULEVARD
AVEN
U
E M cC
LELLAN
HARRIS
HARRIS
AVENUE
AVERILL AVENUE
MARTIN L. KING JR. BOULEVARD
AVENUE
HARRIS
HARRIS
AVERILL AVENUE
FRANKLIN BOULEVARD
JONES CREEK
STORM
WATER POND
IMPOUND LOT
AVENUE
35 36
113A
110B
110A
110C
137A 137B
137C
A. COORDINATE ALL MECHANICAL SERVICE OUTAGES WITH
VA/COR IN WRITING WITH MINIMUM TWO WEEKS NOTICE.
B. CONTRACTOR IS RESPONSIBLE FOR ALL MODIFICATIONS TO THE
EXISTING PIPING NECESSARY TO PERMIT THE INSTALLATION OF
NEW WORK.
C. CONTRACTOR IS RESPONSIBLE FOR ADHERING TO ALL OSHA
AND VA REQUIREMENTS FOR ACCESS AND WORK WITHIN A
PERMIT REQUIRED CONFINED SPACE.
D. CONTRACTOR SHALL PHASE CONSTRUCTION TO PROVIDE
UNINTERRUPTED SERVICE TO BUILDINGS DESIGNATED AS
CRITICAL. PHASING PLAN SHALL BE SUBMITTED TO VA/COR FOR
REVIEW PRIOR TO START OF CONSTRUCTION ACTIVITIES.
E. REFER TO INDUSTRIAL HYGIENIST DRAWINGS FOR LOCATIONS
WITH ASBESTOS CONTAINING MATERIAL (ACM). ABATEMENT
SHALL TAKE PLACE ACCORDING TO INDUSTRIAL HYGIENIST
RECOMMENDATIONS.
GENERAL NOTES
PHASING NOTES
THIS PHASING PLAN AIMS TO HIGHLIGHT POTENTIAL REQUIREMENTS
FOR ADDITIONAL WORK OR EQUIPMENT TO BE PROVIDED AT
DIFFERENT POINTS DURING CONSTRUCTION. IT IS NOT THE INTENT
OF THIS PHASING PLAN TO BE ALL-INCLUSIVE OR PROVIDE THE
CONTRACTOR SPECIFIC INFORMATION RELATED TO SEQUENCING
OR MEANS AND METHODS. THE CONTRACTOR IS RESPONSIBLE FOR
SUBMITTING A DETAILED PHASING PLAN TO THE VA PRIOR TO
COMMENCING ANY WORK.
THIS PHASING PLAN BREAKS THE PROJECT DOWN INTO THE
FOLLOWING CATEGORIES:
ITEM A: STEAM TUNNEL CONDENSATE RETURN PIPING
ITEM B: CONDENSATE PIPING AND EQUIPMENT WITHIN BUILDING
ITEM C: BUILDING 15 BOILER PLANT STEAM EQUIPMENT
ITEM D: BUILDING 15 BOILER PLANT FUEL EQUIPMENT
1 ITEM A:
DURING REPLACEMENT OF CONDENSATE RETURN PIPING WITHIN
STEAM TUNNEL, AFFECTED BUILDINGS WHOSE PATH OF
CONDENSATE RETURN TO BUILDING 15 HAS BEEN INTERRUPTED
SHALL DISCHARGE CONDENSATE TO A NEARBY FLOOR DRAIN
WITHIN EACH BUILDING'S RESPECTIVE MECHANICAL ROOM.
CONTRACTOR SHALL PROVIDE TEMPORARY CENTRIFUGAL
BOILER BLOW OFF CONDENSATE COOLER AND DOMESTIC COLD
WATER LINE TO FLASH AND COOL CONDENSATE BEFORE
DISCHARGING TO DRAIN IN EACH RESPECTIVE BUILDING.
TEMPORARY EQUIPMENT AND PIPING SHALL BE SIZED TO
ACCOMMODATE EXISTING PIPE SIZES SERVING EACH BUILDING.
CONTRACTOR SHALL PROVIDE ALL NECESSARY PIPING AND
VENT CONNECTIONS.
