RESPONSE V10 - Technical Questions.docx

DOCX document 2 MB Posted

Attached to
EHRM Infrastructure Upgrades Construction - Salt Lake City VAMC Project 660-21-700
Solicitation number
36C77623B0041
Issued by

About this file

This document contains responses to technical questions regarding Solicitation Number 36C77623B0041 for EHRM Infrastructure Upgrades Construction at the Salt Lake City VA Medical Center. The solicitation involves upgrading IT distribution and services across multiple buildings and requires electrical, low voltage, and fiber optic cabling work. Bidders must provide an SSHO, CQC manager, and allow work in evenings and weekends. Asbestos abatement will require air clearance testing and third party oversight by the contractor. Limited staging space is available on site. The existing fire alarm and security systems utilize Siemens and Software House technologies. Responses clarify panel specifications, circuit information, and photo documentation. The question deadline was extended to August 1st and the bid due date to August 22nd. The fixed price contract does not include an escalation clause for materials.

View the file

Other files

File Type Posted
RESPONSE Attachment V5.1.docx DOCX document
Construction Wage Rates- Salt Lake County- 08-11-2023.pdf PDF
ADDENDUM No 01.pdf PDF
Bid opening call-in information.pdf PDF
RESPONSE Attachment V5.1 No. 30 Snippet.JPG JPG image
2017 AHERA 3-Year Reinspection v2.2 2017_1205_BT.xlsx XLSX spreadsheet
RESPONSE Attachment V7.2.docx DOCX document
36C77623B0041 0004.pdf PDF
RESPONSE Attachment V2.1.docx DOCX document
RESPONSE Attachment V1.1.docx DOCX document
RESPONSE Attachment V7.1.docx DOCX document
RESPONSE Attachment V3.1.docx DOCX document
36C77623B0041 0003.pdf PDF
36C77623B0041 0003.pdf PDF
36C77623B0041 0002.pdf PDF
660-21-700 PreConstruction Site Visit Sing In Sheet 2023 07 14.pdf PDF
36C77623B0041 0001.pdf PDF
Attachment 13-Utah Tax Memo-EHRM-Salt Lake City.pdf PDF
Attachment 7-Part 6 of 9-Drawings-EHRM-Salt Lake City.pdf PDF
Attachment 12-Construction Wage Rates-Salt Lake County- 04-14-2023.pdf PDF
Attachment 14-Limitations on Subcontracting-EHRM-Salt Lake City.docx DOCX document
Attachment 2-Part 1 of 9-Drawings-EHRM-Salt Lake City.pdf PDF
Attachment 15-Contractor Safety-Environmental-EHRM-S.L.C..docx DOCX document
Attachment 1-Specifications-(1 of 1)-EHRM-Salt Lake City.pdf PDF
Attachment 6-Part 5 of 9-Drawings-EHRM-Salt Lake City.pdf PDF
Attachment 3-Part 2 of 9-Drawings-EHRM-Salt Lake City.pdf PDF
Attachment 9-Part 8 of 9-Drawings-EHRM-Salt Lake City.pdf PDF
Attachment 5-Part 4 of 9-Drawings-EHRM-Salt Lake City.pdf PDF
36C77623B0041.pdf PDF
Attachment 16 - Site Visit Instructions.pdf PDF
Attachment 11-Asbestos Site Survey-EHRM Salt Lake City.pdf PDF
Attachment 10-Part 9 of 9-Drawings-EHRM-Salt Lake City.pdf PDF
Attachment 4-Part 3 of 9-Drawings-EHRM-Salt Lake City.pdf PDF
Attachment 8-Part 7 of 9-Drawings-EHRM-Salt Lake City.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION #36C77623B0041 - TECHNICAL QUESTIONS AND VA RESPONSE TRACKING SHEET - PROJECT NAME: Salt Lake City Project 660-21-700 EHRM Infrastructure Upgrades Construction

ITEM

NO.

