This document is Addendum #1 for the SPS Equipment Site Prep project at the Minneapolis VA Medical Center, dated August 5, 2025. The addendum modifies multiple architectural drawings and specifications, including updates to drawing sheets, demolition plans, floor plans, door schedules, and various specification sections. Key changes include adding new specification sections like Electronic Submittal Procedures (01 33 24), Metal Fabrications (05 50 00), Applied Fireproofing (07 81 00), Automatic Door Operators (08 71 13), and Resinous Specialty Glazed Coating Systems (09 96 59).

The project is a set-aside for Service Disabled Veteran Owned Small Business (SDVOSB) contractors, with a construction value between $2-5 million under NAICS code 236220. The scope involves upgrading and renovating the current Sterile Processing Space (SPS) to prepare for replacement of Steris Medivators and Cart Washers. The addendum reflects modifications to demolition and floor plans for Areas A, B, and C, including equipment relocations, new floor slabs, and changes to room finishes and configurations. The project is part of the Veterans Health Administration's renovation efforts at the Minneapolis facility.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

13605 1st Avenue North Suite 100, Plymouth, MN 55441 P 763.412.4000 F 763.412.4090 ae-mn.com

INSTRUCTIONS TO BIDDERS

ADDENDUM #1

August 05, 2025

SPS Equipment Site Prep

VAMC Minneapolis

Minneapolis, MN

Project #618-CSI-240

The Contents of this Addendum alter and amend the original drawings and specifications and take precedence over the related items therein.

Drawings:

1. Drawing 1395-GI000 – COVER SHEET

a. Revised Sheet Index.

2. Drawing 1395-GI010 – INFECTION CONTROL (ICRA) NOTES & CATEGORIES

a. Added Sheet.

3. Drawing 1395-GC013 – FLOOR PLAN – TEMP SCOPE PROCESSING, AREA A, PH 2A & 2B

a. Revised Floor Plan Keyed Notes FL4 and FL6 as indicated.

b. Revised General Note 17 as indicated.

4. Drawing 1395-GC014 – FLOOR PLAN – TEMP SCOPE PROCESSING, AREA A, PH 2C & 2D

5. Drawing 1395-AD001 – DEMOLITION PLAN – STERILE PROCESSING – AREA B

a. Revised Demolition Plan Keyed Note DE12 to “Not Used”.

6. Drawing 1395-AD001B – DEMOLITION PLAN – STERILE STORAGE – AREA C

a. Revised Demolition Plan Keyed Note DE12 to “Not Used”.

7. Drawing 1395-AE001 – FLOOR PLAN – STERILE PROCESSING – AREA B

b. Revised General Note 17 as indicated.

8. Drawing 1395-AE500 – DOOR SCHEDULE, DOOR & FRAME TYPES AND DETAILS

a. Opening Schedule: Revised Panel Glazing and HDW Group as indicated.

9. Drawing 1395-AF600 – MATERIAL AND ROOM FINISH SCHEDULE

a. Material Schedule: Revised RES-1 as indicated.

b. Material Schedule: Added SC-1.

13605 1st Avenue North Suite 100, Plymouth, MN 55441 P 763.412.4000 F 763.412.4090 ae-mn.com

Specifications:

1. Specification 00 01 10 – Table of Contents

a. Added Section 01 33 24 – Electronic Submittal Procedures.

b. Added Section 05 50 00 – Metal Fabrications.

c. Added Section 07 81 00 – Applied Fireproofing.

d. Added Section 08 77 13 – Automatic Door Operators.

e. Addes Section 09 96 59 – Resinous Specialty Glazed Coating Systems for Ceiling (SC-1)

2. Specification 01 33 24 – Electronic Submittal Procedures

a. Added Section.

3. Specification 01 57 19 – Temporary Environmental Controls

a. Revised Section 1.5F to state, “Perform construction activities involving repetitive, high-level impact noise only after normal business hours (7:00 a.m. to 5:00 p.m.) unless otherwise permitted by local ordinance or the COR.”

4. Specification 05 50 00 – Metal Fabrications

5. Specification 07 81 00 – Applied Fireproofing

6. Specification 08 77 13 – Automatic Door Operators

7. Specification 08 80 00 – Glazing

a. Revised Section 2.2 Heat-Treated Glass to remove Clear Heat Strengthened Glass.

b. Revised Section 2.6 Laminated Glass to Not Used.

c. Revised Section 3.15A to indicate Glass Type MG-1.

d. Revised Section 3.16 Laminated Glass to Not Used.

e. Revised Section 3.20A to indicate Glass Type FR-1.

8. Specification 09 06 00 – Schedule For Finishes

a. Revised Section 2.2A 1. PT-1.

b. Revised Section 2.2A 2. PT-1.

c. Added Section 2.2A 3. T-2, T-3 and T-4.

d. Added Section 2.2D Specialty Coatings.

e. Revised Section 2.2D Painting to Section 2.2E Painting.

9. Specification 09 29 00 – Gypsum Board

a. Revised Section 3.5A to state, “Finish joints, edges, corners, and fastener heads in accordance with ASTM C840. Use Level 4 finish for all finished areas open to public view”.

10. Specification 09 30 00 – Specialty Moldings and Trims

a. Removed Section 1.2E.

11. Specification 09 67 26 00 – Methyl-methacrylate Based Self-leveling Flooring System with a Decorative

Flake Broadcast

a. Removed Section 3.02C.

13605 1st Avenue North Suite 100, Plymouth, MN 55441 P 763.412.4000 F 763.412.4090 ae-mn.com

12. Specification 09 96 59 – Resinous Specialty Glazed Coating Systems for Ceilings (SC-1)

ATTACHMENTS:

DRAWINGS: 1395-GI000, 1395-GC010, 1395-GC013, 1395-GC014, AD001, AD001B, AE001, AE500 and AF600 SPECIFICATIONS: 00 01 10, 01 33 24, 01 57 19, 05 50 00, 07 81 00, 08 71 13, 08 80 00, 09 06 00, 09 29 00, 09 30 00, 09 67 26 and 09 96 59

The inclusion of this Addendum shall be acknowledged upon submission of the Contractor’s Bid. By submission of a Bid, Bidder agrees to full acceptance of the provisions herein. All other provisions of these Specifications, Drawings, and Contract Documents shall remain unchanged and in full effect.