2 ITEM B
IF CONTRACTOR CAN COORDINATE REPLACEMENT OF
CONDENSATE RETURN PIPING AND EQUIPMENT WITHIN BUILDING
110 TO OCCUR SIMULTANEOUSLY WITH STEAM TUNNEL PIPING
REPLACEMENT, NO ADDITIONAL TEMPORARY WORK MAY BE
REQUIRED EXCEPT WHAT IS DETAILED IN ITEM A.
ALTERNATIVELY, CONTRACTOR MAY INSTALL NEW CONDENSATE
RETURN PIPING ADJACENT TO ACTIVE EXISTING AND PERFORM A
SHUTDOWN FOR FINAL PIPE CONNECTIONS.
3 ITEM C:
MAKE-UP WATER - DURING REPLACEMENT OF ITEM A, MAKE-UP
WATER FOR THE BOILER SHALL BE PROVIDED TO MAINTAIN
UNINTERRUPTED STEAM SUPPLY GENERATION. THE TEMPORARY
MAKE-UP WATER SYSTEM SHALL BE LARGE ENOUGH TO PROVIDE
SUFFICIENT TREATED WATER FOR THE BOILER TO OPERATE ON
100% MAKE-UP WATER. THE DESIGN WILL REQUIRE THE
INSTALLATION OF A TEMPORARY 3” DOMESTIC WATER
CONNECTION. THIS WATER MUST BE TREATED WITH THE SAME
RO/DI, CHEMICALS, AND SOFTENING METHODS IN USE BY THE
CURRENT BOILER MAKE-UP WATER SYSTEM. THE WATER SHALL
ACCUMULATE IN A TEMPORARY STORAGE TANK SIZED FOR 2-3
CYCLES OF BOILER FILL TO PROVIDE A BUFFER. THE TREATED
MAKE-UP WATER SHALL TIE INTO THE BOILER FEEDWATER
SYSTEM AT SOME POINT AHEAD OF THE DEAERATOR TANK. THE
CONTRACTOR SHALL BE RESPONSIBLE FOR ALL COMPONENTS
INCLUDING PUMPS, TANKS, FILTERS, VALVES, ETC. NECESSARY
TO PROVIDE ADEQUATE BOILER FILL.
VACUUM PUMP - CONTRACTOR SHOULD MAKE EFFORTS TO
REPLACE VACUUM PUMP WHILE CONDENSATE VACUUM PIPING
WITHIN THE STEAM TUNNEL IS UNDERGOING REPLACEMENT TO
AVOID POTENTIAL TEMPORARY EQUIPMENT. ALTERNATIVELY,
CONTRACTOR SHALL PROVIDE TEMPORARY VACUUM PUMP
SIZED ACCORDING TO NEW EQUIPMENT SCHEDULES AND
PROVIDE TEMPORARY PIPING SOLUTION AS NECESSARY.
CONDENSATE TRANSFER PUMPS - CONTRACTOR SHOULD MAKE
EFFORTS TO REPLACE CONDENSATE TRANSFER PUMPS DURING
REPLACEMENT OF STEAM TUNNEL CONDENSATE PIPING
REPLACEMENT TO AVOID POTENTIAL TEMPORARY EQUIPMENT.
ALTERNATIVELY, THE TWO CONDENSATE TRANSFER PUMPS MAY
BE ISOLATED FROM EACH OTHER AND REPLACED IN SEQUENCE.
CONTRACTOR SHALL PROVIDE ANY TEMPORARY PIPING
SOLUTIONS NECESSARY.
BOILER FEED-WATER PUMP - CONTRACTOR SHALL ISOLATE
EXISTING TURBINE BOILER FEED WATER PUMP AND TRANSFER
FULL LOAD TWO OTHER EXISTING PUMPS. NO TEMPORARY
EQUIPMENT SHOULD BE REQUIRED.
BLOW-DOWN TANK - IF TEMPORARY BLOW-DOWN TANK IS
REQUIRED, PROVIDE SIZED ACCORDING TO NEW SCHEDULED
SIZE OF BLOW-DOWN TANK ON SHEET M601.
