RESPONSE Attachment V7.1.docx

DOCX document 19 KB Posted

Attached to
EHRM Infrastructure Upgrades Construction - Salt Lake City VAMC Project 660-21-700
Solicitation number
36C77623B0041
Issued by

About this file

This document contains a response to questions regarding a construction project. The response clarifies that existing conduit pathways on site will be used, and the cable size will change from 8.5/6mm to 10/8mm to accommodate Commscope cable.

The related federal contract opportunity is a solicitation from the Department of Veterans Affairs Technology Acquisition Center Austin for infrastructure upgrades at the Salt Lake City VAMC. Project 660-21-700 involves EHRM construction work. The response provides additional technical details to support the requirements of this infrastructure upgrade project at the Salt Lake City VAMC.

View the file

Other files

File Type Posted
RESPONSE Attachment V5.1.docx DOCX document
Construction Wage Rates- Salt Lake County- 08-11-2023.pdf PDF
ADDENDUM No 01.pdf PDF
Bid opening call-in information.pdf PDF
RESPONSE Attachment V5.1 No. 30 Snippet.JPG JPG image
2017 AHERA 3-Year Reinspection v2.2 2017_1205_BT.xlsx XLSX spreadsheet
RESPONSE V10 - Technical Questions.docx DOCX document
RESPONSE Attachment V7.2.docx DOCX document
36C77623B0041 0004.pdf PDF
RESPONSE Attachment V2.1.docx DOCX document
RESPONSE Attachment V1.1.docx DOCX document
RESPONSE Attachment V3.1.docx DOCX document
36C77623B0041 0003.pdf PDF
36C77623B0041 0003.pdf PDF
36C77623B0041 0002.pdf PDF
660-21-700 PreConstruction Site Visit Sing In Sheet 2023 07 14.pdf PDF
36C77623B0041 0001.pdf PDF
Attachment 13-Utah Tax Memo-EHRM-Salt Lake City.pdf PDF
Attachment 7-Part 6 of 9-Drawings-EHRM-Salt Lake City.pdf PDF
Attachment 12-Construction Wage Rates-Salt Lake County- 04-14-2023.pdf PDF
Attachment 14-Limitations on Subcontracting-EHRM-Salt Lake City.docx DOCX document
Attachment 2-Part 1 of 9-Drawings-EHRM-Salt Lake City.pdf PDF
Attachment 15-Contractor Safety-Environmental-EHRM-S.L.C..docx DOCX document
Attachment 1-Specifications-(1 of 1)-EHRM-Salt Lake City.pdf PDF
Attachment 6-Part 5 of 9-Drawings-EHRM-Salt Lake City.pdf PDF
Attachment 3-Part 2 of 9-Drawings-EHRM-Salt Lake City.pdf PDF
Attachment 9-Part 8 of 9-Drawings-EHRM-Salt Lake City.pdf PDF
Attachment 5-Part 4 of 9-Drawings-EHRM-Salt Lake City.pdf PDF
36C77623B0041.pdf PDF
Attachment 16 - Site Visit Instructions.pdf PDF
Attachment 11-Asbestos Site Survey-EHRM Salt Lake City.pdf PDF
Attachment 10-Part 9 of 9-Drawings-EHRM-Salt Lake City.pdf PDF
Attachment 4-Part 3 of 9-Drawings-EHRM-Salt Lake City.pdf PDF
Attachment 8-Part 7 of 9-Drawings-EHRM-Salt Lake City.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Is the pathway on 01-ET-601 existing and where is HH-1 located? See snapshot.

RESPONSE: This should read 4 ea. 7 way 8.5/6mm microduct in existing cnd pathways. The 8.5/6 will change to a 10/8 to allow for Commscope cable. See sheet ES101 in the site plans.