This Addendum shall be attached to and become part of the Specifications for the above Contract.

ISSUED BY ANDERSON: TO, JU, AW

END OF ADDENDUM #1

VAMC Minneapolis VA Project# 618-CSI-240

SPS Equipment Site Prep 06-10-2025

1 Veterans Drive Addendum #1 08-05-2025

Minneapolis, MN 55417 06-24-24

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-21

01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 01-24

01 33 23 Shop Drawings, Product Data, and Samples 11-23

01 33 24 Electronic Submittal Procedures (Web-Based Service) 08-05

01 35 26 Safety Requirements 05-24

01 42 19 Reference Standards 11-20

01 45 00 Quality Control 02-21

01 57 19 Temporary Environmental Controls 01-21

01 58 16 Temporary Interior Signage 07-15

01 74 19 Construction Waste Management 04-22

01 81 13 Sustainable Construction Requirements 10-17

01 91 00 General Commissioning Requirements 04-22

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

DIVISION 03 – CONCRETE

03 30 00 Cast-in-Place Concrete 01-21

DIVISION 04 – MASONRY – NOT USED

DIVISION 05 – METALS

05 50 00 Metal Fabrications 08-18

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 Thermal Insulation 01-21

07 81 00 Applied Fireproofing 07-23

07 84 00 Firestopping 01-21

07 92 00 Joint Sealants 04-22

00 01 10-2

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21

08 31 13 Access Doors and Frames 04-22

08 56 19 Pass Windows

08 71 00 Door Hardware 03-24

08 71 13 Automatic Door Operators 01-21

08 80 00 Glazing 01-21

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 01-21

09 06 00 Schedule for Finishes 01-21

09 22 16 Non-Structural Metal Framing 06-18

09 29 00 Gypsum Board 04-20

09 30 00 Specialty Moldings and Trims 01-24

09 30 13 Ceramic/Porcelain Tiling 01-21

09 51 00 Acoustical Ceilings 12-18

09 65 16 Resilient Sheet Flooring 06-22

09 67 26 Methyl-Methacrylate Based Self-Leveling Flooring

System

12-21

09 91 00 Painting 01-21

09 96 59 Resinous Specialty Glazed Coating Systems for Ceilings 01-21

DIVISION 10 – SPECIALTIES

10 14 00 Signage 01-21

10 21 13 Toilet Compartments 01-21

10 26 00 Wall and Door Protection 01-21

10 28 00 Toilet, Bath, and Laundry Accessories 01-21

10 44 13 Fire Extinguisher Cabinets 08-18

DIVISION 11 – EQUIPMENT – NOT USED

DIVISION 12 – FURNISHINGS

12 36 00 Countertops 11-23

DIVISION 14– CONVEYING EQUIPEMENT – NOT USED

DIVISION 21- FIRE SUPPRESSION

21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 01-23

22 05 19 Meters and Gages for Plumbing Piping 09-20

22 05 23 General-Duty Valves for Plumbing Piping 09-20

00 01 10-3

22 07 11 Plumbing Insulation 09-19

22 08 00 Commissioning of Plumbing Systems 11-16

22 11 00 Facility Water Distribution 05-21

22 13 00 Facility Sanitary and Vent Piping 09-20

22 40 00 Plumbing Fixtures 05-24

22 67 19.16 Reverse-Osmosis Water Equipment 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 03-23

23 05 41 Noise and Vibration Control for HVAC Piping and

Equipment

03-23

23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23

23 07 11 HVAC and Boiler Plant Insulation 02-20

23 08 00 Commissioning of HVAC Systems 03-23

23 09 23 Direct-Digital Control System for HVAC 03-23

23 22 13 Steam and Condensate Heating Piping 03-24

23 31 00 HVAC Ducts and Casings 03-23

23 36 00 Air Terminal Units 03-23

23 37 00 Air Outlets and Inlets 03-23

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 11-22

26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22

26 05 26 Grounding and Bonding for Electrical Systems 11-22

26 05 33 Raceway and Boxes for Electrical Systems 11-22

26 05 73 Overcurrent Protective Device Coordination Study 01-22

26 08 00 Commissioning of Electrical Systems 01-22

26 09 23 Lighting Controls 11-22

26 22 00 Low-Voltage Transformers 11-22

26 24 16 Panelboards 11-22

26 27 26 Wiring Devices 11-22

26 29 11 Motor Controllers 11-22

26 29 21 Enclosed Switches and Circuit Breakers 11-22

26 43 13 Surge Protective Devices 01-22

26 51 00 Interior Lighting 03-24

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19

27 05 33 Raceways and Boxes, Conduits and Backboxes for

Communications Systems

12-22

27 05 36 Cable Trays for Communication Systems 12-22

27 05 53 Identification for Communication Systems 12-22

27 10 00 Structured Cabling for Communications Systems 12-22

27 11 19 Communications Termination Blocks and Patch Panels

12-22

00 01 10-4

27 15 13

Communications Copper Horizontal Cabling

27 16 19 Communications Patch Cords, Staton Cords and Cross

Connect Wire

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 04-18

28 05 13 Conductors and Cables for Electronic Safety and

Security

10-18

28 05 26 Grounding and Bonding for Electronic Safety and

Security

09-11

28 05 28.33 Conduits and Backboxes for Electronic Safety and

Security

09-11

28 08 00 Commissioning of Electronic Safety and Security

Systems

11-16

28 13 00 Physical Access Control System

28 31 00 Fire Detection and Alarm

DIVISION 31 – EARTHWORK – NOT USED

DIVISION 33 – UTILITIES – NOT USED

DIVISION 34 – TRANSPORTATION – NOT USED

SPS Equipment Site Prep 08-05-2025

1 Veterans Drive Addendum #1

Minneapolis, MN 55417

01 33 24 - 1

SECTION 01 33 24

ELECTRONIC SUBMITTAL PROCEDURES

(WEB-BASED SERVICE)

PART 1 - GENERAL

1.1 DESCRIPTION

A. This section specifies requirements for provision and use of an electronic, web-based service for submittal and tracking of construction submittals for the Project.

1.2 REFERENCED DOCUMENTS

A. Additional submittal requirements: Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

1.3 SUMMARY:

A. The intent of electronic web-based submittals is to expedite the construction process by reducing paperwork, improving information flow, and decreasing turnaround time.

