S06 Attachment_548-CSI-139 RFI_Responses_7 Pages.pdf

PDF 306 KB Posted

Attached to
Z2DA--FY26: NRM (PROJ: 548-CSI-139) BB Construction Renovate IR Cath Lab
Solicitation number
36C24826Q0453
Issued by

About this file

This is a Request for Information (RFI) Log for a federal construction project involving the renovation of an IR Catheterization Lab at a VA Medical Center (Project 548-CSI-139, Contract 36C24826Q0453).

The log documents 38 RFIs received between April 20-21, 2026, addressing project clarifications and design specifications. Key responsibility clarifications include: the contractor furnishing and installing all cabinets, casework, and the Integrated Modular Air Delivery Manifold system; the contractor providing all rough-in infrastructure for medical equipment; and the contractor responsible for commissioning per specification 01 91 00. The SLD integrated ceiling system is the basis of design, though equal alternatives are permitted. Staffing requirements allow a qualified superintendent to satisfy project manager, quality control, and safety officer roles. Structural design accommodates beam splicing for interstitial installation per detail 4/S-301, with the VA providing access points. Construction scheduling requires major noise-producing activities (concrete cutting, jack hammering, drilling) in early morning, late afternoon, or weekend hours due to an adjacent active procedure room. The contractor is responsible for maintaining area cleanliness with final approval from infectious control before removing ICRA barriers; the VAMC handles terminal cleaning. Equipment manufacturers specified include Tridium Niagara (DDC controls), Lenel (access/security), Tektone (nurse call), Siemens (fire alarm), and Ray-Bar Engineering Corp. switchable x-ray privacy glass. Finishes to match existing include Benjamin Moore Eco Spec OC-17 White Dove walls, Eco Spec 373-1 Flat White soffits, and Corian ½-inch glacier white wall protection. The log references numerous architectural and engineering drawings (AE-001, AI-511, AE-102, QH-101, SS-103, and others) and specifications for materials and systems.

View the file

Other files

File Type Posted
S06 Attachment_Updated Price Cost Schedule 4-30-2026_1 Page.docx DOCX document
36C24826Q0453 0003.docx DOCX document
S06 Attachment_Updated Statement of Work_BB 548-CSI-139_04-30-2026_22 Pages.pdf PDF
S06 Attachment_Site Visit Sign In Sheet - 548-CSI-139 Renovate IR CathLab Walk-Through_1 Page.pdf PDF
36C24826Q0453 0002.docx DOCX document
S06 Attachment_548-CSI-139 WPB Renovate IR Cath Lab_Addendum 01_2026-04-24_28 Pages.pdf PDF
S06 Attachment_Pneumatic Tube Stations Transfer Stations_2 Pages.pdf PDF
S06 Attachment_VA WPB Cath Lab 100 DWGS R1 - 11-17-20_17 Pages.pdf PDF
36C24826Q0453 0001.docx DOCX document
S02 Attachment 25_230923 Direct-Digital Control System for HVAC- rev041326_71 Pages.pdf PDF
S02 Attachment 26_BAS Facility Standards_16 Pages.pdf PDF
S02 Attachment 12_0124003 Medical Gas Pressure Drop Calcs_6 Pages.pdf PDF
S02 Attachment 11_EX 1-AHU-25 Ventilation Calc_1 Page.pdf PDF
S02 Attachment 19_WD FL20260220 dated 01-02-2026_5 pages.pdf PDF
S02 Attachment 05_CD Drawings_100 percent_dated 10.01.2025_548-CSI-139 WPB Renovate IR Cath Lab_71 Pages.pdf PDF
S02 Attachment 04_Cx Plan_100 percent - 548-CSI-139 WPB Renovate IR Cath Lab_55 Pages.pdf PDF
S02 Attachment 24_EMR_1 Page.pdf PDF
S02 Attachment 08_1-AHU-60 Load Calc_1 Page.pdf PDF
36C24826Q0453_1.docx DOCX document
S02 Attachment 18_SLD211033-1 West Palm Beach VA Hybrid_LAYOUT_Rev 4_2 Pages.pdf PDF
S02 Attachment 20_PPQ_4 Pages.pdf PDF
S02 Attachment 09_1-AHU-60 Ventilation Calc_1 Page.pdf PDF
S02 Attachment 10_EX 1-AHU-25 Load Calc_1 Page.pdf PDF
S02 Attachment 22_Base Offer Price Breakdown_1 Page_Excel Form.xlsx XLSX spreadsheet
S02 Attachment 23_VA NOTICE OF LIMITATIONS ON SUBCONTRACTING_2 Pages.pdf PDF
S02 Attachment 06_Narrative_100 percent - 548-CSI-139 WPB Renovate IR Cath Lab_57 Pages.pdf PDF
S02 Attachment 03_Cx Procurement_100 percent - 548-CSI-139 WPB Renovate IR Cath Lab_1 Page.pdf PDF
S02 Attachment 14_2410-08-AVIP_6 Pages.pdf PDF
S02 Attachment 02_Asbestos Report - 548-CSI-139 WPB Renovate IR Cath Lab_36 Pages.pdf PDF
S02 Attachment 07_CD Specifications_100 percent_dated 10.01.2025_548-CSI-139 WPB Renovate IR Cath Lab_897 Pages.pdf PDF
S02 Attachment 21_Price Cost Schedule_1 Page.docx DOCX document
S02 Attachment 15_940537-Submittal-04_45 Pages.pdf PDF
S02 Attachment 13_0124003_100 percent CD Structural Calculations_38 Pages.pdf PDF
S02 Attachment 16_940537-Submittal-05_45 Pages.pdf PDF
S02 Attachment 01_Statement of Work_BB 548-CSI-139_03-31-2026_22 Pages.pdf PDF
S02 Attachment 17_N-SOU240607_3 Pages.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI Log FY26: NRM (PROJ: 548-CSI-139) BB Construction Renovate IR Cath Lab

