Question RFI No. 7 - Buy American Domestic Materials.docx

DOCX document 21 KB Posted

Attached to
Z2DA--570-20-308 - Replace and Expand Chilled Water Infrastructure in Building 1 | Construction Services Procurement
Solicitation number
36C26126R0028
Issued by

About this file

This is a Question and Answer (Q&A) document from a Request for Information (RFI) process for VA Solicitation No. 36C26126R0028, concerning the Chilled Water Infrastructure project (Project No. 570-20-308) at the Department of Veterans Affairs Palo Alto Health Care System. The contractor's question addresses the application of Buy American domestic material requirements under FAR clauses 52.225-11 and 52.225-12, specifically seeking clarification on whether all hydronic-system construction materials (steel pipe, fittings, valves, pumps, coils, variable frequency drives, and DDC control hardware) must comply with domestic content standards, whether materials from WTO GPA/Free Trade Agreement designated countries are automatically acceptable, and the procedure and deadline for requesting determinations of inapplicability based on unreasonable cost or unavailability. The contractor also inquires whether Build America, Buy America (BABA) requirements under 2 CFR Part 184 apply concurrently and how to reconcile potential conflicts with FAR Buy American provisions.

The Government's response indicates that construction materials are typically treated as Commercial Off-The-Shelf (COTS) items, which are excepted from Buy American requirements unless specifically manufactured for the project. The Government confirmed that materials from WTO GPA/FTA designated countries are acceptable under the designated-country waiver in FAR 52.225-11(b). The response does not address the contractor's questions regarding the formal procedure and deadline for requesting determinations of inapplicability or the application of BABA requirements, leaving those matters unresolved for potential clarification in subsequent amendments or communications with the Contracting Officer (Charee Harris, charee.harris@va.gov).

View the file

Other files

File Type Posted
Wage Determinaton CA202600148 07.14.26.pdf PDF
36C26126R0028 0007.docx DOCX document
36C26126R0028 0006.docx DOCX document
90209 - 570-20-308 - VA CA Fresno CHW - ASI-01 Drawings- 20260724.pdf PDF
RFI LOG UPDATE AMENDMENT 005.xlsx XLSX spreadsheet
90209 - 570-20-308 - Fresno CHW - ASI 01 - 20260724.pdf PDF
36C26126R0028 0005.docx DOCX document
36C26126R0028 0004.docx DOCX document
36C26126R0028 -0003.docx DOCX document
SECTION 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.pdf PDF
Construction Clause 52.212-4.docx DOCX document
Attachment C - Key Personnel Evaluation 36C26126R0028.docx DOCX document
36C26126R0028-0002.docx DOCX document
RFI LOG UPDATE AMENDMENT 003.xlsx XLSX spreadsheet
90209 - 570-20-308 - Fresno Chilled Water Bid Set Combined Specs-20260504r1.pdf PDF
VA Specific Clause Payments Fixed Price Construction.docx DOCX document
36C26126R0028 0003.docx DOCX document
VA Specific Clause Payments under Fixed Price Construction.docx DOCX document
VA Fresno Chiller Plant MEP Record Drawings 11-15-24_Part1.pdf PDF
Construction 52.212-4.docx DOCX document
VA Fresno Chiller Plant MEP Record Drawings 11-15-24_Part2.pdf PDF
RFI LOG UPDATE AMENDMENT 002.xlsx XLSX spreadsheet
36C26126R0028 0002.docx DOCX document
36C26126R0028 Site Visit Log In Sheet.pdf PDF
90209 - 570-20-308 - Fresno CHW - Bulletin 01 Summary - 20260701.pdf PDF
90209 - 570-20-308 - Fresno CHW - Bulletin 01 Narrative - 20260701.pdf PDF
Question RFI No. 4 - Asbestos Abatement Scope and Allowance.docx DOCX document
RFI LOG.xlsx XLSX spreadsheet
Question RFI No. 12 - Temporary Pumps Piping.docx DOCX document
90209 - 570-20-308 - Fresno CHW - Bulletin 01 Drawings - 20260701.pdf PDF
36C26126R0028 0001.docx DOCX document
VA NOTICE OF LIMITATIONS ON SUBCONTRACTING DEV 2023.docx DOCX document
90209 - 570-20-308 - Fresno CHW - Bid Set Basis Of Design - 20260504.pdf PDF
Attachment C - Key Personnel Evaluation.docx DOCX document
36C26126R0028_1.docx DOCX document
ID Me Information.docx DOCX document
Attachment E - Past Performance Questionnaire.docx DOCX document
90209 - 570-20-308 - Fresno Chilled Water Bid Set Combined Drawings-20260504_Part3.pdf PDF
Attachment A - Request for Information.docx DOCX document
Attachment D - Construction Experience Project Data Sheet.doc DOC document
90209 - 570-20-308 - Fresno Chilled Water Bid Set Combined Drawings-20260504_Part2.pdf PDF
Attachment B - EMR Sheet.docx DOCX document
90209 - 570-20-308 - Fresno Chilled Water Bid Set Combined Specs-20260504.pdf PDF
90209 - 570-20-308 - Fresno Chilled Water Bid Set Combined Drawings-20260504_Part1.pdf PDF
Attachment G - Supplemental Price Breakdown.xlsx XLSX spreadsheet
Site Visit Location Details.pdf PDF
852.219-75 Fillable.pdf PDF
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION (RFI) FORM