B. Shop drawing and product data submittals shall be transmitted to

Architect in electronic (PDF) format using a web-based service designed specifically for transmitting and tracking submittals between construction team members.

C. The electronic submittal process is not intended for color samples, color charts, or physical material samples.

1.4 GENERAL DESCRIPTION OF PROCEDURES:

A. Submittal Preparation - Contractor may use any or all the following options:

1. Subcontractors and Suppliers provide electronic (PDF) submittals to

Contractor via the submittal exchange website.

2. Subcontractors and Suppliers provide paper submittals to General

Contractor who electronically scans and converts to PDF format.

3. Subcontractors and Suppliers provide paper submittals to Scanning

Service which electronically scans and converts to PDF format.

B. Contractor shall review, comment, and apply electronic stamp certifying that the submittal (as noted) complies with the requirements of the

Contract Documents including verification of manufacturer/product, dimensions and coordination of information with other parts of the work.

C. Contractor shall transmit each submittal to Architect and Owner

(simultaneously) using the web-based submittal exchange service.

01 33 24 - 2

D. Architect/COR review comments will be made available on web-based submittal exchange service. Contractor shall receive email notice of completed review.

E. Distribution of reviewed submittals to subcontractors and suppliers is the responsibility of the Contractor.

1.5 REQUIREMENTS AND RESPONSIBILITIES

A. Submittal Exchange Service shall provide:

1. Web-based tracking and approval system.

2. Automated email notice for new submittals and reminders for submittals approaching the review deadline.

3. Tracking and exchange of ITC/RFI/CO’s and other similar document as well as product and equipment submittals.

4. Means for tracking of the status such documents including whether they have been approved and released by the Owner.

5. Organized storage of submittals that is accessible for review by the designated construction team members at any time.

6. Submit a complete set of submittals on CD to the Owner at the end of the Project. Include all submittals included product submittals, shop drawings, ITC/RFI/CO’s and other similar submittals.

B. Contractor responsibilities:

1. Training in the use of the service by the team members shall be at the option of the Contractor and, if chosen, shall be paid by the

Contractor.

2. Contractor shall have or obtain required hardware and software:

Internet Service and Equipment Requirements:

a. Email address and Internet access at Contractor’s main office.

b. Adobe Acrobat (www.adobe.com), Bluebeam PDF Revu

(www.bluebeam.com), or other similar PDF review software for applying electronic stamps and comments.

3. Contractor shall prepare or have prepared all required submittals in the PDF format required.

a. PDF files must be readable. As a rule, a resolution of 300 dpi should be used.

b. If the Architect can download more readable product data directly from the manufacturer’s website than was submitted by the

Contractor, the Architect shall reserve the right to reject the submittal.

https://url.avanan.click/v2/___http:/www.adobe.com___.YXAzOmFlbW46YTpvOjI1ODYxZTk1YTIxY2I2MGZmZTAzOGNlMGEzOWYwYTk0OjY6N2M2NzphNjA1ZWY3YmI5MTY0YzEwYjIyNDc2ZmNkNjY1NGFkY2NkM2Y2M2Q4YTE2M2I0NTc0MDk0MTg1MjQ4ZDUxZTQyOnA6RjpO https://url.avanan.click/v2/___http:/www.bluebeam.com___.YXAzOmFlbW46YTpvOjI1ODYxZTk1YTIxY2I2MGZmZTAzOGNlMGEzOWYwYTk0OjY6NjQ1YTpmZDY2Y2E2OWJlMDkxNWYyYzhhYjI0YzhhNTU3MDg2Y2I2ZTc2MjJhZjFlZGEwYmYzMDkyZWQ0ZTcwY2Y4MGM0OnA6RjpO

01 33 24 - 3

4. Other responsibilities for submittals shall be as described in

Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

a. Color samples, color charts, or physical material samples shall be submitted as described in Section 01 33 23.

1.6 ACCEPTABLE SERVICES

A. Submittal Exchange, no substitute.

- - - END - - -

01 57 19 -1

SECTION 01 57 19

TEMPORARY ENVIRONMENTAL CONTROLS

PART 1 - GENERAL

1.1 DESCRIPTION

This section specifies the control of environmental pollution and damage that the Contractor must consider for air, water, and land resources. It includes management of visual aesthetics, noise, solid waste, radiant energy, and radioactive materials, as well as other pollutants and resources encountered or generated by the Contractor.

The Contractor is obligated to consider specified control measures with the costs included within the various contract items of work.

Environmental pollution and damage is defined as the presence of chemical, physical, or biological elements or agents which:

1. Adversely effect human health or welfare,

2. Unfavorably alter ecological balances of importance to human life,

3. Effect other species of importance to humankind, or;

4. Degrade the utility of the environment for aesthetic, cultural, and historical purposes.

Definitions of Pollutants:

1. Chemical Waste: Petroleum products, bituminous materials, salts, acids, alkalis, herbicides, pesticides, organic chemicals, and inorganic wastes.

2. Debris: Combustible and noncombustible wastes, such as leaves, tree trimmings, ashes, and waste materials resulting from construction or maintenance and repair work.

3. Sediment: Soil and other debris that has been eroded and transported by runoff water.

4. Solid Waste: Rubbish, debris, garbage, and other discarded solid materials resulting from industrial, commercial, and agricultural operations and from community activities.

5. Surface Discharge: The term "Surface Discharge" implies that the water is discharged with possible sheeting action and subsequent soil erosion may occur. Waters that are surface discharged may terminate in drainage ditches, storm sewers, creeks, and/or "water of the United States" and would require a permit to discharge water from the governing agency.

01 57 19 -2

6. Rubbish: Combustible and noncombustible wastes such as paper, boxes, glass and crockery, metal and lumber scrap, tin cans, and bones.

7. Sanitary Wastes:

a. Sewage: Domestic sanitary sewage and human and animal waste.

b. Garbage: Refuse and scraps resulting from preparation, cooking, dispensing, and consumption of food.

1.2 QUALITY CONTROL

Establish and maintain quality control for the environmental protection of all items set forth herein.

Record on daily reports any problems in complying with laws, regulations, and ordinances. Note any corrective action taken.