36C24826Q0453

RFI

Number

Question VA Response

Reference Sheet, Section of

Detail

Dated Received

1Q: Confirm that this project requires an independent QC, safety and super i.e. three employees, no dual hats?

04/20/2026

1R: VA Response:

Qualified PM and superintendent can satisfy these 3 roles.

2Q: Please confirm the audio/visual Karl Storz is a VA furnished and VA installed product. Contractor is only responsible for rough conduits with pull strings per drawing TN101.

04/20/2026

2R: VA Response:

Contractor is responsible for providing all necessary rough-in / infrastructure required to receive eqpt.

3Q: Please confirm that SPEC 06 41 16 Plastic Laminate Clad Architectural Cabinets (AE PROVIDED) is provide by VA or AE or contractor.it is shown on the finish on schedule on Drawing

AI511

04/20/2026

3R: RDC/JPA Response:

The Contractor is responsible to furnish and install all cabinets / casework. Spec 06 41 16 that notes ‘AE Provided’ is only to identify the spec is provided by AE and not a standard VA TIL spec

4Q: Please confirm who is responsible for 11 76 00 O.R.

Integrated Modular Air Delivery Manifold (AE PROVIDED) drawing QH101 shows contractor provided

04/20/2026

4R: RDC/JPA Response:

The Contractor is responsible to furnish and install the Integrated Modular Air Delivery Manifold system.

Spec 11 76 00 that notes ‘AE Provided’ is only to identify the spec is provided by AE and not a standard VA TIL spec

5Q: Does the GC need to purchase the integrated ceiling system through SLD Technologies or can any other vendor be used

04/20/2026

5R: RDC/JPA Response:

SLD integrated ceiling system is the basis of design.

Another vendor may be used provided the ceiling system is equal and meets the design requirements and performance criteria.

See spec 11 76 00, part 2.1, A

6Q: Where can the dumpster be located 04/20/2026

6R: VA Response:

Dumpster location will be determined prior to start of construction.

7Q: Provide a drawing of where the pneumatic tubing transfer station is located which feeds the pneumatic tubing for the Cath lab

04/20/2026

7R: VA Response:

The transfer station (TU234, also labeled 2-19) is located by column F15 and the tube goes through the interstitial floor to tube station 16. The tube run is approximately 100 ft from the tube station to the transfer station (See attached drawings: “Pneumatic

Tube Stations & Transfer Stations” ).

8Q: Are there downline shutoffs for med gas that are feeding the Cath lab suite.

04/20/2026

8R: AG Response:

All valving for med gases are shown on drawings.

Please clarify the question.

9Q: Please confirm why spec 08 32 13 ICU SLIDING

GLASS DOORS is included as the door schedule does not show sliding glass doors

04/20/2026

9R: RDC/JPA Response:

Doors 223, 235, and 236 are sliding glass doors.

Refer to their door and frame type.

10Q: Does the Demo and construction of construction barriers needs to be done off hours?

04/21/2026

10R: VA Response:

Major noise producing items to be performed in early morning hours or late afternoons or weekends.

Major defined as concrete cutting, jack hammering, concrete drilling, etc. Normal construction related items are not considered for after-hours work. There is an active procedure room adjacent to construction site so we must work with staff to minimize disruption in the area.

11Q: Please provide a complete set of as-builts for all work areas including Structural and MEPFP drawings.

04/21/2026

11R: VA Response:

See attached as-built drawings: “VA WPB Cath Lab

100% DWGS R1 - 11-17-20”.

12Q: Please advise who is responsible for terminal cleaning.

04/21/2026

12R: VA Response:

The VAMC is responsible for terminal cleaning. The contractor is responsible for keeping the area clean and a final construction clean approval from infectious control prior to removing ICRA barriers.

