This file is a blank inspection and testing template for a Building 138 sprinkler system in Year 2026, designed to document semi-annual compliance testing in accordance with NFPA 25: Standard for the Inspection, Testing and Maintenance of Water-Based Fire Protection Systems (2023 Edition). The template provides structured fields for recording inspection results across multiple zones and locations, including the basement, first floor, and attic areas. Specific test parameters documented include main drain static pressure, residual pressure, chamber refill time, and flow test results for the 6" zones in the basement and first floor, as well as the attic center stairwell. The template also includes sections for tamper valve testing at designated device locations (OS & Y valve in Room BA178, P.I.V. west of building, basement zone, first floor zone, and attic), and sprinkler box FDC testing conducted semi-annually.
The template uses standardized result coding where P indicates passed inspection/test, F indicates failed inspection/test, D indicates disconnected systems, and C indicates contractor test with timed results recorded in minutes and seconds format. This blank form serves as a deliverable reference document for the Fire Suppression Sprinklers at Coatesville VAMC solicitation (36C24426Q0415), which requires comprehensive five-year obstruction inspections, testing, and maintenance of the facility's sprinkler systems including internal pipe assessments, valve inspections, FDC hydrostatic testing, hydrant flow testing, and sprinkler gauge replacement, all to be performed by qualified technicians in compliance with NFPA 25 and VA policies within 30 calendar days of contract award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24426Q0415 0005.docx | DOCX document | |
| 36C24426Q0415 0004.docx | DOCX document | |
| Site Visit Information 07-9-2026.docx | DOCX document | |
| RFI Q and As.docx | DOCX document | |
| SPKLR2-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR38-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR57-2026 Blank.xlsx | XLSX spreadsheet | |
| 36C24426Q0415 0003.docx | DOCX document | |
| SPKLR139-2026.xlsx | XLSX spreadsheet | |
| SPKLR1-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR39-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR7-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR59-2026.xlsx | XLSX spreadsheet | |
| SPKLR8-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR9-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR4-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR3-2026 Blank.xlsx | XLSX spreadsheet | |
| SPKLR6-2026.xlsx | XLSX spreadsheet | |
| SPKLR69-2026.xlsx | XLSX spreadsheet | |
| SPKLR138E-2026 Blank.xlsx | XLSX spreadsheet | |
| 36C24426Q0415 0002.docx | DOCX document | |
| 36C24426Q0415 0001.docx | DOCX document | |
| SCA 2015-5791 Rev 31.pdf | ||
| 36C24426Q0415.docx | DOCX document | |
| 852.219-75 MUST SIGN AND RETURN WITH PROPOSAL.pdf |
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Building 138
| SPRINKLER SYSTEM INSPECTION AND TEST | ||
| Building 138 | ||
| YEAR 2026 | 1 ST | 2ND |
| Date |
| Inspector |
| Main Drain | |||||
| Static Pressure | |||||
| Residual Pressure | |||||
| Chamber refill time | |||||
| Flow Test Results | |||||
| Floor | Test Location | 6" | Zone | 6" | Zone |
| BASEMENT | Outside Rm.158 | ||||
| FIRST FLOOR | Outside Rm. 258 | ||||
| ATTIC | Center Stair to Attic | ||||
| Tamper Valve Test Results | |||||
| Device | Location | ||||
| OS & Y | RM. BA178 | ||||
| P.I.V. | WEST OF BLDG | ||||
| BASEMENT ZONE | Outside Rm.158 | ||||
| 1ST FL. ZONE | Outside Rm.258 | ||||
| ATTIC | Center Stair to Attic |
| SPRINKLER BOX |
| FDC |
| TESTED SEMI-ANNUALLY IAW |
| NFPA 25: STANDARD FOR THE INSPECTION, TESTING AND MAINTENANCE |
| OF WATER BASED FIRE PROTECTION SYSTEMS, 2023 EDITION |
| ACCEPTABLE TESTING RESULTS |
| P = PASSED INSPECTION / TEST |
| F = FAILED INSPECTION / TEST |
| D = DISCONNECTED |
| C = CONTRACTOR TEST |
| TIMED RESULTS NOTED IN MINUTES AND SECONDS ( EXAMPLE 1M 30S ) |