About this file

This is a Utility Relocation Schedule prepared by MCI Metro Access Transmission Services for the Big Bend Road from US 41 to Covington Garden Drive project (CIP Number 69647.000) in Hillsborough County, Florida. The document outlines the utility work required to relocate and protect MCI's fiber optic cable infrastructure along County Road 672 in coordination with the county's roadway construction project. The schedule identifies 17 separate utility work items, including installation of new hand holes, placement of new 2-inch HDPE conduits, placement of new 96-count fiber optic cable (FOC), splicing and testing activities, removal of existing FOC, and protection of existing conduit during force main and water main construction. Work is scheduled based on dependent activities, with non-construction items estimated at 90 calendar days (30 days engineering design, 30 days permitting, 30 days as-built information) prior to county project construction, and construction items estimated at 58 calendar days during county project construction. The plans are dated June 12, 2026, and the document was updated in January 2026 with final approvals signed July 8, 2026.

The utility work schedule requires MCI to provide on-site representatives during activities within 2 feet of its facilities, with 72 hours advance notice required at (813) 410-4803 or via email to michael.krol@verizon.com. MCI requests access throughout the project duration to monitor and maintain its facilities. The designated MCI Project Representative is Michael Krol, with Christian Maldonado serving as the Field Representative. County Project Manager Manuel E. Santos, E.I. and Capital Utility Coordinator Lisa Strout provided acceptance and final approval signatures. The schedule notes that MCI is not responsible for events beyond its control that could not be reasonably anticipated or avoided by exercise of due diligence, and any deviation from the provided plans may render the work schedule null and void.

View the file

Other files

File Type Posted
Attachment E- 69692000 BigBendWest Drainage Design Documentation Vol. II Final.pdf PDF
21-Attachment B- Geo Report - 69692000 100P Misc Structures 2025-11-20.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 Spectrum Revised URS 7.13.2026 TR LS.pdf PDF
Attachment B- Geo Report - 69692000 100P Misc Structures 2025-11-20.pdf PDF
Attachment H- Plans- Lighting.pdf PDF
41-Attachment L- CSX Coordination.pdf PDF
Attachment G- FDOT Grant Agreement.pdf PDF
Attachment I- Utility Relocation Schedule CIP 69647.000 Utility Cert Letter 7.15.26.pdf PDF
27-Attachment I- Utility Relocation Schedule 69647.000 100% REVISED - TEC UWS - REV4 7.13.26 TR LS.pdf PDF
13-AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
2-Florida Trench Safety Act, Certification and Disclosure Statement.pdf.pdf PDF
43-Attachment M- Work Class Percentage.pdf PDF
34-Attachment I- Utility Relocation Schedule 69647.000 Spectrum Revised URS 7.13.2026 TR LS.pdf PDF
46-Attachment G- FDOT Grant Agreement.pdf PDF
Attachment B- Geo Report - 69692000 PhIV Rdwy Soil Survey Report 2025-11-20.pdf PDF
40-Attachment K- Insurance Requirements.pdf PDF
52-Attachment H- Plans- ITS.pdf PDF
48-Attachment H- Location Map.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 100% REVISED - TEC UWS - REV4 7.13.26 TR LS.pdf PDF
Attachment H- Location Map.pdf PDF
11-Direct Deposit Authorization Form 5.15.2025.pdf.pdf PDF
AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
3-Allowance Authorization Release Form.pdf.pdf PDF
29-Attachment I- Utility Relocation Schedule CIP 69647.000 100% URS PGS7-10-2026 REV 1SignedTR.pdf PDF
Attachment D- Permits - SWFWMD ERP 43024488.004 Approved.pdf PDF
17-Attachment F- 69692000 6050BigBend ROE ChildcareBrandon 10-9-25 Signed.pdf PDF
Agreement - Construction - Stand Alone.docx.pdf PDF
54-Attachment K- CSX Insurance Receipt.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 BIG BEND US 41 TO COVINGTON FTR URS 071426 TR LS.pdf PDF
39-Attachment J- CSX1036508- Agreement.pdf PDF
Attachment B- Geo Report - 69692000 Kings Lake Dr Misc Struc 100% Geo Report SS.pdf PDF
8-Change Order Form.pdf.pdf PDF
42-Agreement - Construction - Stand Alone.docx.pdf PDF
Attachment E- 69692000 BigBendWest Drainage Design Documentation Vol. I Final SS (1).pdf PDF
14-Attachment D- Permits - SWFWMD ERP 43024488.004 Approved.pdf PDF
23-Attachment E- 69692000 Waterset-Kings Lake Drainage Memo.pdf PDF
Attachment F- 669692000 6089BigBend ROE HomeDepot 10-9-25 signed.pdf PDF
20-Attachment B- Geo Report - 69692000 PhIV Rdwy Soil Survey Report 2025-11-20.pdf PDF
Attachment B- Geo Report - 69692000 Waterset Trail 100% RSS SS.pdf PDF
47-Attachment H- Clear Letters 2.pdf PDF
18-Attachment F- 669692000 BayIndustrial ROE 10-9-25. signed.pdf PDF
30-Attachment I- Utility Relocation Schedule CIP 69647.000 URS Uniti Fiber REV 3 7.10.26 TR LS.pdf PDF
Attachment F- 669692000 BayIndustrial ROE 10-9-25. signed.pdf PDF
Attachment I- Utility Relocation Schedule CIP 69647.000 100% URS PGS7-10-2026 REV 1SignedTR.pdf PDF
36-Bid Bond.doc.doc DOC document
9-Insurance Certificate.doc.doc DOC document
Attachment A- Construction Sign 2026.pdf PDF
32-Attachment I- Utility Relocation SchedCIP 69647 000 US 41 to Covington Garden Drive Zayo UWS 71326 TR LS.pdf PDF
1-Drug Free Workplace Form.doc.doc DOC document
Attachment E- 69692000 Waterset-Kings Lake Drainage Memo.pdf PDF
Show 40 more

