Question RFI No. 12 - Temporary Pumps Piping.docx

DOCX document 27 KB Posted

Attached to
Z2DA--570-20-308 - Replace and Expand Chilled Water Infrastructure in Building 1 | Construction Services Procurement
Solicitation number
36C26126R0028
Issued by

About this file

This is a Request for Information (RFI) document submitted by a contractor to clarify design requirements for temporary chilled water and hot water infrastructure during Phase 2 of a mechanical renovation project at the Department of Veterans Affairs Palo Alto Health Care System (VAPAHCS). The RFI, numbered 12 and issued June 10, 2026, relates to Solicitation Number 36C26126R0028 (Project 570-20-308: Replace and Expand Chilled Water Infrastructure in Building 1) and references the Mechanical Phasing Plan (Drawing M-002) and related specifications (Section 23 21 13).

The contractor identifies significant ambiguities in the Phase 2 requirements for providing temporary pumps and piping connections to maintain continuous service to existing chilled water and hot water risers during sub-basement piping work. The RFI requests the Architect/Engineer of Record provide specific design parameters including: required temporary capacity (tons/MBH), design flow (GPM), pump head, and supply/return temperatures; identification of areas and loads requiring continuous service with redundancy requirements; quantity, sizing, electrical power source, and control specifications for temporary pumps; temporary piping sizes, materials, routing, lengths, insulation, connection points, and isolation provisions; expected seasonal changeover frequency and operational responsibility; anticipated duration and allowable outage windows; and scope confirmation that the contractor furnishes, installs, operates, maintains, and removes the temporary system as part of the base bid. The Project Manager's response dated July 1, 2025 indicates that Update Sheets MP101A-1 and MP101B-1 in Bulletin 1 provide diagrammatic layouts, that all risers must remain operational until full transition to new risers, and that updated Schedule M-601 details requirements for two temporary pumps.

View the file

Other files

File Type Posted
Wage Determinaton CA202600148 07.14.26.pdf PDF
36C26126R0028 0007.docx DOCX document
36C26126R0028 0006.docx DOCX document
90209 - 570-20-308 - VA CA Fresno CHW - ASI-01 Drawings- 20260724.pdf PDF
RFI LOG UPDATE AMENDMENT 005.xlsx XLSX spreadsheet
90209 - 570-20-308 - Fresno CHW - ASI 01 - 20260724.pdf PDF
36C26126R0028 0005.docx DOCX document
36C26126R0028 0004.docx DOCX document
36C26126R0028 -0003.docx DOCX document
SECTION 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.pdf PDF
Construction Clause 52.212-4.docx DOCX document
Attachment C - Key Personnel Evaluation 36C26126R0028.docx DOCX document
36C26126R0028-0002.docx DOCX document
RFI LOG UPDATE AMENDMENT 003.xlsx XLSX spreadsheet
90209 - 570-20-308 - Fresno Chilled Water Bid Set Combined Specs-20260504r1.pdf PDF
VA Specific Clause Payments Fixed Price Construction.docx DOCX document
36C26126R0028 0003.docx DOCX document
VA Specific Clause Payments under Fixed Price Construction.docx DOCX document
VA Fresno Chiller Plant MEP Record Drawings 11-15-24_Part1.pdf PDF
Construction 52.212-4.docx DOCX document
VA Fresno Chiller Plant MEP Record Drawings 11-15-24_Part2.pdf PDF
RFI LOG UPDATE AMENDMENT 002.xlsx XLSX spreadsheet
36C26126R0028 0002.docx DOCX document
36C26126R0028 Site Visit Log In Sheet.pdf PDF
90209 - 570-20-308 - Fresno CHW - Bulletin 01 Summary - 20260701.pdf PDF
90209 - 570-20-308 - Fresno CHW - Bulletin 01 Narrative - 20260701.pdf PDF
Question RFI No. 4 - Asbestos Abatement Scope and Allowance.docx DOCX document
RFI LOG.xlsx XLSX spreadsheet
Question RFI No. 7 - Buy American Domestic Materials.docx DOCX document
90209 - 570-20-308 - Fresno CHW - Bulletin 01 Drawings - 20260701.pdf PDF
36C26126R0028 0001.docx DOCX document
VA NOTICE OF LIMITATIONS ON SUBCONTRACTING DEV 2023.docx DOCX document
90209 - 570-20-308 - Fresno CHW - Bid Set Basis Of Design - 20260504.pdf PDF
Attachment C - Key Personnel Evaluation.docx DOCX document
36C26126R0028_1.docx DOCX document
ID Me Information.docx DOCX document
Attachment E - Past Performance Questionnaire.docx DOCX document
90209 - 570-20-308 - Fresno Chilled Water Bid Set Combined Drawings-20260504_Part3.pdf PDF
Attachment A - Request for Information.docx DOCX document
Attachment D - Construction Experience Project Data Sheet.doc DOC document
90209 - 570-20-308 - Fresno Chilled Water Bid Set Combined Drawings-20260504_Part2.pdf PDF
Attachment B - EMR Sheet.docx DOCX document
90209 - 570-20-308 - Fresno Chilled Water Bid Set Combined Specs-20260504.pdf PDF
90209 - 570-20-308 - Fresno Chilled Water Bid Set Combined Drawings-20260504_Part1.pdf PDF
Attachment G - Supplemental Price Breakdown.xlsx XLSX spreadsheet
Site Visit Location Details.pdf PDF
852.219-75 Fillable.pdf PDF
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION (RFI) FORM

