RFI LOG UPDATE AMENDMENT 005.xlsx
XLSX spreadsheet 23 KB Posted
- Solicitation number
- 36C26126R0028
About this file
This is a Request for Information (RFI) Log Update Amendment 005 document containing 34 clarification questions and answers related to a federal construction solicitation for chilled water infrastructure replacement and expansion at a Department of Veterans Affairs facility in Fresno, California (Project No. 570-20-308, Solicitation No. 36C26126R0028). The solicitation closing date is July 29, 2026 at 11:00 AM Pacific Time.
The RFI responses address critical technical, scheduling, and administrative requirements for bidders. Technical clarifications include confirmation that CPM schedules are required and will be excluded from page count, specifications for fire sprinkler system modifications limited to 1,500 head adjustments with no full system redesign required, and detailed corrections to mechanical drawings including pipe sizing on chilled water systems, fan coil unit schedules, and building automation control point schedules. Scheduling clarifications confirm work hours are Monday through Friday 7:00 AM to 4:00 PM on a standard 40-hour week, with after-hours and weekend work to be addressed as needed; patients remain on the 5th floor East/West and 6th floor East Wing 24/7. Procurement clarifications cover asbestos abatement budgeted at $500,000 as a separate line item, pump specifications governed by updated drawing M-601 (four total pumps including N+1 standby), temporary piping requirements per updated drawings, and confirmation that the Commissioning Agent will be provided by the VA while the contractor provides all support. Administrative responses clarify email subject line formatting for proposal submissions, definitions of "similar scope and complexity" as projects consisting primarily of chilled water systems, elimination of letters of intent for current employees, confirmation that Key Personnel project experience may span 10 years from solicitation issuance, and that FAR 52.209-5 representation and certification is no longer applicable due to recent FAR changes.
View the file
Other files
Show all 47
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| 36C26126R0028 Amendment 005 | ||
| RFI No. | Question | Response |
| 1 | “Factor III Schedule Phasing Management. The Section M paragraph 3 evaluation states “provide a phased schedule with a synopsis as to how the work will be accomplished within a 915-day period of performance.” Is a CPM graphical Schedule required? | Yes, a CPM schedule will suffice for this submission |
| 2 | Factor II Schedule Phasing Management. The Section M paragraph evaluation states "provide a phased schedule with a synopsis as to how the work will be accomplished within a 915 day period of performance. Is a CPM graphical Schedule required and exclude from page count? | Yes, a CPM schedule will suffice for this submission |
| and we will exclude from the page count. |
| 3 | Factor III Schedule Phasing Management. The Section M paragraph 3 evaluation states “provide a phased schedule with a synopsis as to how the work will be accomplished within a 915-day period of performance.” Is a CPM schedule required and allowed to be 11x17 and that page size count as 1 page (not 2)? | Yes, a CPM schedule will suffice for this submission |
| we will remove the schedule from the page count. |
| 4 | See uestion Attachment RFI 4 | Response: Contractor shall assume $500,000.00 for |
| asbestos abatement as a sepearate line item on price | ||
| break down sheet. Any unused portion shall be credited | ||
| back to the VA. Any additional required shall be a modification | ||
| to the contract. |
| 5 | Specification Section 21 13 13, Wet-Pipe Sprinkler Systems, states that the work consists of modifications to the existing sprinkler system as required to facilitate the project, that such modifications shall be limited and only required to support the installation of new work, and shall include selective demolition and minimal new work to restore existing conditions impacted by the project (Section 21 13 13, 1.1.B, 1.1.C, and 1.1.D). Please confirm that the existing fire sprinkler system is to remain in place and that only minor modifications are required to accommodate the new work under this contract. new work under this contract. | |
| Where sections of the existing ceiling are removed to perform the new work, please confirm whether the existing pendent sprinkler heads in those areas are to be reworked / turned up to the upright (vertical) position, and confirm the extent of any such head relocation or reorientation to be included in the bid. Please also confirm that any heads disturbed by the ceiling demolition are to be reinstalled to restore the existing conditions, consistent with Section 21 13 13, 1.1.D. Please confirm that the Contractor is not required to perform any new fire sprinkler system design, engineered sprinkler layout, or hydraulic calculations for this project. Section 21 13 13, 1.3.A.3 states “Hydraulic Calculations: Not required based on scope of work. Modifications to the existing sprinkler system shall be based on the pipe schedule of the existing system.” We understand this to mean the work is limited to modifications based on the existing system’s pipe schedule, working drawings are not required and that no full system design or hydraulic modeling is required. Please confirm this understanding is correct | 1. The work consists of modifications to the existing sprinkler system as required to facilitate the project, that such modifications shall be limited and only required to support the installation of new work, and shall include selective demolition and minimal new work to restore existing conditions impacted by the project. This project does not replace the fire sprinkler system or otherwise provide upgrades to the system. 