1.3 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. National Archives and Records Administration (NARA):

33 CFR 328....................Definitions

1.4 SUBMITTALS

In accordance with Section, 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND

SAMPLES, furnish the following:

1. Environmental Protection Plan: After the contract is awarded and prior to the commencement of the work, the Contractor shall meet with the Contracting Officer’s Representative (COR) to discuss the proposed Environmental Protection Plan and to develop mutual understanding relative to details of environmental protection. Not more than 20 days after the meeting, the Contractor shall prepare and submit to the Contracting Officer for approval, a written and/or graphic Environmental Protection Plan including, but not limited to, the following:

a. Name(s) of person(s) within the Contractor's organization who is

(are) responsible for ensuring adherence to the Environmental

Protection Plan.

b. Name(s) and qualifications of person(s) responsible for manifesting hazardous waste to be removed from the site.

c. Name(s) and qualifications of person(s) responsible for training the Contractor's environmental protection personnel.

01 57 19 -3

d. Description of the Contractor's environmental protection personnel training program.

e. A list of Federal, State, and local laws, regulations, and permits concerning environmental protection, pollution control, noise control and abatement that are applicable to the

Contractor's proposed operations and the requirements imposed by those laws, regulations, and permits.

f. Methods for protection of features to be preserved within authorized work areas including trees, shrubs, vines, grasses, ground cover, landscape features, air and water quality, fish and wildlife, soil, historical, and archeological and cultural resources.

g. Procedures to provide the environmental protection that comply with the applicable laws and regulations. Describe the procedures to correct pollution of the environment due to accident, natural causes, or failure to follow the procedures as described in the

Environmental Protection Plan.

h. Permits, licenses, and the location of the solid waste disposal area.

i. Drawings showing locations of any proposed material storage areas, structures, sanitary facilities, and stockpiles of excess or spoil materials. Include as part of an Erosion Control Plan approved by the District Office of the U.S. Soil Conservation

Service and the Department of Veterans Affairs.

j. Environmental Monitoring Plans for the job site including land, water, air, and noise.

k. Work Area Plan showing the proposed activity in each portion of the area and identifying the areas of limited use or nonuse. Plan should include measures for marking the limits of use areas. This plan may be incorporated within the Erosion Control Plan.

l. Inclusion of “best management practices” and methodologies.

Approval of the Contractor's Environmental Protection Plan will not relieve the Contractor of responsibility for adequate and continued control of pollutants and other environmental protection measures.

1.5 PROTECTION OF ENVIRONMENTAL RESOURCES

Protect environmental resources within the project boundaries and those affected outside the limits of permanent work during the entire period

01 57 19 -4 of this contract. Confine activities to areas defined by the specifications and drawings.

Protection of Land Resources: Prior to construction, identify all land resources to be preserved within the work area. Do not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, grasses, topsoil, and landforms without permission from the COR.

Do not fasten or attach ropes, cables, or guys to trees for anchorage unless specifically authorized, or where special emergency use is permitted. Provide erosion control plans, in phases where required.

1. Work Area Limits: Prior to any construction, mark the areas that require work to be performed under this contract. Mark or fence isolated areas within the general work area that are to be saved and protected. Protect monuments, works of art, and markers before construction operations begin. Convey to all personnel the purpose of marking and protecting all necessary objects.

2. Protection of Landscape: Protect trees, shrubs, vines, grasses, land forms, and other landscape features shown on the drawings to be preserved by marking, fencing, or using any other approved techniques.

a. Box and protect from damage existing trees and shrubs to remain on the construction site.

b. Immediately repair all damage to existing trees and shrubs by trimming, cleaning, and painting with antiseptic tree paint.

c. Do not store building materials or perform construction activities closer to existing trees or shrubs than the farthest extension of their limbs.

3. Reduction of Exposure of Unprotected Erodible Soils: Plan and conduct earthwork to minimize the duration of exposure of unprotected soils. Clear areas in reasonably sized increments only as needed to use. Form earthwork to final grade as shown.

Immediately protect side slopes and back slopes upon completion of rough grading.

4. Temporary Protection of Disturbed Areas: Construct diversion ditches, benches, and berms to retard and divert runoff from the construction site to protected drainage areas approved under paragraph 208 of the Clean Water Act.

01 57 19 -5

a. Sediment Basins: Trap sediment from construction areas in temporary or permanent sediment basins that accommodate the runoff of a local 100______ (design year) storm. After each storm, pump the basins dry and remove the accumulated sediment.

Control overflow/drainage with paved weirs or by vertical overflow pipes, draining from the surface.

b. Reuse or conserve the collected topsoil sediment as directed by the COR. Topsoil use and requirements are specified in Section 31

20 00, EARTH MOVING.

c. Institute effluent quality monitoring programs as required by

Federal, State, and local environmental agencies.

5. Erosion and Sedimentation Control Devices: The erosion and sediment controls selected and maintained by the Contractor shall be such that water quality standards are not violated as a result of the

Contractor's activities. Construct or install all temporary and permanent erosion and sedimentation control features. on the

Environmental Protection Plan. Maintain temporary erosion and sediment control measures such as berms, dikes, drains, sedimentation basins, grassing, and mulching, until permanent drainage and erosion control facilities are completed and operative.

6. Manage borrow areas on and off Government property to minimize erosion and to prevent sediment from entering nearby water courses or lakes.

7. Manage and control spoil areas on Government property to limit spoil to areas on the Environmental Protection Plan and prevent erosion of soil or sediment from entering nearby water courses or lakes.

8. Protect adjacent areas from despoilment by temporary excavations and embankments.

9. Handle and dispose of solid wastes in such a manner that will prevent contamination of the environment. Place solid wastes

(excluding clearing debris) in containers that are emptied on a regular schedule. Transport all solid waste off Government property and dispose of waste in compliance with Federal, State, and local requirements.

10. Store chemical waste away from the work areas in corrosion resistant containers and dispose of waste in accordance with Federal, State, and local regulations.

01 57 19 -6

11. Handle discarded materials other than those included in the solid waste category as directed by the COR.

Protection of Water Resources: Keep construction activities under surveillance, management, and control to avoid pollution of surface and ground waters and sewer systems. Implement management techniques to control water pollution by the listed construction activities that are included in this contract.

