28-Attachment I- Utility Relocation Schedule CIP 69647.000 100% URS LEVEL 3 COMMUNICATIONS 07-14-2026TR LS.pdf

PDF 245 KB Posted

Attached to
Big Bend Road from US 41 to Covington Garden Dr.
Solicitation number
IFB-26-00378
Issued by
Hillsborough County, Florida

About this file

This is a Utility Relocation Schedule document prepared by Hillsborough County for the Big Bend Road project (CIP 69647.000), which involves resurfacing and widening approximately 0.75 miles of existing 4-lane divided rural highway to a 6-lane urban typical section. The utility agency/owner is Level 3 Communications LLC. The schedule outlines the relocation, adjustment, installation, and protection of Level 3 Communications' fiber optic conduit facilities along County Road 672 from US 41 to Covington Garden Drive. Work is estimated to require 124 calendar days prior to county project construction, 46 calendar days during county project construction, 150 calendar days for material procurement, and 30 calendar days for as-built information. Key dependencies include right-of-way and structure staking prior to directional boring operations, with multiple handholes requiring adjustment or placement. The project representative is Matt Anthony (239-822-4986) and the field representative is Jennifer Posey (813-833-2952). The document was dated June 12, 2026, with final approval on July 14, 2026.

The utility work consists primarily of directional boring operations for twelve runs of 1.25-inch HDPE conduit with fiber optic cable (ranging from 170 feet to 2,020 feet in length) at minimum depths of 9 to 15 feet, placement of new handholes, pulling of new fiber optics, fiber splicing activities (with potential scheduling delays up to 90 days), and removal of existing fiber and conduit after cutover. Level 3 Communications requires 48-hour advance notice prior to construction start and specifies that work during normal business hours (8:00 AM to 5:00 PM, Monday through Friday) requires seven days' notice, while work outside normal hours requires 72-hour advance notice. The roadway contractor is required to provide staking of right-of-way and structures prior to Level 3 activity commencement, and all work must comply with Hillsborough County Utility Accommodation Manual requirements.

View the file

Other files

File Type Posted
Attachment E- 69692000 BigBendWest Drainage Design Documentation Vol. II Final.pdf PDF
21-Attachment B- Geo Report - 69692000 100P Misc Structures 2025-11-20.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 Spectrum Revised URS 7.13.2026 TR LS.pdf PDF
Attachment B- Geo Report - 69692000 100P Misc Structures 2025-11-20.pdf PDF
Attachment H- Plans- Lighting.pdf PDF
41-Attachment L- CSX Coordination.pdf PDF
Attachment G- FDOT Grant Agreement.pdf PDF
Attachment I- Utility Relocation Schedule CIP 69647.000 Utility Cert Letter 7.15.26.pdf PDF
27-Attachment I- Utility Relocation Schedule 69647.000 100% REVISED - TEC UWS - REV4 7.13.26 TR LS.pdf PDF
13-AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
2-Florida Trench Safety Act, Certification and Disclosure Statement.pdf.pdf PDF
43-Attachment M- Work Class Percentage.pdf PDF
34-Attachment I- Utility Relocation Schedule 69647.000 Spectrum Revised URS 7.13.2026 TR LS.pdf PDF
46-Attachment G- FDOT Grant Agreement.pdf PDF
Attachment B- Geo Report - 69692000 PhIV Rdwy Soil Survey Report 2025-11-20.pdf PDF
40-Attachment K- Insurance Requirements.pdf PDF
52-Attachment H- Plans- ITS.pdf PDF
48-Attachment H- Location Map.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 100% REVISED - TEC UWS - REV4 7.13.26 TR LS.pdf PDF
Attachment H- Location Map.pdf PDF
11-Direct Deposit Authorization Form 5.15.2025.pdf.pdf PDF
AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
3-Allowance Authorization Release Form.pdf.pdf PDF
29-Attachment I- Utility Relocation Schedule CIP 69647.000 100% URS PGS7-10-2026 REV 1SignedTR.pdf PDF
Attachment D- Permits - SWFWMD ERP 43024488.004 Approved.pdf PDF
17-Attachment F- 69692000 6050BigBend ROE ChildcareBrandon 10-9-25 Signed.pdf PDF
Agreement - Construction - Stand Alone.docx.pdf PDF
54-Attachment K- CSX Insurance Receipt.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 BIG BEND US 41 TO COVINGTON FTR URS 071426 TR LS.pdf PDF
39-Attachment J- CSX1036508- Agreement.pdf PDF
Attachment B- Geo Report - 69692000 Kings Lake Dr Misc Struc 100% Geo Report SS.pdf PDF
8-Change Order Form.pdf.pdf PDF
42-Agreement - Construction - Stand Alone.docx.pdf PDF
Attachment E- 69692000 BigBendWest Drainage Design Documentation Vol. I Final SS (1).pdf PDF
14-Attachment D- Permits - SWFWMD ERP 43024488.004 Approved.pdf PDF
23-Attachment E- 69692000 Waterset-Kings Lake Drainage Memo.pdf PDF
Attachment F- 669692000 6089BigBend ROE HomeDepot 10-9-25 signed.pdf PDF
20-Attachment B- Geo Report - 69692000 PhIV Rdwy Soil Survey Report 2025-11-20.pdf PDF
Attachment B- Geo Report - 69692000 Waterset Trail 100% RSS SS.pdf PDF
47-Attachment H- Clear Letters 2.pdf PDF
18-Attachment F- 669692000 BayIndustrial ROE 10-9-25. signed.pdf PDF
30-Attachment I- Utility Relocation Schedule CIP 69647.000 URS Uniti Fiber REV 3 7.10.26 TR LS.pdf PDF
Attachment F- 669692000 BayIndustrial ROE 10-9-25. signed.pdf PDF
Attachment I- Utility Relocation Schedule CIP 69647.000 100% URS PGS7-10-2026 REV 1SignedTR.pdf PDF
36-Bid Bond.doc.doc DOC document
9-Insurance Certificate.doc.doc DOC document
31-Attachment I- Utility Relocation Schedule MCI 69647.000 100% URS WSP-8-26 LS.pdf PDF
Attachment A- Construction Sign 2026.pdf PDF
32-Attachment I- Utility Relocation SchedCIP 69647 000 US 41 to Covington Garden Drive Zayo UWS 71326 TR LS.pdf PDF
1-Drug Free Workplace Form.doc.doc DOC document
Show 40 more