DATE QUESTION RECEIVED
DATE QUESTION ANSWERED
QUESTION
GOVERNMENT RESPONSE
1.
7/20/2023
8/17/2023
*Please refer to Attachment V1.1*
See Attachment V1.1 responses.
2.
7/20/2023
8/17/2023
Since we were unable to visit every building at the pre-bid, can someone at the VA take a picture and (publish in the solicitation website) of each one of these existing panels and nameplate data with the door in the open position. We need to verify panel manufacturer and AIC rating in order get the correct breakers to install in existing panels.

*Please refer to Attachment V2.1* See Attachment V2.1 responses. Panel make, model, and AIC ratings have been provided in response.

3.
7/21/2023
8/17/2023
Please provide the circuit numbers for mechanical equipment SS-2 and rooftop outlet located on the 3rd level roof of building 01 shown on sheet 01-EP130.

*Please refer to Attachment V3.1* Circuit SS-2 units on sheet 01-EP130 to panel “1-3-C-E-P2”. This is located in the new CT room 3C06A-1.

4.
7/25/2023
7/25/2023
Due to the complexity of this project I respectively request that the technical questions due date and bid date be extended by 1 week.
CO and COR have agreed to extend the technical questions due date to 8/1/23. The Bid Due date will be extended to 8/22/23.
5.
7/25/2023
8/17/2023
- Specification states to provide an SSHO, can the project superintendent have dual duties as the superintendent and SSHO?
The Superintendent shall not have any shared duties as a QCM, SSHO or any other roles on the project.
6.
7/25/2023
8/17/2023
- Specification states to provide a CQC System Manager, can the project superintendent have dual duties as the superintendent and CQC System Manager?
The QCM shall not have any shared duties as a SSHO, superintendent or any other role on the project.
7.
7/25/2023
8/17/2023
- If the superintendent is able to provide combined SSHO and CQC System Manager capabilities, will they be able to perform all three positions in tandem?
See 5.
8.
7/25/2023
8/17/2023
*Please refer to Attachment V5.1*
See Attachment V5.1 responses.
9.
7/25/2023
8/17/2023
1. Attachment 13 indicates that bidders are to include all state and local sales or use taxes for construction materials. Assuming this project takes place entirely on federal property, please confirm that sales tax is not applicable on labor, only use tax on materials and equipment.
As listed in the solicitation and Attachment 13, bid all state and local taxes. There are no exemptions on this project.
10.
7/25/2023
8/17/2023
2. Is the contractor required to keep the existing EHRM system in place during uplift, or is the Government responsible?
The contractor will need to coordinate with the owner to ensure the existing system is up and operational and is only moved when the owner dictates the move.
11.
7/25/2023
8/17/2023
3. What is the cutover process to integrate into the Nation-Wide system?
This project is to upgrade the Information Technology distribution and services to buildings at the George E. Wahlen VA Medical Center campus. Integration to a “Nation-Wide” system is out of the scope of this project.
12.
7/25/2023
8/17/2023
4. Will the Government consider extending the contract duration by 365 days? The current 730 day duration may not be adequate due to phasing/sequencing requirements.
No
13.
7/25/2023
8/17/2023
5. At the site visit we were only provided minimal project area reviews. Please provide photographs of existing conditions of all areas of work (at a minimum, representative areas of existing conditions at each building, TR, and surrounding areas of the TRs)
See Attachment of typical existing IT rooms and corridors.
14.
7/25/2023
8/17/2023
6. Please provide information on the current fire alarm system to include manufacturer and vendor who services it.
It is a Siemens MXL fire system, serviced by Alarm Control.
15.
7/25/2023
8/17/2023
7. Please provide information on the current security system(s) to include manufacturer and vendor who services it.
Software House

CCure 9000.