1. Washing and Curing Water: Do not allow wastewater directly derived from construction activities to enter water areas. Collect and place wastewater in retention ponds allowing the suspended material to settle, the pollutants to separate, or the water to evaporate.

2. Control movement of materials and equipment at stream crossings during construction to prevent violation of water pollution control standards of the Federal, State, or local government.

3. Monitor water areas affected by construction.

Protection of Fish and Wildlife Resources: Keep construction activities under surveillance, management, and control to minimize interference with, disturbance of, or damage to fish and wildlife. Prior to beginning construction operations, list species that require specific attention along with measures for their protection.

Protection of Air Resources: Keep construction activities under surveillance, management, and control to minimize pollution of air resources. Burning is not permitted on the job site. Keep activities, equipment, processes, and work operated or performed, in strict accordance with the State of Minnesota Department of Agriculture &

Natural Resourses and Federal emission and performance laws and standards. Maintain ambient air quality standards set by the

Environmental Protection Agency, for those construction operations and activities specified.

1. Particulates: Control dust particles, aerosols, and gaseous by-products from all construction activities, processing, and preparation of materials (such as from asphaltic batch plants) at all times, including weekends, holidays, and hours when work is not in progress.

2. Particulates Control: Maintain all excavations, stockpiles, haul roads, permanent and temporary access roads, plant sites, spoil

01 57 19 -7 areas, borrow areas, and all other work areas within or outside the project boundaries free from particulates which would cause a hazard or a nuisance. Sprinklering, chemical treatment of an approved type, light bituminous treatment, baghouse, scrubbers, electrostatic precipitators, or other methods are permitted to control particulates in the work area.

3. Hydrocarbons and Carbon Monoxide: Control monoxide emissions from equipment to Federal and State allowable limits.

4. Odors: Control odors of construction activities and prevent obnoxious odors from occurring.

Reduction of Noise: Minimize noise using every action possible. Perform noise-producing work in less sensitive hours of the day or week as directed by the COR. Maintain noise-produced work at or below the decibel levels and within the time periods specified.

1. Perform construction activities involving repetitive, high-level impact noise only after normal business hours (7:00 a.m. to 5:00 p.m.) unless otherwise permitted by local ordinance or the COR.

Repetitive impact noise on the property shall not exceed the following dB limitations:

Time Duration of Impact Noise Sound Level in dB

More than 12 minutes in any hour 70

Less than 30 seconds of any hour 85

Less than three minutes of any hour 80

Less than 12 minutes of any hour 75

2. Provide sound-deadening devices on equipment and take noise abatement measures that are necessary to comply with the requirements of this contract, consisting of, but not limited to, the following:

a. Maintain maximum permissible construction equipment noise levels at 15 meter (50 feet) (dBA):

EARTHMOVING MATERIALS HANDLING

FRONT LOADERS 75 CONCRETE MIXERS 75

BACKHOES 75 CONCRETE PUMPS 75

DOZERS 75 CRANES 75

TRACTORS 75 DERRICKS IMPACT 75

SCAPERS 80 PILE DRIVERS 95

01 57 19 -8

GRADERS 75 JACK HAMMERS 75

TRUCKS 75 ROCK DRILLS 80

PAVERS, STATIONARY 80 PNEUMATIC TOOLS 80

PUMPS 75

GENERATORS 75 SAWS 75

COMPRESSORS 75 VIBRATORS 75

b. Use shields or other physical barriers to restrict noise transmission.

c. Provide soundproof housings or enclosures for noise-producing machinery.

d. Use efficient silencers on equipment air intakes.

e. Use efficient intake and exhaust mufflers on internal combustion engines that are maintained so equipment performs below noise levels specified.

f. Line hoppers and storage bins with sound deadening material.

g. Conduct truck loading, unloading, and hauling operations so that noise is kept to a minimum.

3. Measure sound level for noise exposure due to the construction at least once every five successive working days while work is being performed above 55 dB(A) noise level. Measure noise exposure at the property line or 15 m (50 feet) from the noise source, whichever is greater. Measure the sound levels on the A weighing network of a

General Purpose sound level meter at slow response. To minimize the effect of reflective sound waves at buildings, take measurements at

900 to 1800 mm (three to six feet) in front of any building face.

Submit the recorded information to the COR noting any problems and the alternatives for mitigating actions.

Restoration of Damaged Property: If any direct or indirect damage is done to public or private property resulting from any act, omission, neglect, or misconduct, the Contractor shall restore the damaged property to a condition equal to that existing before the damage at no additional cost to the Government. Repair, rebuild, or restore property as directed or make good such damage in an acceptable manner.

Final Clean-up: On completion of project and after removal of all debris, rubbish, and temporary construction, Contractor shall leave the construction area in a clean condition satisfactory to the COR.

01 57 19 -9

Cleaning shall include off the station disposal of all items and materials not required to be salvaged, as well as all debris and rubbish resulting from demolition and new work operations.

- - - E N D - - -

1 Veterans Drive Addendum #1

Minneapolis, MN 55417 08-01-18

05 50 00- 1

SECTION 05 50 00

METAL FABRICATIONS

SPEC WRITER NOTE:

PART 1 - GENERAL

1.1 DESCRIPTION

A. This section specifies items and assemblies fabricated from structural steel shapes and other materials as shown and specified.

B. Items specified.

1. Support for Wall and Ceiling Mounted Items: (SD055000-01, SD055000-02, SD102113-01, SD102600-01, SD123100-01 &

SD123100-02)

2. Frames:

3. Guards

4. Covers and Frames for Pits and Trenches.

5. Gratings

6. Loose Lintels

7. Shelf Angles

8. Plate Door Sill

9. Safety Nosings

10. Screened Access Doors

11. Steel Counter or Bench Top Frame and Leg

12. Steel Pipe Bollards

1.2 RELATED WORK

A. Colors, finishes, and textures: Section 09 06 00, SCHEDULE FOR

FINISHES.

B. Prime and finish painting: Section 09 91 00, PAINTING.

C. Stainless steel corner guards: Section 10 26 00, WALL AND DOOR

PROTECTION.

1.3 SUBMITTALS

A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT

DATA, AND SAMPLES.