4 ITEM D:
CONTRACTOR SHALL PROVIDE TEMPORARY FUEL PUMP SYSTEM
SIZED ACCORDING TO NEW SCHEDULE ON SHEET M601.
TEMPORARY FUEL PUMPS MAY NOT BE REQUIRED IF
CONTRACTOR CAN INSTALL NEW FUEL PUMPS ADJACENT TO
EXISTING OR IF EXISTING PUMPS CAN BE REPLACED
SEQUENTIALLY.
CONTRACTOR SHALL REPLACE FUEL PIPING BETWEEN THE
PUMPS AND THE OUTDOOR STORAGE TANKS IN TWO PHASES.
PHASE ONE SHALL BE REPLACEMENT OF ALL PIPING BETWEEN
THE FUEL PUMPS AND THE TWO SMALLER OUTDOOR FUEL
STORAGE TANKS. PHASE TWO SHALL BE REPLACEMENT OF ALL
PIPING BETWEEN THE FUEL PUMPS AND THE LARGE OUTDOOR
FUEL STORAGE TANK. CONTRACTOR SHALL PROVIDE ALL
REQUIRED VALVES TO COMPLETE WORK.
BLOW DOWN / CONDENSATE COOLER SCHEDULE
EQUIPMENT
TAG EQUIPMENT TYPE LOCATION SERVICE MANUFACTURER MODEL TYPE MAWP
(PSI) NOTES
VARIES BLOW DOWN /
CONDENSATE COOLER
VARIOUS BUILDING
MECHANICAL ROOMS CONDENSATE CEMLINE CBO TANGENTIAL 150 1,2,3,4,5,6,7
NOTES:
1. OTHER ACCEPTABLE MANUFACTURERS: VA APPROVED EQUAL.
2. TANK SHALL HAVE TANGENTIAL BLOW OFF INLET AND MINIMUM 3/8" THICK 90 DEGREE WEAR PLATE.
3. TANK MATERIAL OF CONSTRUCTION SHALL BE CARBON STEEL.
4. PROVIDE TEMPERATURE CONTROL VALVE TO MAINTAIN PROPER DRAIN TEMPERATURE.
5. TANK INSULATION SHALL BE FIELD APPLIED AS SPECIFIED IN VA SPECIFICATION 23 07 11.
6. TANK SHALL CONFORM TO ALL REQUIREMENTS SET FORTH IN VA SPECIFICATION 23 50 11 SECTION 2.4.
7. TANK SHALL BE SIZED TO PAIR WITH EXISTING PIPE SIZE IN EACH RESPECTIVE BUILDING'S MECHANICAL SPACE.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
K:
\C
C G
_P R
O
JE
C
TS
\2
2\
-1
_5
-2 0-
3_
H am pt on
, V A_
FC
A
St ea m D ef ic it\
0- D es ig n D oc um en ts
\4
D ra w in gs
\W O
R
KI
N G
\A U
TO
C
AD
\5
-2
0-
_M
2.
dw g 5/
/2
4:
:4
PM
ISSUE FOR BIDOffice of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
CORRECT FCA DEFICIENCIES
STEAM DISTRIBUTION SYSTEM
HAMPTON, VIRGINIA
590-20-903
Project Director
Revisions: Date:
www. bancroft-ae.com
BAE PROJECT NO. 22-118
3300 Dundee Road Northbrook, IL 60062
T: 847.952.9362
VA CONTRACT NO. 36C24622C0070 05/30/2024
0 16' 32' 64' 128'1/64"=1'-0"1 MECHANICAL - SITE PLAN OVERALL - PHASING
NORTH
MECHANICAL - PHASING PLAN
RH RR
M002
OVERALL
ADDENDUM 1 05/30/2024
ADDENDUM #1
| 59020903_Addendum_1_05302024_Cover |
| 590-20-93_M002-M002 |
| M002 |
SEA-2024-05-30-ADD1
File details come from the government source that posted it. Updated .