2. Provide interim life safety measures to provide protection during construction. See 01 35 26 Safety Requirements. Comply with NFPA 13 requirements for sprinklers that are removed. A sprinkler that is removed from its fitting is required to be replaced. 3.The building is hydraulically calculated. Where modifications are proposed that increase the pressure requirements, calculations are to be expected as a requirement. Where sprinklers are moved to the next ceiling tile to accommodate other work, this minor modification is not anticipated to cause a requirement for calculations. Fire sprinkler design (shop submittals) will be required where modifications are necessary to facilitate the other scopes of work. |
6 The SOW states normal hours of operation are 7:00 AM to 4:00 PM, Monday through Friday, and that utility shutdowns require 72-hour (minor) to two-week (major) advance coordination. Because Building 1 remains a fully operating hospital, please provide the allowable working hours for each type of occupied area affected by the work — for example, Clinics, ICU, Kitchen, and the 7th Floor Administration area. A floor-by-floor breakdown of permitted working hours and access restrictions would be very helpful for planning, phasing, and pricing. Will weekend work be required on a regular basis in any of these areas? Please confirm so that after-hours and weekend labor premiums can be appropriately reflected in the base bid and the schedule. In our opinion, many areas will have to be vacated in phases during the work. A significant portion of the work is located in the hallways, and for patient safety and other practical considerations we believe that access to the adjacent patient rooms, clinics, and other occupied spaces will be impractical and unsafe while construction operations are underway in those corridors. Please confirm the VA’s expectations for temporary relocation / decanting of these spaces and how phasing is to be coordinated with ongoing hospital operations. We anticipate that the Laboratory and surrounding areas will be highly impacted by the work. What move-out and phasing can be expected for the Lab — for example, will the Lab be relocated or temporarily or partially taken out of service, and what sequencing, duration, and interim life-safety measures does the VA anticipate for that area? For the purposes of the price proposal, work hours will be Monday through Friday 7:00 AM to 4:00 PM (corrected), or other established daytime 40 hour week. Any after-hours/weekend work will be addressed as the need arises. The facility will address this matter at each phase.
7 See Question Attachment RFI 7 Typically, construction is Commercial of The Shelf (COTS) parts, and that is an exception to the Buy American Act. Unless you have an item that is specifically manufactured for this project.
8 Drawings MP-901 (Mechanical Piping) and M-701 (Mechanical) show the chilled water piping layout, but the pipe size designations (line sizes/diameters) are not entered on the drawings. Pipe sizes are required to properly size all valves, complete material take-offs, confirm equipment connection sizes, and verify pressure drop and pump sizing, and they directly affect procurement quantities and price. Please enter/provide the pipe sizes on Drawings MP-901 and M-701, specifically:
(a) the line size for each segment of the chilled water supply and return mains shown on each drawing;
(b) the branch and runout sizes serving each equipment connection; and
(c) any size transitions/reducers and tie-in sizes to existing piping that are not currently called out.
Please issue revised/marked-up MP-901 and M-701 with the pipe sizes shown, or a schedule keyed to each drawing. Absent these sizes, valves cannot be properly sized and the hydronic piping scope cannot be accurately quantified or priced. Riser pipe dimensions have been added to sheet MP901. Lateral pipe dimensions are found on the individual floors. See Updates Attached - Dav Energy Solutions
| 9 | The Fan Coil Unit Schedule (Drawing M-601, 24 units) and the Chilled Water Cooling Coil Schedule (Drawing M-602, 72 coils) show the capacity, CFM, and GPM fields largely blank, with notes directing the contractor to replace units “like-for-like” and to “perform airflow measurement on each unit prior to demolition and match new unit flow to existing.” Under a design-bid-build delivery method, the Architect/Engineer of Record is responsible for providing the equipment performance data; selecting and sizing equipment from field measurements is design-build scope and cannot be performed during the bid period. It is impossible to accurately price the Fan Coil Units and Chilled Water Cooling Coils without the missing performance information. Accordingly, please provide complete, scheduled performance data for each unit and coil so the equipment can be bid, including: total and sensible cooling capacity (MBH); heating capacity, if applicable; CFM; entering/leaving air temperatures; GPM; entering/leaving water temperatures; water-side pressure drop; fluid type; coil rows/fins and connection sizes; fan motor HP and electrical characteristics; and the model/basis-of-design selection. Absent the missing schedule data, bidders cannot price the Fan Coil Units and Chilled Water Cooling Coils on a fixed-price basis. |
