90209 - 570-20-308 - Fresno CHW - Bulletin 01 Summary - 20260701.pdf

PDF 126 KB Posted

Attached to
Z2DA--570-20-308 - Replace and Expand Chilled Water Infrastructure in Building 1 | Construction Services Procurement
Solicitation number
36C26126R0028
Issued by

About this file

This is Addendum #1 to the construction solicitation for the Replace and Expand Chilled Water project at Fresno VA Medical Center in Fresno, California (Project No. 570-20-308), dated July 01, 2026. The addendum consists of three narrative pages and one combined set of revised construction drawings dated July 01, 2026, and contractors must acknowledge receipt by inserting the addendum number and date in their proposal forms or risk disqualification.

The addendum includes comprehensive drawing revisions across multiple disciplines. Life Safety revisions remove the requirement to switch from smoke to heat detectors during construction and instead require dust covers on smoke detectors daily per Specification 01 35 26, clarify that shown fire extinguishers are existing, and eliminate redundant door sets. Structural revisions add Cold-Formed Metal Framing notes, remove unused Concrete & Reinforcing Steel notes, update Design Data sections, and introduce new and revised framing sheets (S-051, S-108A, S-109B, S-110B, S-501). Architectural revisions revise slab demolition hatching, shaft wall locations, interior elevation callouts, reflected ceiling plan legends, and add new interior elevation notes and finishes sheets. Fire Protection revisions adjust scope and add missing sprinklers to floor plans. Fire Alarm revisions update scope and device locations across all floor plans. Mechanical revisions add Out of Scope shading, correct pipe routing, add keynotes and sheet notes across numerous floor plan sheets, update schedules for pumps, fan coil units, and duct coils, and add controls point schedules. Electrical revisions update breaker sizing, VFD basis of design for the Zone Coil Pump, and the one-line diagram with updated schedules.

View the file

Other files

File Type Posted
Wage Determinaton CA202600148 07.14.26.pdf PDF
36C26126R0028 0007.docx DOCX document
36C26126R0028 0006.docx DOCX document
90209 - 570-20-308 - VA CA Fresno CHW - ASI-01 Drawings- 20260724.pdf PDF
RFI LOG UPDATE AMENDMENT 005.xlsx XLSX spreadsheet
90209 - 570-20-308 - Fresno CHW - ASI 01 - 20260724.pdf PDF
36C26126R0028 0005.docx DOCX document
36C26126R0028 0004.docx DOCX document
36C26126R0028 -0003.docx DOCX document
SECTION 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.pdf PDF
Construction Clause 52.212-4.docx DOCX document
Attachment C - Key Personnel Evaluation 36C26126R0028.docx DOCX document
36C26126R0028-0002.docx DOCX document
RFI LOG UPDATE AMENDMENT 003.xlsx XLSX spreadsheet
90209 - 570-20-308 - Fresno Chilled Water Bid Set Combined Specs-20260504r1.pdf PDF
VA Specific Clause Payments Fixed Price Construction.docx DOCX document
36C26126R0028 0003.docx DOCX document
VA Specific Clause Payments under Fixed Price Construction.docx DOCX document
VA Fresno Chiller Plant MEP Record Drawings 11-15-24_Part1.pdf PDF
Construction 52.212-4.docx DOCX document
VA Fresno Chiller Plant MEP Record Drawings 11-15-24_Part2.pdf PDF
RFI LOG UPDATE AMENDMENT 002.xlsx XLSX spreadsheet
36C26126R0028 0002.docx DOCX document
36C26126R0028 Site Visit Log In Sheet.pdf PDF
90209 - 570-20-308 - Fresno CHW - Bulletin 01 Narrative - 20260701.pdf PDF
Question RFI No. 4 - Asbestos Abatement Scope and Allowance.docx DOCX document
RFI LOG.xlsx XLSX spreadsheet
Question RFI No. 7 - Buy American Domestic Materials.docx DOCX document
Question RFI No. 12 - Temporary Pumps Piping.docx DOCX document
90209 - 570-20-308 - Fresno CHW - Bulletin 01 Drawings - 20260701.pdf PDF
36C26126R0028 0001.docx DOCX document
VA NOTICE OF LIMITATIONS ON SUBCONTRACTING DEV 2023.docx DOCX document
90209 - 570-20-308 - Fresno CHW - Bid Set Basis Of Design - 20260504.pdf PDF
Attachment C - Key Personnel Evaluation.docx DOCX document
36C26126R0028_1.docx DOCX document
ID Me Information.docx DOCX document
Attachment E - Past Performance Questionnaire.docx DOCX document
90209 - 570-20-308 - Fresno Chilled Water Bid Set Combined Drawings-20260504_Part3.pdf PDF
Attachment A - Request for Information.docx DOCX document
Attachment D - Construction Experience Project Data Sheet.doc DOC document
90209 - 570-20-308 - Fresno Chilled Water Bid Set Combined Drawings-20260504_Part2.pdf PDF
Attachment B - EMR Sheet.docx DOCX document
90209 - 570-20-308 - Fresno Chilled Water Bid Set Combined Specs-20260504.pdf PDF
90209 - 570-20-308 - Fresno Chilled Water Bid Set Combined Drawings-20260504_Part1.pdf PDF
Attachment G - Supplemental Price Breakdown.xlsx XLSX spreadsheet
Site Visit Location Details.pdf PDF
852.219-75 Fillable.pdf PDF
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Replace and Expand Chilled Water Fresno VA Medical Center

570-20-308 July 01, 2026

DATE: July 01, 2026

Narrative of Changes

PROJECT NAME: Replace and Expand Chilled Water

Fresno VA Medical Center, Fresno, CA

PROJECT NO.: 570-20-308

Bulletin #01

NOTICE TO BIDDERS:

All contractors submitting proposals for the above named project shall take note of the following changes, additions, interpretations, clarifications, etc., in connection with the drawings and specifications and other general documents.