B. Manufacturer's Literature and Data:

Grating, each type Floor plate

Trap door Wheel guards

Ceiling hatch Sidewalk Access door

Manhole Covers Safety nosing

1 Veterans Drive Addendum #1

Minneapolis, MN 55417 08-01-18

05 50 00- 2

C. Shop Drawings:

1. Each item specified, showing complete detail, location in the project, material and size of components, method of joining various components and assemblies, finish, and location, size and type of anchors.

2. Mark items requiring field assembly for erection identification and furnish erection drawings and instructions.

3. Provide templates and rough-in measurements as required.

D. Manufacturer's Certificates:

1. Anodized finish as specified.

2. Live load designs as specified.

E. Design Calculations for specified live loads including dead loads.

F. Furnish setting drawings and instructions for installation of anchors to be preset into concrete and masonry work, and for the positioning of items having anchors to be built into concrete or masonry construction.

1.4 QUALITY ASSURANCE

A. Each manufactured product shall meet, as a minimum, the requirements specified, and shall be a standard commercial product of a manufacturer regularly presently manufacturing items of type specified.

B. Each product type shall be the same and be made by the same manufacturer.

C. Assembled product to the greatest extent possible before delivery to the site.

D. Include additional features, which are not specifically prohibited by this specification, but which are a part of the manufacturer's standard commercial product.

1.5 APPLICABLE PUBLICATIONS

A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.

B. American Society of Mechanical Engineers (ASME):

B18.6.1-97..............Wood Screws

B18.2.2-87(R2010).......Square and Hex Nuts

C. American Society for Testing and Materials (ASTM):

A36/A36M-14.............Structural Steel

A47-99(R2014)...........Malleable Iron Castings

1 Veterans Drive Addendum #1

Minneapolis, MN 55417 08-01-18

05 50 00- 3

A48-03(R2012)...........Gray Iron Castings

A53-12..................Pipe, Steel, Black and Hot-Dipped, Zinc-Coated

Welded and Seamless

A123-15.................Zinc (Hot-Dip Galvanized) Coatings on Iron and

Steel Products

A240/A240M-15...........Standard Specification for Chromium and

Chromium-Nickel Stainless Steel Plate, Sheet and Strip for Pressure Vessels and for General

Applications.

A269-15.................Seamless and Welded Austenitic Stainless Steel

Tubing for General Service

A307-14.................Carbon Steel Bolts and Studs, 60,000 PSI

Tensile Strength

A391/A391M-07(R2015)....Grade 80 Alloy Steel Chain

A786/A786M-15...........Rolled Steel Floor Plate

B221-14.................Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Shapes, and Tubes

B456-11.................Electrodeposited Coatings of Copper Plus Nickel

Plus Chromium and Nickel Plus Chromium

B632-08.................Aluminum-Alloy Rolled Tread Plate

C1107-13................Packaged Dry, Hydraulic-Cement Grout

(Nonshrink)

D3656-13................Insect Screening and Louver Cloth Woven from

Vinyl-Coated Glass Yarns

F436-16.................Hardened Steel Washers

F468-06(R2015)..........Nonferrous Bolts, Hex Cap Screws, Socket Head

Cap Screws and Studs for General Use

F593-13.................Stainless Steel Bolts, Hex Cap Screws, and

Studs

F1667-15................Driven Fasteners: Nails, Spikes and Staples

D. American Welding Society (AWS):

D1.1-15.................Structural Welding Code Steel

D1.2-14.................Structural Welding Code Aluminum

D1.3-18.................Structural Welding Code Sheet Steel

E. National Association of Architectural Metal Manufacturers (NAAMM)

AMP 521-01(R2012).......Pipe Railing Manual

AMP 500-06..............Metal Finishes Manual

1 Veterans Drive Addendum #1

Minneapolis, MN 55417 08-01-18

05 50 00- 4

MBG 531-09(R2017).......Metal Bar Grating Manual

MBG 532-09..............Heavy Duty Metal Bar Grating Manual

F. Structural Steel Painting Council (SSPC)/Society of Protective

Coatings:

SP 1-15.................No. 1, Solvent Cleaning

SP 2-04.................No. 2, Hand Tool Cleaning

SP 3-04.................No. 3, Power Tool Cleaning

G. Federal Specifications (Fed. Spec):

RR-T-650E...............Treads, Metallic and Nonmetallic, Nonskid

PART 2 - PRODUCTS

2.1 DESIGN CRITERIA

A. In addition to the dead loads, design fabrications to support the following live loads unless otherwise specified.

C. Railings and Handrails: 900 N (200 pounds) in any direction at any point.

2.2 MATERIALS

A. Structural Steel: ASTM A36.

B. Stainless Steel: ASTM A240, Type 302 or 304.

C. Aluminum, Extruded: ASTM B221, Alloy 6063-T5 unless otherwise specified. For structural shapes use alloy 6061-T6 and alloy 6061-

T4511.

D. Floor Plate:

1. Steel ASTM A786.

2. Aluminum: ASTM B632.

E. Steel Pipe (Bollard): ASTM A53.

1. Galvanized for exterior locations.

2. Type S, Grade A unless specified otherwise.

3. NPS (inside diameter) as shown.

F. Cast-Iron: ASTM A48, Class 30, commercial pattern.

G. Malleable Iron Castings: A47.

H. Primer Paint: As specified in Section 09 91 00, PAINTING.

I. Stainless Steel Tubing: ASTM A269, type 302 or 304.

J. Modular Channel Units:

1. Factory fabricated, channel shaped, cold formed sheet steel shapes, complete with fittings bolts and nuts required for assembly.

2. Form channel within turned pyramid shaped clamping ridges on each side.

1 Veterans Drive Addendum #1

Minneapolis, MN 55417 08-01-18

05 50 00- 5

3. Provide case hardened steel nuts with serrated grooves in the top edges designed to be inserted in the channel at any point and be given a quarter turn so as to engage the channel clamping ridges.

Provide each nut with a spring designed to hold the nut in place.

4. Factory finish channels and parts with oven baked primer when exposed to view. Channels fabricated of ASTM A525, G90 galvanized steel may have primer omitted in concealed locations. Finish screws and nuts with zinc coating.

5. Fabricate snap-in closure plates to fit and close exposed channel openings of not more than 0.3 mm (0.0125 inch) thick stainless steel.