| See updated schedules on sheets M-601 and M-602. It remains the contractor responsibility to field verify the values in the table during the construction phase and replace like-for-like. |
10 Drawings M-703 (Pump Control Point Schedule) and M-705 (Seasonal Change Over Valve Control Point Schedule) are essentially blank — the schedule headings are shown, but the control points and associated data are not filled in. Without this information the HVAC controls/DDC scope cannot be quantified or priced (the point count directly drives controller, input/output, wiring, and programming costs) and the control sequences cannot be implemented. This is a design-bid-build project; the completed control point schedules are required from the Architect/Engineer of Record in order to bid. Please provide the completed M-703 Pump Control Point Schedule and M-705 Seasonal Change Over Valve Control Point Schedule, including for each point: point name/description; point type (AI, AO, BI, BO); signal type/range; whether the point is hardwired or obtained via network/integration; setpoints and alarm limits; the associated equipment or device; and any interlocks. Please also provide the associated sequences of operation for the pumps and the seasonal changeover valves so the points list can be reconciled with the intended control sequence. Absent the completed control point schedules, bidders cannot accurately price the building automation/DDC controls for the pumps and seasonal changeover valves on a fixed-price basis. See updated sheets M-703 and M-705 in Bulletin 1 issued July 1, 2026
11 The Statement of Work (Work Required – MEP / Mechanical) calls for “two or more new 10-HP” and “two or more new 25-HP” chilled water pumps. However, the Pump Schedule on Drawing M-601 lists P-KCOIL at 2,020 GPM / 60 HP (two pumps, including N+1 standby) and P-ZONE at 730 GPM / 20 HP (two pumps, including N+1 standby), all variable-speed, 460V/3-phase, with NEMA premium-efficiency motors. Please confirm the M-601 Pump Schedule governs for pricing, including the motor horsepower, the total pump quantity (four pumps plus standby), and the VFD requirement. See updated pump schedules on sheet M-601 in Bulletin 1, issued July 1, 2026. Contract documents (drawings and specifications) govern.
12 See Question Attachment RFI 12 Update sheets MP101A-1 and MP101B-1 in Bulletin 1 issued July 1, 2025 show a diagramatic layout for the required temporary piping. All risers will be required to be maintained operational until the system is fully transitioned to the new risers. Updated schedule on M-601 details the requirements for the two (2) temporary pumps.
13 May we have an As-built for the Canopy that is currently holding and carrying the chilled water? Yes, As Buils are attached in 2 parts
14 Will we have to cut through hard lid ceiling in the kitchen. Has that ceiling been tested for Asbestos? The In-Scope Kitchen Area is ceiling tile. The Asbestos report does not have any information on the ceiling . The grout on the floor was negative
15 Will we need to submit a phasing plan as part of our technical proposal A technical phasing plan is not required for proposal.
16 Which areas of the hospital will need to be worked on after hours? For the purpose of the proposal plan on standard daylight hours.
We will modify contract for any after hour work as the need arises
17 Which floors of the hospital will have patients there 24/7 and what should we plan to schedule for those floors 5th floor East and West wing, 6th floor East Wing. For the purpose of Bidding plan on standard day light hours. We will modify the contract for any after hour work as the need arises.
18 May you be able to add as-builts for all 7 floors of the Fresno VA? AS Builts of the facility are available for refrence only. It's the contractors responsibility to verify site conditions
19 How do we account for the mental health ward Accounabilty of tools and persons must be maintained at all times. Tools and fastenters must be accounted for at all times. Check in with Nursing station to log tools, persons and equipment at all time.
20 Do you have roof drawings or plans for this project? Please see Bulletin 01 issued on July 01, Roof Demo Drawings and notes were added to Sheets AD108A and AD109B. New work Roof Drawings and notes are included with Sheets AE108B and AE109B.
21 Per Spec section 23 08 00.1.1 and 26 08 00.1.1: The commissioning process, which the Contractor is responsible for executing, is defined in Section 01 91 00 GENERAL COMMISSIONING REQUIRMENTS. A Commissioning Agent (CxA) appointed by the VA will manage the commissioning process. Will the general contractor be providing commissioning or will the VA provide? The VA is to provide the CxA and the contractor is to provide all support. Please see specification section 01 9100.
22 Can you provide specs for 01 91 00? It is included in the table of contents but there are no specs for commissioning. See the specification section attached as well as a revised bid specification set with the inserted 01 9100 section.