Contractor Name:

Address:

Phone and Email:

Send to: charee.harris@va.gov

RFI

PROJECT NO.:
570-20-308
RFI NO.:
12
PROJECT NAME:
Chilled Water Infrastructure
DATE REQUESTED:
6/10/26
SOLICITATION NO.:
36C26126R0028
REFERENCE:
M-002 Mechanical Phasing Plan, Phase 2 / Temporary Chilled & Hot Water
DRAWING:
M-002; MP101 series; M-601 (P-TEMP)
SPECIFICATION SECTION:

23 21 13 / 01 00 00

DESCRIPTION OF PROBLEM OR INFORMATION BEING REQUESTED

Per Phase 2 of the Mechanical Phasing Plan (Drawing M-002), the contractor is to provide temporary pumps and temporary connections from the chilled water/hot water mains (depending on the season) to the existing risers during the sub-basement piping work, to then be replaced with temporary piping from the new piping to the existing risers for the duration of the project (through removal at Phase 13). As written, Phase 2 is vague and does not contain the information or details needed to properly price the temporary piping and pumps. This is a design-bid-build project; bidders require the following from the Architect/Engineer of Record to develop a fixed price:

(a) Performance basis — the required temporary capacity (tons / MBH), design flow (GPM), pump head, and design supply/return temperatures for both the chilled-water and hot-water seasonal conditions;

(b) Loads/areas served — which existing risers, areas, and loads must remain in continuous service during Phase 2, and any minimum redundancy (e.g., standby/N+1) required for occupied patient-care spaces;

(c) Temporary pumps — quantity, size, standby requirement, and the electrical power source/characteristics and controls the temporary pumps are to connect to (and by whom);

(d) Temporary piping — size(s), material, routing/path, approximate lengths, insulation, and the specific connection/tie-in points at the mains and at the existing risers, including isolation and shutdown provisions;

(e) Seasonal changeover — the expected number of chilled-to-hot (and reverse) changeovers, and who is responsible for operating the changeover during the temporary period;

(f) Duration and operation — the anticipated duration the temporary system must remain in service, allowable system-interruption/outage windows, and water treatment/makeup/glycol requirements; and

(g) Scope confirmation — confirmation that the temporary system is to be furnished, installed, operated, maintained, and ultimately removed by the contractor as part of the base bid.

Absent this information, the temporary piping and pumps required by Phase 2 cannot be accurately quantified or priced.

PROJECT MANAGER’S RESPONSE

Update sheets MP101A-1 and MP101B-1 in Bulletin 1 issued July 1, 2025 show a diagramatic layout for the required temporary piping. All risers will be required to be maintained operational until the system is fully transitioned to the new risers. Updated schedule on M-601 details the requirements for the two (2) temporary pumps.

Justin Millerberg, Davenergy Solutions

TRACKING NO.:
AMENDMENT NO.:
VA PROJECT ENGINEER/MANAGER:
DATE:

File details come from the government source that posted it. Updated .