K. Grout: ASTM C1107, pourable type.

L. Insect Screening: ASTM D3656.

2.3 HARDWARE

A. Rough Hardware:

1. Furnish rough hardware with a standard plating, applied after punching, forming and assembly of parts; galvanized, cadmium plated, or zinc-coated by electro-galvanizing process. Galvanized G-90 where specified.

2. Use G90 galvanized coating on ferrous metal for exterior work unless non-ferrous metal or stainless is used.

B. Fasteners:

1. Bolts with Nuts:

a. ASME B18.2.2.

b. ASTM A307 for 415 MPa (60,000 psi) tensile strength bolts.

c. ASTM F468 for nonferrous bolts.

d. ASTM F593 for stainless steel.

2. Screws: ASME B18.6.1.

3. Washers: ASTM F436, type to suit material and anchorage.

4. Nails: ASTM F1667, Type I, style 6 or 14 for finish work.

2.4 FABRICATION GENERAL

A. Material

1. Use material as specified. Use material of commercial quality and suitable for intended purpose for material that is not named or its standard of quality not specified.

2. Use material free of defects which could affect the appearance or service ability of the finished product.

1 Veterans Drive Addendum #1

Minneapolis, MN 55417 08-01-18

05 50 00- 6

B. Size:

1. Size and thickness of members as shown.

2. When size and thickness is not specified or shown for an individual part, use size and thickness not less than that used for the same component on similar standard commercial items or in accordance with established shop methods.

C. Connections

1. Except as otherwise specified, connections may be made by welding, riveting or bolting.

2. Field riveting will not be approved.

3. Design size, number and placement of fasteners, to develop a joint strength of not less than the design value.

4. Holes, for rivets and bolts: Accurately punched or drilled and burrs removed.

5. Size and shape welds to develop the full design strength of the parts connected by welds and to transmit imposed stresses without permanent deformation or failure when subject to service loadings.

6. Use Rivets and bolts of material selected to prevent corrosion

(electrolysis) at bimetallic contacts. Plated or coated material will not be approved.

7. Use stainless steel connectors for removable members machine screws or bolts.

D. Fasteners and Anchors

1. Use methods for fastening or anchoring metal fabrications to building construction as shown or specified.

2. Where fasteners and anchors are not shown, design the type, size, location and spacing to resist the loads imposed without deformation of the members or causing failure of the anchor or fastener, and suit the sequence of installation.

3. Use material and finish of the fasteners compatible with the kinds of materials which are fastened together and their location in the finished work.

4. Fasteners for securing metal fabrications to new construction only, may be by use of threaded or wedge type inserts or by anchors for welding to the metal fabrication for installation before the concrete is placed or as masonry is laid.

1 Veterans Drive Addendum #1

Minneapolis, MN 55417 08-01-18

05 50 00- 7

5. Fasteners for securing metal fabrication to existing construction or new construction may be expansion bolts, toggle bolts, power actuated drive pins, welding, self drilling and tapping screws or bolts.

E. Workmanship

1. General:

a. Fabricate items to design shown.

b. Furnish members in longest lengths commercially available within the limits shown and specified.

c. Fabricate straight, true, free from warp and twist, and where applicable square and in same plane.

d. Provide holes, sinkages and reinforcement shown and required for fasteners and anchorage items.

e. Provide openings, cut-outs, and tapped holes for attachment and clearances required for work of other trades.

f. Prepare members for the installation and fitting of hardware.

g. Cut openings in gratings and floor plates for the passage of ducts, sumps, pipes, conduits and similar items. Provide reinforcement to support cut edges.

h. Fabricate surfaces and edges free from sharp edges, burrs and projections which may cause injury.

2. Welding:

a. Weld in accordance with AWS.

b. Welds shall show good fusion, be free from cracks and porosity and accomplish secure and rigid joints in proper alignment.

c. Where exposed in the finished work, continuous weld for the full length of the members joined and have depressed areas filled and protruding welds finished smooth and flush with adjacent surfaces.

d. Finish welded joints to match finish of adjacent surface.

3. Joining:

a. Miter or butt members at corners.

b. Where frames members are butted at corners, cut leg of frame member perpendicular to surface, as required for clearance.

4. Anchors:

a. Where metal fabrications are shown to be preset in concrete, weld

32 x 3 mm (1-1/4 by 1/8 inch) steel strap anchors, 150 mm (6

1 Veterans Drive Addendum #1

Minneapolis, MN 55417 08-01-18

05 50 00- 8 inches) long with 25 mm (one inch) hooked end, to back of member at 600 mm (2 feet) on center, unless otherwise shown.

b. Where metal fabrications are shown to be built into masonry use

32 x 3 mm (1-1/4 by 1/8 inch) steel strap anchors, 250 mm (10 inches) long with 50 mm (2 inch) hooked end, welded to back of member at 600 mm (2 feet) on center, unless otherwise shown.

5. Cutting and Fitting:

a. Accurately cut, machine and fit joints, corners, copes, and miters.

b. Fit removable members to be easily removed.

c. Design and construct field connections in the most practical place for appearance and ease of installation.

d. Fit pieces together as required.

e. Fabricate connections for ease of assembly and disassembly without use of special tools.

f. Joints firm when assembled.

g. Conceal joining, fitting and welding on exposed work as far as practical.

h. Do not show rivets and screws prominently on the exposed face.

i. The fit of components and the alignment of holes shall eliminate the need to modify component or to use exceptional force in the assembly of item and eliminate the need to use other than common tools.

F. Finish:

1. Finish exposed surfaces in accordance with NAAMM AMP 500 Metal

Finishes Manual.

2. Aluminum: NAAMM AMP 501.

a. Mill finish, AA-M10, as fabricated, use unless specified otherwise.

b. Clear anodic coating, AA-C22A41, chemically etched medium matte, with Architectural Class 1, 0.7 mils or thicker.

c. Colored anodic coating, AA-C22A42, chemically etched medium matte with Architectural Class 1, 0.7 mils or thicker.

d. Painted: AA-C22R10.

3. Steel and Iron: NAAMM AMP 504.

a. Zinc coated (Galvanized): ASTM A123, G90 unless noted otherwise.

b. Surfaces exposed in the finished work:

1 Veterans Drive Addendum #1

Minneapolis, MN 55417 08-01-18

05 50 00- 9

1) Finish smooth rough surfaces and remove projections.

