About this file

This document provides details for a federal contract solicitation to construct a clean core addition to a surgical suite at a Department of Veterans Affairs medical center. The solicitation will be a Request for Proposal conducted in accordance with FAR Parts 15, 19, and 36 and evaluated using Lowest Price Technically Acceptable procedures. The work includes constructing approximately 2,900 square feet of renovated existing space and 3,900 square feet of new space, with a 490 calendar day period of performance. The solicitation will be advertised as a total Service-Disabled Veteran-Owned Small Business set-aside with a NAICS code of 236220 and size standard of $39.5 million. All questions must be submitted in writing by the specified date, with the magnitude of construction estimated between $5 million to $10 million.

36E77619R0097 0004 P01 - SKA02 - REVISED DOOR SCHEDULE.pdf

View the file

Other files for this federal contract opportunity

Other files attached to Construct Clean Core (VA-19-00058573), newest first.
File Type Posted
36E77619R0097-0007000.docx DOCX document
36E77619R0097-0006000.docx DOCX document
36E77619R0097-0005001.pdf PDF
36E77619R0097-0005000.docx DOCX document
36E77619R0097-0004001.docx DOCX document
36E77619R0097-0004004.pdf PDF
36E77619R0097-0004002.pdf PDF
36E77619R0097-0004000.docx DOCX document
36E77619R0097-0004003.pdf PDF
36E77619R0097-0003001.pdf PDF
36E77619R0097-0003000.docx DOCX document
36E77619R0097-0002001.pdf PDF
36E77619R0097-0002002.pdf PDF
36E77619R0097-0002000.docx DOCX document
36E77619R0097-0001030.docx DOCX document
36E77619R0097-0001031.pdf PDF
36E77619R0097-010.pdf PDF
36E77619R0097-006.pdf PDF
36E77619R0097-008.pdf PDF
36E77619R0097-014.pdf PDF
36E77619R0097-011.pdf PDF
36E77619R0097-003.docx DOCX document
36E77619R0097-015.docx DOCX document
36E77619R0097-007.pdf PDF
36E77619R0097-012.pdf PDF
36E77619R0097-004.pdf PDF
36E77619R0097-005.zip ZIP file
36E77619R0097-013.pdf PDF
36E77619R0097-009.pdf PDF
36E77619R0097-007.pdf PDF
36E77619R0097-009.pdf PDF
36E77619R0097-008.pdf PDF
36E77619R0097-012.pdf PDF
36E77619R0097-004.pdf PDF
36E77619R0097-013.pdf PDF
36E77619R0097-005.zip ZIP file
36E77619R0097-006.pdf PDF
36E77619R0097-003.docx DOCX document
36E77619R0097-010.pdf PDF
36E77619R0097-015.docx DOCX document
36E77619R0097-011.pdf PDF
36E77619R0097-014.pdf PDF
36E77619R0097-000.docx DOCX document
36E77619R0097-000.docx DOCX document
Show all 44

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Graphic Scale

HA Project No.

