This file is a blank inspection and testing template for Building 1's sprinkler system for the year 2026, designed to document compliance with NFPA 25 standards for water-based fire protection systems. The template provides a structured format for recording semi-annual sprinkler system inspections and tests, including main drain static and residual pressure measurements, chamber refill time, and flow test results across multiple floors and zones (basement, ground floor, first through third floors, and attic). The form identifies specific test locations throughout the building using asset identification numbers, including six-inch zones in the center stairwell, the main riser in the basement, and various valve and device locations such as OS&Y valves, pressure independent valves (PIV), tamper alarms, and the Fire Department Connection (FDC).
The template establishes a standardized inspection protocol requiring documented results for each location with pass/fail indicators, timed chamber refill results noted in minutes and seconds, and notation fields for inspector names and dates of inspection. This blank template is intended for use in conjunction with the related federal contract opportunity (Solicitation 36C24426Q0415) for five-year obstruction inspection and maintenance services at Coatesville VA Medical Center, where contractors must perform all NFPA 25-required inspections, internal pipe assessments, valve inspections, FDC hydrostatic testing, and hydrant flow testing within 30 calendar days of award during regular administrative hours (Monday-Friday, 8:00 a.m. to 4:30 p.m.).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24426Q0415 0005.docx | DOCX document | |
| 36C24426Q0415 0004.docx | DOCX document | |
| Site Visit Information 07-9-2026.docx | DOCX document | |
| RFI Q and As.docx | DOCX document | |
| SPKLR2-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR38-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR57-2026 Blank.xlsx | XLSX spreadsheet | |
| 36C24426Q0415 0003.docx | DOCX document | |
| SPKLR139-2026.xlsx | XLSX spreadsheet | |
| SPKLR39-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR7-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR59-2026.xlsx | XLSX spreadsheet | |
| SPKLR8-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR9-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR4-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR138-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR3-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR6-2026.xlsx | XLSX spreadsheet | |
| SPKLR69-2026.xlsx | XLSX spreadsheet | |
| SPKLR138E-2026 Blank.xlsx | XLSX spreadsheet | |
| 36C24426Q0415 0002.docx | DOCX document | |
| 36C24426Q0415 0001.docx | DOCX document | |
| SCA 2015-5791 Rev 31.pdf | ||
| 36C24426Q0415.docx | DOCX document | |
| 852.219-75 MUST SIGN AND RETURN WITH PROPOSAL.pdf |
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Building 1
| SPRINKLER SYSTEM INSPECTION AND TEST | ||
| Building 1 | ||
| YEAR 2026 | 1ST | 2ND |
| Date |
| Inspector(s) |
| Main Drain | ||||||
| Static Pressure | ||||||
| Residual Pressure | ||||||
| Chamber Refill Time | ||||||
| Flow Test Results | ||||||
| Floor / Zone | Test Location | 6" | Zone | 6" | Zone | |
| BSMT. 2202-0146 | RM. B06 (EMS closet) | |||||
| GRND. 2202-0156 | CENTER STAIR | |||||
| 1ST. 2202-0173 | CENTER STAIR | |||||
| 2ND. 2202-0179 | CENTER STAIR | |||||
| 3RD. 2202-0185 | CENTER STAIR | |||||
| ATTIC 2202-0189 | CENTER | |||||
| Cupola 2202-0191 | Attic | |||||
| Tamper Alarm / Valve Test Results | ||||||
| DEVICE | LOCATION | |||||
| OS & Y-Mislabeled Main B21 2202-0159 | RM. B21 (Key 49) | KEY #49 | ||||
| P.I.V. 2202-0158 | S. E. OF BLDG. | |||||
| West Stair Riser 2202-0160 | Grd Floor West Stairwell | |||||
| East Stair Riser 2202-0162 | Grd Floor East Stairwell | |||||
| MAIN RISER 2202-0161 | CENTER STAIR | |||||
| BSMT. ZONE 2202-0147 | RM. B21 (Key 49) | |||||
| GRD. FL. ZONE 2202-0157 | CENTER STAIR | |||||
| Exterior PIV 2202-0163 | S.E. Corner | |||||
| 1ST. FL. ZONE 2202-0174 | CENTER STAIR | |||||
| 2ND FL. ZONE 2202-0180 | CENTER STAIR | |||||
| 3RD FL. ZONE 2202-0186 | CENTER STAIR | |||||
| ATTIC ZONE 2202-0190 | ATTIC | |||||
| CUPOLA ZONE 2202-0192 | ATTIC | |||||
| ATTIC OS & Y 2202-0193 | ATTIC | |||||
| ATTIC 2202-0194 | ATTIC |
| SPRINKLER BOX |
| FDC |
| TESTED SEMI-ANNUALLY IAW |
| NFPA 25: STANDARD FOR THE INSPECTION, TESTING AND MAINTENANCE |
| OF WATER BASED FIRE PROTECTION SYSTEMS, 2023 EDITION |
| ACCEPTABLE TESTING RESULTS |
| P = PASSED INSPECTION / TEST |
| F = FAILED INSPECTION / TEST |
| D= DISCONNECTED |
| C= CONTRACTOR TEST |
| TIMED RESULTS NOTED IN MINUTES AND SECONDS ( EXAMPLE 1M 30S ) |