13Q: Please advise if the Project Superintendent can serve as a "dual hat" as the Contractor Quality Control Manager (CQCM) on this project

04/21/2026

13R: VA Response:

Qualified superintendent can satisfy both of these

14Q: Please advise if the Project Superintendent can serve as a "dual hat" as the Site Safety and Health Officer (SSHO) on this project

04/21/2026

14R: VA Response:

Qualified superintendent can satisfy both of these

15Q: Please advise on the following manufacturers for the building - DDC Controls, Security, Cameras, Access Control, Nurse Call and Fire Alarm System.

04/21/2026

15R: VA Response:

DDC Controls: Tridium Niagara

Access/Security: Lenel

Nurse Call/Code Blue: Tektone

Fire Alarm System: Siemens

16Q: Please confirm that the commissioning costs will be provided by the VA

04/21/2026

16R: VA Response:

It is the responsibility of the contractor to provide commissioning. See spec 01 91 00 1.8

17Q: Please confirm that there are enough licenses available for the Access Control additions.

04/21/2026

17R: VA Response:

Yes

18Q: Please confirm there are enough licenses available for the CCTV additions.

04/21/2026

18R: VA Response:

There are no cameras in project.

19Q: Please provide the deck height at the wall partition locations since it shows the partitions going to the structure above for wall types shown on Sheet AE- 001.

Sheet AE-001

Wall Types/Lead Shielding Plan

04/21/2026

19R: RDC/JPA Response:

See Addendum 01 dwg Sheet AE001 for deck height added to wall types.

Sheet AE001

20Q: Please confirm Edge Guard or equivalent ICRA walls can be utilized in lieu of the T-1.0 walls (gypsum walls) as shown on Sheets AE-001 and

GC-201.

Sheet AE-001 and Sheet GC-201

Wall Types/Lead Shielding Plan and Phasing Plans - Second Floor

04/21/2026

20R: RDC/JPA Response:

All temporary construction barriers are required to be 1-hr rated. Any barriers installed in lieu of field built wall type T-1.0 must meet the same requirements for fire separation, ICRA & PCRA

21Q: Please provide existing Cardiac Lab room finishes we are to match during Phase 1.

GC-201

Phasing Plans - Second Floor

04/21/2026

21R: RDC/JPA Response:

Walls: Benjamin Moore, Eco Spec OC-17, White

Dove (epoxy or acrylic)

Soffit: Benjamin Moore, Eco Spec 373-1 Flat White

See keynote 9.43 for existing luxury vinyl tile and existing resilient wall base product info.

Sheet AF-102

22Q: Please confirm Phase 1 Work is to be done after hours and is to be scheduled between 17:00PM - 06:00AM Monday thru Friday, any Saturday and Sunday as stated in Note "P" on Sheet GC-201.

Second Floor

04/21/2026

22R: VA Response:

Major noise producing items to be performed in early morning hours or late afternoons or weekends.

Major defined as concrete cutting, jack hammering, concrete drilling, etc. Normal construction related items are not considered for after-hours work. There is an active procedure room adjacent to construction

23Q: Please confirm the working hours and days for Phase 2.

Second Floor

04/21/2026

23R: VA Response:

Major noise producing items to be performed in early morning hours or late afternoons or weekends.

Major defined as concrete cutting, jack hammering, concrete drilling, etc. Normal construction related items are not considered for after-hours work. There is an active procedure room adjacent to construction

24Q: Please confirm the door openings that require a card reader since there is no information provided on the door schedule.

AE-601

Door & Window Schedule / Details

24R: RDC/JPA Response:

Refer to the Note Floor Plan and keynote 8.09 on sheet AE102 for the door openings. Also refer to specifications for door hardware 08 71 00.

25Q: Please provide glazing specifications for the G-1 and G-2 Frosted and clear tempered glass.

Schedule / Details

04/21/2026

25R: RDC/JPA Response:

Specification Section 08 80 00 GLAZING has revised and been reissued for clarity.

Spec 08 80 00

26Q: Please provide specifications and Basis of Design for the G-5 Switchable Frosted lead-lined glass.

Schedule / Details

04/21/2026

26R: RDC/JPA Response:

Specification Section 13 49 00 RADIATION

PROTECTION has revised and been reissued for clarity. The basis of design is Ray-Bar Engineering

Corp. switchable x-ray privacy glass (or equal).

Spec 13 49 00

27Q: Please provide product data and specifications for the Medrad Wall Mounted Keypad we are responsible for installing.

QH-101

FF&E Plan - Second Floor

04/21/2026

27R: VA Response:

Mark 7 Arterion, table mount/wall mount

28Q: Please provide Basis of Design for the WSF Flooring we are to match to existing noted on AF102. No information provided in the plans and specifications.