23 Reference Instructions to Bidders/Offerors, Section 3 Submission Instructions on RFP Page 16: Item a. states, “The subject line of the email must be cited RFP: 36C26126R0028.” However, Item d. states, “Offerors MUST mark the subject line of the email as 36C26126R0028 Replace and Expand Chilled Water Infrastructure Technical Proposal and 36C26126R0028 Replace and Expand Chilled Water Infrastructure Price Proposal.” Please clarify The email(s) can be 36C26126R0028 Price Proposal and 36C26126R0028 Technical Proposal. If both items are sent in the same email please mark 36C26126R0028 Price and Technical Proposal.
24 Reference Instructions to Bidders/Offerors, Section 7, Item b. on RFP Page 18: Item b. states, “Similar scope and complexity, when referred to in the evaluation factors, is defined as projects that consist primarily with Modular Swing spaces, HVAC, Flooring (same type) and trailer swing space components, modernization, repair, and maintenance.” The provided definition of similar scope and complexity seems to be for a different project/scope. Please confirm the definition of similar scope and complexity as it pertains to this “Repair and Expand Chilled Water Infrastructure” project. Segement shall be corrected to to read : 18 item b. Similar scope and complexity, when referred to in the evaluation factors, is defined as projects that consist primarily with chilled water systems.
25 Instructions to Bidders/Offerors, Section 7, Item f. on RFP Page 18 outlines the information required for the letter of intent for Current Employees, but then states, “**Letters of Commitment/Intent are only required for those personnel being hired specifically for the project and are not current employees. A letter is not required for current employees.” Please confirm a letter of intent is not required for current employees. Confirmed. Letter intent is not required for current employees.
26 Instructions to Bidders/Offerors, Section 7, Item g. on RFP pages 18/19 states to provide the following information on the cover for the Price Volume: “Renovate and Expand Chilled Water Infrastructure”. For consistency with the project title and Technical Volume cover requirements, please confirm this should be “Replace and Expand Chilled Water Infrastructure”. Please see response for RFI 23: The email(s) can be 36C26126R0028 Price Proposal and 36C26126R0028 Technical Proposal. If both items are sent in the same email please mark 36C26126R0028 Price and Technical Proposal.
27 Instructions to Bidders/Offerors, Section 7, Item g. on RFP Page 19 under BINDER INDEX, Tab 2, it states, “Cost Break-Out Sheet (fully completed) for each project 612A4-25-004”. Please confirm this should be for Project No. 570-20-308. Confirmed this project is 570-20-308
28 Instructions to Bidders/Offerors, Section 7, Item g. on RFP Page 19 under BINDER INDEX, Tab 3 it states, “SF24 Bid Bond with Raised Seals, and Power of Attorney (original bid bond, fully completed/signed as required)”. As this is an electronic proposal delivery, please confirm this is referring to a scanned copy of the original bid bond. Correct. This refers to an electronic copy. Raised seals must be visible.
29 Reference Instructions to Bidders/Offerors, RFP Page 19, Prospective Contractors’ Responsibility: Item 3 states, “Completed Representations and Certifications; FAR 52.209-5, and 52.209-7.” We do not find FAR 52.209-5 in the RFP. Please provide this. Due to the recent FAR overhaul, 52.209-5 is no longer a clause. Therefore, this requirement no longer applies.
30 Attachment C (Key Personnel Evaluation) indicates we are to provide information for Elevator personnel (ex., Elevator Design Project Manager, Elevator Project Superintendent, etc.). The personnel listed in this attachment are not applicable or aligned with RFP requirements for Key Personnel. Please advise. Key personnel as stated in evaluation factors are as follows: Project Manager, Superintendent, Safety Officer, Quality Control Manager. Updated attachment c is attached to amendment 003.
31 Attachment C (Key Personnel Evaluation) directs us to provide projects for Key Personnel that were completed within the past six years. However, Factor V on RFP Page 80 defines recency as active or completed efforts performed within the past ten (10) years from the issuance date of this solicitation. Considering that Key Personnel must have 3 projects of similar size and scope, will the Government please allow Key Personnel project experience to be active or completed efforts performed within the past ten (10) years from the issuance date of this solicitation? Yes, 10 years applies to the Key Personnel and Projects.
32 The response to RFI No. 6 in Amendment 0001 states, “For the purposes of the price proposal, work hours will be Monday through Friday 7:00 AM to 4:00 AM, or other established daytime 40 hour week.” Please confirm this should state, “7:00 AM to 4:00 PM”. Confirmed 7:00 AM to 4:00 PM or 0700-1600 hours
33 Could we confirm fire sprinkler counts. 1175 observed, account for 1500 for the purposes of the proposal.
34 Qty of 1,500 sprinkler heads are to be “touched” over the course of this project. By touches I mean converting pendent to upright, eliminating and capping a head, relocating a head, upright back to pendent. Is my interpretation correct? Correct