2) Fill holes, dents and similar voids and depressions with epoxy type patching compound.

c. Shop Prime Painting:

1) Surfaces of Ferrous metal:

a) Items not specified to have other coatings.

b) Galvanized surfaces specified to have prime paint.

c) Remove all loose mill scale, rust, and paint, by hand or power tool cleaning as defined in SSPC-SP2 and SP3.

d) Clean of oil, grease, soil and other detrimental matter by use of solvents or cleaning compounds as defined in SSPC-

SP1.

e) After cleaning and finishing apply one coat of primer as specified in Section 09 91 00, PAINTING.

2) Non ferrous metals: Comply with MAAMM-500 series.

4. Stainless Steel: NAAMM AMP-504 Finish No. 4.

SPEC WRITER NOTE: Specify items to receive chromium plating.

5. Chromium Plating: ASTM B456, satin or bright as specified, Service

Condition No. SC2.

G. Protection:

1. Insulate aluminum surfaces that will come in contact with concrete, masonry, plaster, or metals other than stainless steel, zinc or white bronze by giving a coat of heavy-bodied alkali resisting bituminous paint or other approved paint in shop.

2. Spot prime all abraded and damaged areas of zinc coating which expose the bare metal, using zinc rich paint on hot-dip zinc coat items and zinc dust primer on all other zinc coated items.

2.5 SUPPORTS

A. General:

1. Fabricate ASTM A36 structural steel shapes as shown.

2. Use clip angles or make provisions for welding hangers and braces to overhead construction.

3. Field connections may be welded or bolted.

B. For Ceiling Hung Toilet Stall:

1. Use a continuous steel channel above pilasters with hangers centered over pilasters.

1 Veterans Drive Addendum #1

Minneapolis, MN 55417 08-01-18

05 50 00- 10

2. Make provision for installation of stud bolts in lower flange of channel.

3. Provide a continuous steel angle at wall and channel braces spaced as shown.

4. Use threaded rod hangers.

5. Provide diagonal angle brace where the suspended ceiling over toilet stalls does not extend to side wall of room.

6. Provide supports for ceiling hung pilasters at dressing booths and entrance screen to toilet room similar to support for toilet stall pilasters.

C. For Wall Mounted Items:

1. For items supported by metal stud partitions.

2. Steel strip or hat channel minimum of 1.5 mm (0.0598 inch) thick.

3. Steel strip minimum of 150 mm (6 inches) wide, length extending one stud space beyond end of item supported.

4. Steel hat channels where shown. Flange cut and flatted for anchorage to stud.

5. Structural steel tube or channel for grab bar at water closets floor to structure above with clip angles or end plates formed for anchors.

6. Use steel angles for thru wall counters. Drill angle for fasteners at ends and not over 100 mm (4 inches) on center between ends.

2.6 FRAMES

B. Channel Door Frames:

1. Fabricate of structural steel channels of size shown.

2. Miter and weld frames at corners.

3. Where anchored to masonry or embedded in concrete, weld to back of frame at each jamb, 5 mm (3/16 inch) thick by 44 mm (1-3/4 inch) wide steel strap anchors with ends turned 50 mm (2 inches), and of sufficient length to extend at least 300 mm (12 inches) into wall.

Space anchors 600 mm (24 inches) above bottom of frame and 600 mm

(24 inches) o.c. to top of jamb. Weld clip angles to bottom of jambs and provide holes for expansion bolts.

4. Where anchored to concrete or masonry in prepared openings, drill holes at jambs for anchoring with expansion bolts. Weld clip angles to bottom of frame and provide holes for expansion bolt anchors as shown. Drill holes starting 600 mm (24 inches) above bottom of frame

1 Veterans Drive Addendum #1

Minneapolis, MN 55417 08-01-18

05 50 00- 11 and 600 mm (24 inches) o.c. to top of jamb and at top of jamb.

Provide pipe spacers at holes welded to channel.

5. Where closure plates are shown, continuously weld them to the channel flanges.

6. Weld continuous 19 x 19 x 3 mm (3/4 x 3/4 x 1/8 inch) thick steel angles to the interior side of each channel leg at the head and jambs to form a caulking groove.

7. Prepare frame for installation of hardware specified in Section 08

71 00, DOOR HARDWARE.

a. Cut a slot in the lock jamb to receive the lock bolt.

b. Where shown use continuous solid steel bar stops at perimeter of frame, weld or secure with countersunk machine screws at not more than 450 mm (18 inches) on center.

7. Type 15 Door Frames:

a. Structural steel angle frames with plate or bar full height to heads. Extend reinforcing at hinge cutouts two inches beyond cutout.

b. Fabricate top anchorage to beam side at mid height.

c. Weld clip angles to both legs of angle at top and bottom.

d. Drill clips and plates, at top and bottom for anchoring jamb angles with two 9 mm (3/8 inch) expansion bolts at each location.

e. Cut rabbet for pivot hinges and lock strike.

2.7 GUARDS

A. Wall Corner Guards:

1. Fabricate from steel angles and furnish with anchors as shown.

2. Continuously weld anchor to angle.

B. Edge Guard Angles for Openings in slabs.

1. Fabricate from steel angles of sizes and with anchorage shown.

2. Where size of angle is not shown, provide 50 x 50 x 6 mm (2 x 2 x

1/4 inch) steel angle with 32 x 5 mm (1-1/4 x 3/16 inch) strap anchors, welded to back.

3. Miter or butt angles at corners and weld.

4. Use one anchor near end and three feet on centers between end anchors.

C. Wheel Guards:

1. Construct wheel guards of not less than 16 mm (5/8 inch) thick cast iron.

1 Veterans Drive Addendum #1

Minneapolis, MN 55417 08-01-18

05 50 00- 12

2. Provide corner type, with flanges for bolting to walls.

2.8 COVERS AND FRAMES FOR PITS AND TRENCHES

A. Fabricate covers to support live loads specified.

B. Galvanized steel members after fabrication in accordance with ASTM

A123, G-90 coating.

C. Steel Covers:

1. Use 6 mm (1/4 inch) thick floor plate for covers unless otherwise shown. Use gratings where shown as specified in paragraph GRATINGS.

Use smooth floor plate unless noted otherwise.

2. Provide clearance at all sides to permit easy removal of covers.

3. Make cutouts within 6 mm (1/4 inch) of penetration for passage of pipes and…