This file is a blank inspection and testing template for the sprinkler system at Building 39 (Building 38 identified in header) at Coatesville VAMC, formatted as an Excel spreadsheet for Year 2026. The template is structured to record semi-annual inspections and tests in compliance with NFPA 25: Standard for the Inspection, Testing and Maintenance of Water-Based Fire Protection Systems, 2023 Edition. The document includes designated test locations and recording fields organized by inspection type: Main Drain Static Pressure, Residual Pressure, Chamber Refill Time, and Flow Test Results for the 6" Zone and Main Flow; and separate sections for Tamper Valve Test Results and Sprinkler Box Fire Department Connection (FDC) testing. Test locations are mapped throughout the facility, including the basement (Building B-10), first floor (Room 08, Women's Restroom), second floor (Room 120, Room 219), and attic areas, with specific device locations such as OS&Y valves, PIV (Post Indicator Valve), and standpipes identified. The template uses standardized notation where P indicates passed inspection/test, F indicates failed, D indicates disconnected, C indicates contractor test, and timed results are recorded in minutes and seconds format. This blank template serves as the inspection record documentation mechanism for the five-year obstruction inspection and maintenance contract at Coatesville VAMC.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24426Q0415 0005.docx | DOCX document | |
| 36C24426Q0415 0004.docx | DOCX document | |
| Site Visit Information 07-9-2026.docx | DOCX document | |
| RFI Q and As.docx | DOCX document | |
| SPKLR2-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR57-2026 Blank.xlsx | XLSX spreadsheet | |
| 36C24426Q0415 0003.docx | DOCX document | |
| SPKLR139-2026.xlsx | XLSX spreadsheet | |
| SPKLR1-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR39-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR7-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR59-2026.xlsx | XLSX spreadsheet | |
| SPKLR8-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR9-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR4-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR138-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR3-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR6-2026.xlsx | XLSX spreadsheet | |
| SPKLR69-2026.xlsx | XLSX spreadsheet | |
| SPKLR138E-2026 Blank.xlsx | XLSX spreadsheet | |
| 36C24426Q0415 0002.docx | DOCX document | |
| 36C24426Q0415 0001.docx | DOCX document | |
| SCA 2015-5791 Rev 31.pdf | ||
| 36C24426Q0415.docx | DOCX document | |
| 852.219-75 MUST SIGN AND RETURN WITH PROPOSAL.pdf |
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Building 39
| SPRINKLER SYSTEM INSPECTION AND TEST | ||
| Building 38 | ||
| YEAR 2026 | 1 ST | 2ND |
| Date |
| Inspector |
| Main Drain | ||||||
| Static Pressure | ||||||
| Residual Pressure | ||||||
| Chamber Refill Time | ||||||
| Flow Test Results | ||||||
| Floor | Test Location | 6" | Zone | 6" | Zone | |
| 6" Main Flow 1302-0145 | B-10 | |||||
| Basement 1302-0140 | Rm. 08 (Women's RR) | |||||
| First Floor 1302-0142 | Rm. 120 | Key #49 | ||||
| Second Floor 1302-0159 | Rm. 219 | Key #49 | ||||
| Attic 1302-0161 | By Elevator Rm | |||||
| Tamper Valve Test Results | ||||||
| Device | Location | |||||
| OS &Y 1302-0144 | B-10 | |||||
| PIV 1302-0153 | South Of Bldg. | |||||
| Main Riser 1302-0147 | Rm. 08 | |||||
| Basement Zone 1302-0141 | Elevator Lobby | |||||
| East Standpipe 1302-0146 | Bsmt Stairs | |||||
| West Standpipe 1302-0148 | Bsmt Stairs | |||||
| First Floor 1302-0155 | Rm. 120 | Key #49 | ||||
| Second Floor 1302-0160 | Rm. 219 | Key #49 | ||||
| Attic 1302-0162 | By Elevator Rm |
| SPRINKLER BOX |
| FDC |
| TESTED SEMI-ANNUALLY IAW |
| NFPA 25: STANDARD FOR THE INSPECTION, TESTING AND MAINTENANCE |
| OF WATER BASED FIRE PROTECTION SYSTEMS, 2023 EDITION |
| ACCEPTABLE TESTING RESULTS |
| P = PASSED INSPECTION / TEST |
| F = FAILED INSPECTION / TEST |
| D = DISCONNECTED |
| C = CONTRACTOR TEST |
| TIMED RESULTS NOTED IN MINUTES AND SECONDS ( EXAMPLE 1M 30S ) |