AF-102

Floor & Wall finish plans - Second Floor

04/21/2026

28R: RDC/JPA Response:

Walls: Benjamin Moore, Eco Spec OC-17, White

Dove (epoxy or acrylic)

Soffit: Benjamin Moore, Eco Spec 373-1 Flat White

Wall Protection: Corian, ½” thick, glacier white

29Q: Please provide Basis of design for the Wall Protection CG-1, CR-1, EG-1 and HR-1 we are to match to existing. No information provided in the specifications.

AI-511

Casework Sections & Details & Finish legend

04/21/2026

29R: RDC/JPA Response:

Cardiac Lab finishes are to be provided by VA. Refer to Finish Legend for product info for CG-1 and EG-1 (not to match existing).

Sheet AI-511

30Q: Please confirm we are to include RWP-1 on all walls within the Hybrid OR 2B-237 and the Semi- Restricted Room 2B-235.

plans - Second Floor

30R: RDC/JPA Response:

RWP-1 (4’H) to be on all walls within the Hybrid OR 2B-237 and Semi-Restricted Room 2B-235

31Q: Please confirm that we are to include RWP-1 on all remaining walls within the Transition Area Room 2B-236 that are not noted as P-2 walls.

plans - Second Floor

04/21/2026

31R: RDC/JPA Response:

RWP-1 (4’H) to be on all walls within the Transition Area Room 2B-236, including the wall noted as P-2.

This wall is to receive P-2 above the 4’H RWP-1.

32Q: Please provide the Basis of Design for the Stainless Steel shelf we are to furnish and install as noted on Elevation 2 and the Toilet Accessories Schedule as item "A" on Sheet AI-401.

AI-401

Interior Elevations

04/21/2026

32R: RDC/JPA Response:

See Addendum 01 dwg Sheet AI401 & QH101 for revised Toilet Accessories Schedule that has been updated to provide Stainless Steel Shelf Basis of Design is Bradley 7512-60.

Sheet AI401 & QH101

33Q: Please provide quantities for the demolition of the existing Fire sprinkler system and for the New Fire protection scope of work.

FX101 & FP401

Second Floor Plan - Fire Protection - Demolition & Enlarged Second floor plan - Fire Protection - New Work

04/21/2026

33R: AG Response:

Area of work is shown on drawings. Existing quantities are to be determined by contractor.

34Q: Please provide Elevation marks on the Floor plan for Casework C2 found on detail 4 on sheet AI401.

04/21/2026

34R: RDC/JPA Response:

See Addendum 01 dwg Sheet AE102 that has been revised to include elevation markers on Note Plan.

Sheet AE102

35Q: Please provide Elevation marks on the Floor plan for Casework C3 found on detail 1 on sheet AI401.

04/21/2026

35R: RDC/JPA Response:

See Addendum 01 dwg Sheet AE102 that has been revised to include elevation markers on Note Plan.

Sheet AE102

36Q: Please provide more details and dimensions on the case work Section noted as C2 and C3 on sheet A511.

AI-511

Casework Sections & Details & Finish legend

36R: RDC/JPA Response:

See Addendum 01 dwg Sheet AI401 revised Interior

Elevation 4 and Sheet AI511 for updated details of

C2 and C3.

Sheet AI401 & AI511

37Q: Please provide existing floor in all areas within the scope of work that we are to demolish.

AD102

Demolition Plan - Second Floor

04/21/2026

37R: RDC/JPA Response:

Walls: Benjamin Moore, Eco Spec OC-17, White Dove (epoxy or acrylic) Soffit: Benjamin Moore, Eco Spec 373-1 Flat White Wall Protection: Corian, ½” thick, glacier white

38Q: Detail 1/SS103 specifies the installation of wide flange beams ranging in size from W12X26 to W16X67 that are 25' to 27' long in the interstitial space to support the new medical equipment to be installed in the IR Cath Lab. The area in which these beams are to be installed is extremely congested with large main ducts, substantial electrical feeders, medical gas mains, and other utilities that would require relocation.

1) Please provide plans detailing the necessary utility systems relocations

2) Identify a feasible point of entry into the interstitial space for the delivery and installation of the specified beams

3) Alternatively, develop a revised structural design utilizing smaller members supported from the reinforced concrete framework that will support the proposed equipment loads.

SS103

Second Floor Interstitial & Third Floor Framing Plan

04/21/2026

38R: AG Response:

1. The steel is to be installed low, below the new ductwork so in sequencing the beams should be installed first. If conflicts between the steel and existing utilities exist, Contractor shall send a RFI of the specific condition.

2. VA to provide Contractor with access points to interstitial space.

3. The beams can be spliced into smaller pieces and reconnected in the field per 4/S-301, which is called out in coded note 3 on SS103.

Sheet SS103 & S-301