35368 Revised Attc L CBOS Key Personnel Response Guide.docx
DOCX document 123 KB Posted
- Solicitation number
- S-73000-00007613
- Issued by
- Multnomah County, Portland City, Oregon
About this file
The document is a Revised Attachment L - CBOS Key Personnel Response Guide for RFP/Bid Solicitation #S-73000-00007613 issued by the Oregon Department of Transportation (ODOT). The RFP is for a Commercial Back-Office Toll System Integrator and Customer Services Center to support the Oregon Toll Program, a comprehensive program for revenue collection and congestion management. The RFP requires proposers to identify all key personnel for the Implementation phase and, if different, the Operations and Maintenance phase, and to provide a summary of their experience and qualifications. Proposers must also provide an organizational chart outlining key personnel positions and any additional personnel deemed key.
The RFP covers the jurisdictions of Multnomah County and the City of Portland. No pricing, set-asides, or funding details are provided in the document. The contract term and any renewal options are not specified.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP/Bid Solicitation #S-73000-00007613 Attachment L
Revised Attachment L – CBOS -Key Personnel Response Guide Evaluation Criteria 4.10.2.7
CBOS Contractor Key personnel Summary Required Response
4.10.2.7.1 Identify all Key Personnel during the Implementation and briefly summarize their experience and qualifications as it applies to the requirements of the position. (Max Points 10)
4.10.2.7.2 If different personnel will be assigned during the Operations and Maintenance, identify which key positions will have different individuals assigned and briefly summarize their experience and qualifications as it applies to the requirements of the position. (Max Points 10)
· As a separate attachment, provide An Organizational Chart that outlines the use of key personnel positions and any additional personnel positions the Contractor deems as key, and supervisory positions that the Proposer needs to operate customer service operations.
[Provide Required Response Here]