Latest 50 of 89 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Updated 01/2026

NON-CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

Engineering Design 30 Prior to County Project Construction 58 Permitting 30 During County Project Construction 35 Material Procurement 0 As-Built Information 30 Other 0 * Calendar Days = UAO Workdays x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Hillsborough County, the roadway contractor, and other right-of-way users, the location, relocation, adjustment, installation, and/or protection of facilities, on this Hillsborough County project. The following data is based on the plans dated as listed in the Title Block.

Any deviation by Hillsborough County or its Contractor from plans, as provided may render this work schedule null and void.

Upon notification by Hillsborough County of such change, this utility may require additional days for assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond the control of the UAO that could not reasonably be anticipated by the UAO and which could not be avoided by the UAO with the exercise of due diligence at the time of the occurrence. The UAO agrees to notify Hillsborough County in writing prior to starting, stopping, resuming, or completing work. The UAO is to provide As-Built information.

The UAO shall obtain a utility permit and comply with the requirements of the Hillsborough County UAM.

During the project, the UAO shall locate their facilities within 48 hours of notice to their Representative: Michael Krol Telephone Number: (813) 410-4803

UAO Project Representative: Michael Krol Telephone Number: (813) 410-4803 UAO Field Representative: Christian Maldonado Telephone Number: (727) 296-5803 This document is a printout of a Hillsborough County form maintained in an electronic format and all revisions thereto by the UAO in the form of additions, deletions or substitutions are reflected only in an Appendix entitled “Changes to Form Document” and no change is made in the text of the document itself. Hand notations on affected portions of this document may refer to changes reflected in the above-named Appendix but are for reference purposes only and do not change the terms of the document. By signing this document, the UAO hereby represents that no change has been made to the text of this document except through the terms of the Appendix entitled “Changes to Form Document”.

You MUST signify by selecting or checking which of the following applies:

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: **Engineer of Record (EOR): Acceptance by Hillsborough

County PM:

(Signature) (Signature) (Signature) Michael Krol Tamishe J. Rodriguez, P.E. Manuel E. Santos, E.I.

(Printed Name) (Printed Name) (Printed Name) Senior Engineer Spec-Outside Plant Engineer of Record County Project Manager

(Title) (Title) (Title) 7/06//2026

(Date) (Date) (Date)

Final Approval by Hillsborough County Utility Coordination:

(Signature) (Date)

Lisa Strout Capital Utility Coordinator (Printed Name) (Title)

(**When requested by the County, the EOR will attest to compatibility of plans, specifications and Utility Work Schedule)

Hillsborough County County Road: 672 Plans Dated: 6/12/2026 Project Phase: Revised 100% CIP Number: 69647.000 Project Name: Big Bend Road from US 41 to Covington Garden Drive Utility Agency/Owner (UAO): MCI Metro Access Transmission Services

Tamishe Rodriguez Text Box Plans Dated: 6/12/2026

Tamishe Rodriguez Text Box 7/8/2026

Special Conditions and Constraints

1. MCI requires a representative on-site to monitor activities taking place within 2ft of its facilities. Please notify Michael Krol at (813) 410-4803 or michael.krol@verizon.com 72 hours in advance of work taking place within 2ft of MCI facilities to ensure a representative is on-site to monitor construction.