Contractor Name:

Address:

Phone and Email:

Send to: charee.harris@va.gov

RFI

PROJECT NO.:
570-20-308
RFI NO.:
7
PROJECT NAME:
Chilled Water Infrastructure
DATE REQUESTED:
6/10/26
SOLICITATION NO.:
36C26126R0028
REFERENCE:
FAR 52.225-11 (clause, §4.5) & 52.225-12 (notice, §2.3) – Buy American under Trade Agreements
DRAWING:
N/A
SPECIFICATION SECTION:

23 21 13 / Division 23 & 26

DESCRIPTION OF PROBLEM OR INFORMATION BEING REQUESTED

The solicitation incorporates TWO distinct, companion Buy American authorities for construction performed under trade agreements, and they serve different functions:

• FAR 52.225-11, Buy American—Construction Materials Under Trade Agreements (NOV 2025) (DEVIATION), at solicitation §4.5 — the substantive CLAUSE. It establishes the domestic-content requirement (iron/steel content test for predominantly iron-or-steel materials), sets the unreasonable-cost differential at 20% for this acquisition, addresses critical items/components per FAR 25.105, and states that the Contracting Officer has determined the WTO GPA and Free Trade Agreements apply — thereby waiving the Buy American restriction for designated-country construction material. Paragraphs (c) and (d) prescribe the supporting information and price-comparison data for a request.

• FAR 52.225-12, Notice of Buy American Requirement—Construction Materials Under Trade Agreements (MAY 2014), at solicitation §2.3 — the solicitation PROVISION (notice). Paragraph (b) prescribes the procedure and timing for an offeror to request a determination of inapplicability, and how offers will be evaluated.

Please confirm:

(a) that all hydronic-system construction materials brought to the site for incorporation into the work — including steel pipe, fittings, valves, pumps, coils, VFDs, and DDC control hardware — must be domestic construction material under FAR 52.225-11, and confirm that material from a WTO GPA/FTA designated country is already acceptable under the designated-country waiver stated in FAR 52.225-11(b), such that only non-domestic, non-designated-country material requires a determination of inapplicability;

(b) the procedure and deadline — under the notice provision FAR 52.225-12(b) — for an offeror to request a determination of inapplicability for unreasonable cost or nonavailability, including the supporting information and price-comparison data required by FAR 52.225-11(c) and (d), given long lead times on certain domestic valves and electronic/control components; and confirm that the 20% unreasonable-cost differential in the DEVIATION version of FAR 52.225-11 governs that evaluation; and

(c) whether this project is also subject to Build America, Buy America (BABA) domestic-content requirements (2 CFR Part 184 / Pub. L. 117-58) in addition to the FAR Buy American clauses, and if so, how the two sets of requirements are to be reconciled. The response affects material sourcing, procurement lead time, and price.

PROJECT MANAGER’S RESPONSE

Typically, construction is Commercial of The Shelf (COTS) parts, and that is an exception to the Buy American Act. Unless you have an item that is specifically manufactured for this project.

Confirming that material from a WTO GPA/FTA designated country is already acceptable under the designated-country waiver stated in FAR 52.225-11(b)

TRACKING NO.:
AMENDMENT NO.:
VA PROJECT ENGINEER/MANAGER:
DATE:

File details come from the government source that posted it. Updated .