Latest 50 of 89 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Hillsborough County County Road: 672 (Big Bend Rd) Plans Dated: 06/12/2026 CIP Number: 69647.000 Project Name: Big Bend Road from US 41 to Covington Garden Drive Utility Agency/Owner (UAO): Level 3 Communications LLC.

NON-CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

Total Preliminary 30 Prior to County Project Construction 124 Total Material Procurement 150 During County Project Construction 46 Total Right-of-Way Acquisition 0 As-Built Information ______30_____ Total Other 14 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Hillsborough County, the roadway contractor, and other right-of-way users, the location, relocation, adjustment, installation, and/or protection of facilities, on this Hillsborough County project. The following data is based on the plans dated as listed in the Title Block.

Any deviation by Hillsborough County or its Contractor from plans, as provided may render this work schedule null and void.

Upon notification by, Hillsborough County of such change, this utility may require additional days for assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond the control of the UAO that could not reasonably be anticipated by the UAO and which could not be avoided by the UAO with the exercise of due diligence at the time of the occurrence. The UAO agrees to notify Hillsborough County in writing prior to starting, stopping, resuming, or completing work. The UAO is to provide As-Built information.

The UAO shall obtain a utility permit and comply with the requirements of the Hillsborough County UAM.

During the project, the UAO shall locate their facilities within 48 hours of notice to their Representative: Matt Anthony Telephone Number: 239-822-4986 UAO Project Representative: Matt Anthony Telephone Number: 239-822-4986 UAO Field Representative: Jennifer Posey Telephone Number: 813-833-2952 This document is a printout of a Hillsborough County form maintained in an electronic format and all revisions thereto by the UAO in the form of additions, deletions or substitutions are reflected only in an Appendix entitled “Changes to Form Document” and no change is made in the text of the document itself. Hand notations on affected portions of this document may refer to changes reflected in the above-named Appendix but are for reference purposes only and do not change the terms of the document. By signing this document, the UAO hereby represents that no change has been made to the text of this document except through the terms of the Appendix entitled “Changes to Form Document”.

You MUST signify by selecting or checking which of the following applies:

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: **Engineer of Record (EOR): Acceptance by Hillsborough

County:

(Signature) (Signature) (Signature) Matt Anthony Tamishe J. Rodriguez, P.E. Manuel E. Santos, P.E.

(Printed Name) (Printed Name) (Printed Name) NIPM Engineer of Record County Project Manager

(Title) (Title) (Title) 7/14/2026

(Date) (Date) (Date)

Final Approval by Hillsborough County:

(Signature) (Date)

Lisa Strout CAPITAL UTILITY MANAGER (Printed Name) (Title)

(**When requested by the County, the EOR will attest to compatibility of plans, specifications and Utility Work Schedule)

Rodriguez, Tamishe (ChinTa) Text Box 7/14/2026

Special Conditions and Constraints

1. Existing facilities include HDPE's Conduits with Buried FOC.

2. LEVEL 3 requests that the contractor stakes R/W & Structures, then contact Matt Anthony Level 3 Employee at 239-822-4986, 48 Hrs. prior to the start of construction.

3. Adjustment (Raise or lower the Handholes with a vertical or horizontal position where needed or possible) activities to be provided by CenturyLink National master contractor who will work closely with the Roadway

Contractor. (All adjustments will require R/W & structures to be staked prior to being completed)

4. Level 3 and Contractor’s normal business hours are from 8am to 5pm, Monday through Friday (excluding Holidays).

5. Any work during normal business hours not scheduled needs 7 DAYS notice. Due to needing locates to be called in and cleared.

6. Any work outside of normal business hours to be scheduled a minimum of 72 hours in advance.

7. Level 3 requests for the Road Contractor to provide Staking prior to activities as listed in Section C.

The emergency number for nights, weekends and Level 3 Florida holidays is (800) 228-8485.