16.
7/25/2023
8/17/2023
8. Please provide pictures of the existing electrical panels that are being affected by this project. The breakers being added by this project can vary greatly in cost, depending on the panel.
See response 2.
17.
7/25/2023
8/17/2023
The Drawings for this project have extensive reference to "Verify in Field". The organized site visit did not provide access to or sufficient time in all work areas. It was also stated that the organized site visit will be the only opportunity to visit the site. Will work elements and spaces that deviate from the project plans be handled as an unforeseen or differing site condition?
Yes, within reason. Also see responses to all these questions, specifically response 13.
18.
7/25/2023
8/17/2023
The duration of this project will require cost escalation for materials. It does not appear that an escalation clause has been included. The volatile nature of construction materials will have a great impact on the contract value. How will cost escalation related to project materials be handled? Will the contractor be responsible for all risk associated with cost escalation or will an escalation clause be added?
In accordance with FAR 52.216-1, this requirement will remain as a Firm Fixed Price contract.
19.
7/25/2023
8/17/2023
On the enlarged power plans there are new devices shown being fed from existing panels. Please show the locations.

· 1-2-A-N-P2 on enlarged power plan F5/01-EP401

· 1-4-A-N-P2 on enlarged power plan B1/01-EP402

· 1-4-A-N-P2 on enlarged power plan B3/01-EP402

· 1-4-A-N-P2 on enlarged power plan B5/01-EP402

· 1-4-A-N-P2 on enlarged power plan D3/01-EP402

· 1-3-A-N-P2 on enlarged power plan D1/01-EP402

See updated drawings showing locations on Addendum No 1.

20.
7/27/2023
8/17/2023
*Please refer to Attachment V7.1*
See Attachment V7.1 response
21.
7/27/2023
8/17/2023
*Please refer to Attachment V7.2*
See Attachment V7.2 responses.
22.
8/1/2023
8/17/2023
1. Is there a full asbestos/lead inspection report available? All we have received is a map showing their location of known ACM materials. This is not sufficient for our needs.
See attachment Excel table “2017 AHERA 3-Year Reinspection v2.2 2017_1205_BT”. An updated inspection report will be provided to awardee after the project is awarded as additional guidance.
23.
8/1/2023
8/17/2023
2. Will there be any limitations to the hours of operation that we will be allowed to work? Would it be possible to work after regular business hours?
Advance scheduling with the VA will be of paramount importance and work in evening, nighttime, and weekend hours will be required and shall be included in the constructors Base Bid Pricing. See Statement of Work.
24.
8/1/2023
8/17/2023
3. What will the clearance criteria be for areas where asbestos abatement has been completed? Will the owner want visual and/or air clearances for all areas?
TEM samples inside the regulated area shall be at or below 70 asbestos s/mm2 to satisfy the project final clearance criteria. Any suspicious material must be tested by the contractor. See specifications 02 82 13.19, 02 82 11 and HR drawings for more information.
25.
8/1/2023
8/17/2023
4. Who is responsible for providing 3rd party oversight for abatement activities?
General Contractor.
26.
8/1/2023
8/17/2023
5. What should we plan for in regard to staging areas and parking?
There will be limited space available.

Due to changing conditions and projects on campus, defined staging and parking areas are not established at this time. See sheet AE002 for conceptual staging plan and construction path of travel to each building.

27.
8/1/2023
8/17/2023
6. Will we be allowed to utilize the power and water available onsite?
Yes.
28.
8/2/2023
Please confirm the existing Fire Alarm system for the above-mentioned solicitation.
See response to 14.
29.
8/4/2023
Will any other manufacturers other than Duraline Microduct be acceptable?
Duraline is the acceptable manufacturer for the Microduct.
30.
8/4/2023
Will CommScope ABF be acceptable over AFL?
Yes confirmed.
31.
8/4/2023
Will CommScope ISP fiber and connectivity be acceptable over Corning?
Yes, confirmed if it matches the HD Corning used as BOD.

image4.jpeg image5.jpeg image6.jpeg image7.jpeg image8.jpeg image9.jpeg image10.jpeg image11.jpeg image12.jpeg image13.jpeg image14.jpeg image15.jpeg image16.jpeg image1.jpeg image2.jpeg image3.jpeg