The following instructions have precedence over anything contrarily shown on the drawings or described in the specification documents, and all such shall be taken into consideration and be included in the Contractor's bids.

Acknowledge receipt of this Addendum by inserting its number and date in the space provided in the Form of Proposal.

Failure to do so may subject bidder to disqualification.

This Addendum #1 consists of three (3) narrative pages and (1) combined set of all Construction Drawings dated July

01, 2026

DRAWING REVISIONS

1. General Sheets:

A. G001: Revised drawing sheet index.

2. Life Safety Sheets:

A. GI001, Interim Life Safety Measures. Change to remove requirement for switching from smoke detectors to heat detectors during construction operations and instead following Specification 01 35

26 which requires dust covers on the smoke detectors prior to construction operations each day and removing the dust covers at the end of each work day.

B. GI002: Edited the Fire Extinguisher Paragraph. Fire extinguishers shown are existing.

C. GI floor plans: Had two sets of doors in each location. One set was deleted.

3. Civil Sheets:

A. None

4. Structural Sheets:

A. S-001: Added “Cold-Formed Metal Framing” notes section and removed “Concrete & Reinforcing

Steel” notes section. Updated “Design Data” notes section.

B. S-030: Removed details that are not used.

C. S-051: New sheet.

D. S-108A: Updated framing.

E. S-109B: Updated framing.

F. S-110B: New sheet.

G. S-501: New sheet.

5. Architectural Sheets:

A. AD001: Added additional phasing general notes.

B. AD101A – AD109B: Revised slab demolition hatch.

C. AE101A – AE109B: Revised shaft wall location. Revised interior elevation callouts. Revised exterior shaft detailing and notes.

D. AC101A – AC109B: Revised reflected ceiling plan legend.

E. AI420: New sheet with interior elevation notes.

F. IN100: New sheet with interior finishes.

6. Fire Protection Sheets:

A. FP001: Adjusted Scope and General Notes.

B. FP101A- (all floor plans) Added sprinklers where missing in some areas. Adjusted Sheet Notes, Legend, and Scope Legend.

7. Fire Alarm Sheets:

A. FA001: Updated scope of work.

B. FA101A – FA109B (all floor plans). Adjusted sheet notes, keynotes, device legend and existing device locations.

8. Mechanical Sheets:

A. All Sheets: Out of Scope shading added

B. MP101A-1: Keynotes 1, 2 added, sheet note 4 added, diagrammatic temporary piping added

C. MP101B-1: Keynotes 2, 3 added, sheet note 4 added, diagrammatic temporary piping added

D. MP101A-2: Pipe routing corrected following model issues. Keynotes 2-9 and Sheet note 4 added

E. MP101B-2: Pipe routing corrected following model issues. Keynotes 2-9 and Sheet note 4 added

F. MP101A-3: Sheet note 4 added

G. MP101B-3: Sheet note 4 added

H. MP101A-4: Sheet note 4 added

I. MP101B-4: Sheet note 4 added

J. MP102A-1: Sheet note 4 added

K. MP102A-2: Sheet note 4 added

L. MP102B-2: Sheet note 4 added

M. MP102A-3: Sheet note 4 added

N. MP102B-3: Sheet note 4 added

O. MP103A-1: Sheet note 4 added

P. MP103A-2: Sheet note 4 added, condensate pipe routing updated

Q. MP103B-2: Sheet note 4 added

R. MP103A-3: Sheet note 4 added

S. MP103B-3: Sheet note 4 added

T. MP104A-1: Sheet note 4 added

U. MP104A-2: Sheet note 4 added

V. MP104B-2: Sheet note 4 added, condensate pipe routing updated

W. MP104B-3: Sheet note 4 added

X. MP105A-1: Sheet note 4 added

Y. MP105B-2: Sheet note 4 added, condensate pipe routing updated

Z. MP105B-3: Sheet note 4 added

AA. MP106A-1: Sheet note 4 added

BB. MP106B-3: Sheet note 4 added

CC. MP107A-1: Sheet note 4 added

DD. MP107A-2: Sheet note 4 added

EE. MP107B-2: Sheet note 4 added, condensate pipe routing updated

FF. MP107A-3: Sheet note 4 added, condensate pipe routing updated

GG. MP107B-3: Sheet note 4 added, condensate pipe routing updated

HH. MP108A-1: Sheet note 4 added

II. MP108B-1: Sheet note 4 added

JJ. MP108B-2: Sheet note 4 added, condensate pipe routing updated

KK. MP108B-3: Sheet note 4 added

LL. MP109B-1: Sheet note 4 added

MM. MP109B-3: Sheet added

NN. MP110B-1: Sheet note 4 added, pipe routing adjusted to be closer to parapet wall

OO. MP401: Sheet note 4 added, pipe routing corrected following a modeling issue

PP. M-601: Pump schedule and Fan coil unit schedules updated

QQ. M-602: Duct coil schedule updated

RR. M-703: Controls point schedule added

SS. M-705: Controls point schedule added

TT. M-706: Sheet added

UU. MP901: Pipe sizes added, keynote 1 added, Sheet note 4 added

9. Electrical Sheets:

A. EP-101B: Updated breaker size and VFD basis of design model for Zone Coil Pump

B. E-601: Updated one-line diagram and schedules

File details come from the government source that posted it. Updated .