C. Disposition of Facilities (List All Existing & Proposed) on Project

TYPE / SIZE /

MATERIAL / OFFSET

TO BASELINE FROM

STA TO STA

DESCRIPTION

OF

UTILITY WORK

DEPENDENT

ACTIVITIES

M.O.T.

PHASE

NUMBER

CONSECUTIVE

CALENDAR

DAYS

Prior During H/H

(12)1.25” HDPE

W/216F & 96F

1077+07 66’ LT

ADJUST H/H AND CONDUITS

DURING PLACEMENT OF

DRIANAGE PIPE

PLACEMENT OF 14”X23”

BETWEEN S-1 AND S-2

PHASE I

STAGE II

0 4

(12)1.25” HDPE

1077+09 64’ LT

1084+02 63’ LT

DIRECTIONAL BORE

695’ @ MIN DEPTH OF 10’

STAKING OF R/W &

STRUCTURES

PHASE I 4 0

PLACE NEW H/H

1084+02 63’ LT

PLACE NEW H/H STAKING OF R/W &

STRUCTURES

PHASE I 1 0

(12)1.25” HDPE

1084+02 63’ LT

1086+88 66’ LT

286’ @ MIN DEPTH OF 10’

PHASE I 2 0

PLACE NEW H/H

1086+88 66’ LT

PLACE NEW H/H STAKING OF R/W &

STRUCTURES

PHASE I 1 0

(3)1.5” HDPE

1086+88 66’ LT

1089+21 102’ LT

270’ @ MIN DEPTH OF 15’

PHASE I 2 0

(12)1.25” HDPE

1086+88 66’ LT

1097+00 63’ LT

1012’ @ MIN DEPTH OF 15’

PHASE I 6 0

PLACE NEW H/H

1097+00 63’ LT

PLACE NEW H/H AFTER DIRECTIONAL BORE IS

COMPLETE

PHASE I 1 0

PLACE NEW H/H

1100+47 63’ LT

PLACE NEW H/H STAKING OF R/W &

PHASE I

1 0

(12)1.25” HDPE

1100+47 63’ LT

1120+67 80’ LT

2020’ @ MIN DEPTH OF 15’

STAKING OF R/W &

STRUCTURES

PHASE I 14 0

PLACE NEW H/H

1120+67 80’ LT

PLACE NEW H/H AFTER DIRECTIONAL BORE IS

COMPLETE

PHASE I 1 0

(12)1.25” HDPE

1120+67 80’ LT

1132+52 93’ LT

DIRECTIONAL BORE

1185’ @ MIN DEPTH OF 9’

STAKING OF R/W &

STRUCTURES

PHASE I 6 0

PLACE NEW H/H

1132+52 93’ LT

PLACE NEW H/H AFTER DIRECTIONAL BORE IS

COMPLETE

PHASE I 1 0

(12)1.25” HDPE

1132+52 93’ LT

1132+40 80’ RT

DIRECTIONAL BORE

170’ @ MIN DEPTH OF 9’

STAKING OF R/W &

STRUCTURES

PHASE I 3 0

PLACE NEW H/H

1132+52 93’ RT

PLACE NEW H/H AFTER

CAPTURING EXISTING

CONDUITS

AFTER DIRECTIONAL BORE IS

COMPLETE

PHASE I 1 0

PULLING NEW FIBER

216F 96F

1077+09 64’ LT

1132+52 93’ RT

PULL 2 NEW FIBERS THRU

EXISTING AND NEW CONDUIT

DIRECTIONAL BORES

COMPLETED

N/A 20 0

FIBER SPLICING

216F & 96

2 SEPARATE SPLICING EVENTS

(SCHEDULING OF SPLICE DATES

COULD BE UP TO 90 DAYS DUE

TO IMPORTNACE OF THESE

FIBERS

COMPLETION OF PULLING NEW

FIBERS

N/A 90 0

(12)1.25” HDPE

1077+09 64’ LT

1097+00 63’ LT

REMOVE ALL FIBER AND

REMOVE CONDUIT WHERE

POSSIBLE

AFTER CUT OVER N/A 0 10

(12)1.25” HDPE

1100+47 63’ LT

1115+41 79’ LT

REMOVE ALL FIBER AND

REMOVE CONDUIT WHERE

POSSIBLE

AFTER CUT OVER N/A 0 12

(12)1.25” HDPE

1115+41 79’ LT

1115+41 65’ RT

REMOVE ALL FIBER AND

REMOVE CONDUIT WHERE

POSSIBLE

AFTER CUT OVER N/A 0 4

(12)1.25” HDPE

1115+41 65’ RT

1132+52 93’ RT

REMOVE ALL FIBER AND

REMOVE CONDUIT WHERE

POSSIBLE

AFTER CUT OVER N/A 0 16

2026-07-14T13:55:11-0400
Tamishe J Rodriguez
2026-07-14T14:24:39-0400
Lisa Strout
2026-07-14T14:30:33-0400
Manuel E. Santos

File details come from the government source that posted it. Updated .