2. MCI requests access throughout the duration of the project to monitor and maintain its facilities for the ability to provide service and will coordinate with the Road Contractor.

3. Hold/Guard/Protect may include the use of sheeting, shoring and bracing of MCI's facilities and should be decided upon by the Field Representative of MCI in coordination with the Department's Contractor on a case-by-case basis. This by no means relieves the Contractor of its responsibilities as written in Statute 556 and contract documents.

Hillsborough County County Road: 672 Plans Dated: 6/12/2026 Project Phase: Revised 100% CIP Number: 69647.000 Project Name: Big Bend Road from US 41 to Covington Garden Drive Utility Agency/Owner (UAO): MCI Metro Access Transmission Services

Tamishe Rodriguez

Plans Dated: 6/12/2026

Section C. Disposition of Facilities (List All Existing & Proposed) on Project

Act No.

Type / Size /

Material

From Station/Offset

To Station/Offset

Description of Utility Work

Dependent Activities

M.O.T.

Phase

No.

Consecutive Calendar Days

Prior During

1.

New 24x36 Hand Hole

STA 1083+11

70’ LT

Place new Hand Hole to intercept existing conduit

Once staking for ROW and proposed drainage is completed, MCI will begin new placement process

N/A

2.

New (2) 2” HDPE conduits

STA 1089+60

103’ LT

Place (2) 2” HDPE conduits.

Approximate depth 36 inches

Once staking for ROW and proposed drainage is completed, MCI will begin new placement process

N/A

3.

Place new hand hole

Once staking for ROW and proposed drainage is

4.

STA 1092+70

113’ LT

Place (2) 2” HDPE conduits.

Approximate depth 36 inches

Once staking for ROW and proposed FM is completed, MCI will begin new placement process

5.

Place new hand hole

Once staking for ROW and proposed drainage is

6.

129’ LT

Place (2) 2” HDPE conduits.

Approximate depth 36 inches

Once staking for ROW and proposed drainage is

7.

STA 1093+01

95’ LT

Place (2) 2” HDPE conduits.

Approximate depth 36 inches

Once staking for ROW and proposed FM is completed, MCI will begin new placement process

8.

New 96 FOC

STA 136+09

165’ LT

Place new 96

FOC

Once new conduit and handholes are placed

9.

New 96 FOC

Place new 96

FOC

Once new conduit and handholes are placed

10.

Splicing and

Testing

Splice and Test new 96 FOC

Once new 96 FOC is placed

11.

Existing 96 FOC

Remove existing

96 FOC

Once new 96 FOC is spliced and tested

12.

Existing 96 FOC

Remove existing

96 FOC

Once new 96 FOC is spliced and tested

13.

Existing (1) 2” HDPE conduit

Place existing conduit OOS

Once existing 96 FOC is removed

14.

Existing (2) 2” HDPE w/ FOC

STA 1098+40

STA 1100+72

Hold/ Guard/ Protect existing conduit

Construction of Force Main

15.

STA 1101+30

108.6’ LT

Hold/ Guard/

Construction of Water Main and walve

Hillsborough County County Road: 672 Plans Dated: 6/12/2026 Project Phase: Revised 100% CIP Number: 69647.000 Project Name: Big Bend Road from US 41 to Covington Garden Drive Utility Agency/Owner (UAO): MCI Metro Access Transmission Services

Tamishe Rodriguez

Section C. Disposition of Facilities (List All Existing & Proposed) on Project

Act No.

Type / Size /

Material

From Station/Offset

To Station/Offset

Description of Utility Work

Dependent Activities

M.O.T.

Phase

No.

Consecutive Calendar Days

Prior During

16.

STA 1101+30

108.6’ LT

Hold/ Guard/

Construction of Water Main and valve

17.

STA 1105+48

STA 1109+00

118’ LT

Hold/ Guard/

Construction of Force Main

Hillsborough County County Road: 672 Plans Dated: 6/12/2026 Project Phase: Revised 100% CIP Number: 69647.000 Project Name: Big Bend Road from US 41 to Covington Garden Drive Utility Agency/Owner (UAO): MCI Metro Access Transmission Services

Tamishe Rodriguez

2026-07-06T13:16:53-0400
Michael Krol
2026-07-08T09:49:44-0400
Tamishe J Rodriguez
2026-07-08T11:41:01-0400
Lisa Strout
2026-07-08T14:53:03-0400
Manuel E. Santos

File details come from the government source that posted it. Updated .