Scale

Date

Harriman Associatesc

Auburn

Boston

Portland

Portsmouth

SKA02

REVISED DOOR

SCHEDULE

PROVIDENCE, RHODE ISLAND

650-337

12-03-19

CONSTRUCT CLEAN

CORE

ADDITION TO SURGICAL

SUITE

DOOR AND FRAME SCHEDULE

DOOR

MARK

DOOR PANELS FRAME

FIRE

RATING

HDW

SET REMARKSPANEL SIZE

MAT TYPE LEAF 2

TYPE

MAT /

FIN TYPE

DETAILS

No. W LEAF 2

W H T HEAD JAMB SILL

LEVEL 02

201.2 (1) 3' - 0" 7' - 0" 1 3/4" WD F HM 1 F3 F4 - HW-1A

202.1 (1) 3' - 0" 7' - 0" 1 3/4" WD F HM 1 F3 F4 - HW-1A

202A (1) 3' - 0" 7' - 0" 1 3/4" WD F HM 1 F3 F4 - HW-2

203 (2) 3' - 0" 3' - 0" 7' - 0" 1 3/4" WD N HM F2 F4 - 90 MIN HW-10A

206.2 (1) 4' - 0" 7' - 0" 1 3/4" WD F HM 1 F3 F4 - HW-1N REFER TO F1/A60.1 FOR JAMB

FRAMING REVISION

207.2 (1) 4' - 0" 7' - 0" 1 3/4" WD F HM 1 F3 F4 - HW-1N REFER TO F1/A60.1 FOR JAMB

FRAMING REVISION

208.2 (1) 4' - 0" 7' - 0" 1 3/4" WD F HM 1 F3 F4 - HW-1N REFER TO F1/A60.1 FOR JAMB

FRAMING REVISION

208.3 (2) 3' - 0" 3' - 0" 7' - 0" 1 3/4" WD N HM 1 F3 F4 - HW-8B

209.2 (1) 4' - 0" 7' - 0" 1 3/4" WD F HM 1 F3 F4 - HW-1N REFER TO F1/A60.1 FOR JAMB

FRAMING REVISION

210 (2) 3' - 6" 3' - 6" 7' - 0" 1 3/4" WD F HM 1 F2 F4 - HW-8B .

211 (1) 3' - 0" 7' - 0" 1 3/4" WD F HM 2 F3 F4 HW-1A

221 (1) 3' - 0" 7' - 0" 1 3/4" WD F HM 1 F2 F4 - HW3G

222.2 (2) 3' - 0" 3' - 0" 7' - 0" 1 3/4" WD N HM 1 F2 F4 - 90 MIN HW-10A

250 (1) 4' - 0" 7' - 0" 1 3/4" WD N HM 1 F2 F4 - HW-4P

251 (1) 3' - 0" 7' - 0" 1 3/4" WD F HM 1 F2 F4 - 45 MIN HW-5B

252 (2) 3' - 0" 3' - 0" 7' - 0" 1 3/4" WD N HM F2 F4 - 45 MIN HW-10A2

253 (1) 3' - 0" 7' - 0" 1 3/4" WD HG HM 1 F2 F4 - HW-3E

254 (1) 3' - 8" 7' - 0" 1 3/4" WD F HM 1 F2 F4 - 45 MIN HW-4K

255 (1) 3' - 8" 7' - 0" 1 3/4" WD HG HM 1 F2 F4 - 45 MIN HW-1K

256.1 (1) 3' - 0" 7' - 0" 1 3/4" WD HG HM 1 F2 F4 - 45 MIN HW-4C

256.2 (1) 3' - 8" 7' - 0" 1 3/4" WD HG HM 1 F2 F4 - HW-4C

257 (1) 3' - 6" 7' - 0" 1 3/4" HM F HM 2 F2 F4 - HW-5G

260 (1) 4' - 0" 7' - 0" 1 3/4" WD HG HM 1 F2 F4 - 45 MIN HW-1N

261 (1) 4' - 0" 7' - 0" 1 3/4" WD F HM 1 F2 F4 - 45 MIN HW-1N

263.1 (2) 3' - 0" 3' - 0" 7' - 0" 1 3/4" WD N HM 1 F2 F4 - HW-8B

263.2 (1) 4' - 0" 7' - 0" 1 3/4" WD N HM 1 F2 F4 - 45 MIN HW-1N

264 (2) 3' - 0" 3' - 0" 7' - 0" 1 3/4" WD F HM 1 F2 F4 - HW-11

265.1 (2

UNEQUAL) 4' - 0" 2' - 0" 7' - 0" 1 3/4" WD N N HM F2 F4 - 45 MIN HW-8B

N

F

N

N

F

N

N 2

Sheets
SKA02 - REVISED DOOR SCHEDULE

File details come from the government source that posted it. Updated .