29-Attachment I- Utility Relocation Schedule CIP 69647.000 100% URS PGS7-10-2026 REV 1SignedTR.pdf

PDF 344 KB Posted

Attached to
Big Bend Road from US 41 to Covington Garden Dr.
Solicitation number
IFB-26-00378
Issued by
Hillsborough County, Florida

About this file

This document is a Utility Relocation Schedule prepared by Peoples Gas System, a utility agency/owner, for the Big Bend Road project (County Road 672, CIP Number 69647.000) in Hillsborough County, Florida. The schedule outlines utility relocation, adjustment, and protection requirements for gas mains and associated infrastructure along Big Bend Road from US 41 to Covington Garden Drive, based on project plans dated June 12, 2026. The project encompasses the installation of new 6-inch and 2-inch coated steel gas mains, removal of retired gas mains, and installation of new gas valves at multiple locations along the roadway corridor. Work is estimated to require 120 calendar days for preliminary engineering and material procurement prior to county project construction, with zero calendar days allocated during construction. The schedule was authorized by Patrick Allen (Gas Design Project Manager) on July 10, 2026, and approved by Hillsborough County's Manuel E. Santos and Lisa Strout on the same date. The relocation schedule is valid for one year from the authorization date.

The document specifies that Peoples Gas System employees and subcontractors operate on a standard Monday through Friday, 8 a.m. to 5 p.m. schedule, excluding observed holidays, with any work outside these hours requiring 72 hours advance scheduling and verification. All work must comply with Hillsborough County's Utility Agreement Management (UAM) requirements and obtain appropriate utility permits. An 18-inch separation clearance must be maintained with all existing gas mains and facilities. The project contacts include UAO Project Representative Patrick Allen (813-460-0454) and UAO Field Representative Javier Vazquez (813-275-3726), with facility location available through Sunshine 811. The document notes that Peoples Gas System may grout fill and retire gas mains under paved roadways as an alternative to removal, and that crew availability may be limited due to emergency response obligations elsewhere. The overall Big Bend Road project, which includes resurfacing and widening approximately 0.75 miles of existing roadway with associated drainage and sidewalk improvements, carries an estimated cost of $21,624,946.34.

View the file

Other files

File Type Posted
Attachment E- 69692000 BigBendWest Drainage Design Documentation Vol. II Final.pdf PDF
21-Attachment B- Geo Report - 69692000 100P Misc Structures 2025-11-20.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 Spectrum Revised URS 7.13.2026 TR LS.pdf PDF
Attachment B- Geo Report - 69692000 100P Misc Structures 2025-11-20.pdf PDF
Attachment H- Plans- Lighting.pdf PDF
41-Attachment L- CSX Coordination.pdf PDF
Attachment G- FDOT Grant Agreement.pdf PDF
Attachment I- Utility Relocation Schedule CIP 69647.000 Utility Cert Letter 7.15.26.pdf PDF
27-Attachment I- Utility Relocation Schedule 69647.000 100% REVISED - TEC UWS - REV4 7.13.26 TR LS.pdf PDF
13-AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
2-Florida Trench Safety Act, Certification and Disclosure Statement.pdf.pdf PDF
43-Attachment M- Work Class Percentage.pdf PDF
34-Attachment I- Utility Relocation Schedule 69647.000 Spectrum Revised URS 7.13.2026 TR LS.pdf PDF
46-Attachment G- FDOT Grant Agreement.pdf PDF
Attachment B- Geo Report - 69692000 PhIV Rdwy Soil Survey Report 2025-11-20.pdf PDF
40-Attachment K- Insurance Requirements.pdf PDF
52-Attachment H- Plans- ITS.pdf PDF
48-Attachment H- Location Map.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 100% REVISED - TEC UWS - REV4 7.13.26 TR LS.pdf PDF
Attachment H- Location Map.pdf PDF
11-Direct Deposit Authorization Form 5.15.2025.pdf.pdf PDF
AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
3-Allowance Authorization Release Form.pdf.pdf PDF
Attachment D- Permits - SWFWMD ERP 43024488.004 Approved.pdf PDF
17-Attachment F- 69692000 6050BigBend ROE ChildcareBrandon 10-9-25 Signed.pdf PDF
Agreement - Construction - Stand Alone.docx.pdf PDF
54-Attachment K- CSX Insurance Receipt.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 BIG BEND US 41 TO COVINGTON FTR URS 071426 TR LS.pdf PDF
39-Attachment J- CSX1036508- Agreement.pdf PDF
Attachment B- Geo Report - 69692000 Kings Lake Dr Misc Struc 100% Geo Report SS.pdf PDF
8-Change Order Form.pdf.pdf PDF
42-Agreement - Construction - Stand Alone.docx.pdf PDF
Attachment E- 69692000 BigBendWest Drainage Design Documentation Vol. I Final SS (1).pdf PDF
14-Attachment D- Permits - SWFWMD ERP 43024488.004 Approved.pdf PDF
23-Attachment E- 69692000 Waterset-Kings Lake Drainage Memo.pdf PDF
Attachment F- 669692000 6089BigBend ROE HomeDepot 10-9-25 signed.pdf PDF
20-Attachment B- Geo Report - 69692000 PhIV Rdwy Soil Survey Report 2025-11-20.pdf PDF
Attachment B- Geo Report - 69692000 Waterset Trail 100% RSS SS.pdf PDF
47-Attachment H- Clear Letters 2.pdf PDF
18-Attachment F- 669692000 BayIndustrial ROE 10-9-25. signed.pdf PDF
30-Attachment I- Utility Relocation Schedule CIP 69647.000 URS Uniti Fiber REV 3 7.10.26 TR LS.pdf PDF
Attachment F- 669692000 BayIndustrial ROE 10-9-25. signed.pdf PDF
Attachment I- Utility Relocation Schedule CIP 69647.000 100% URS PGS7-10-2026 REV 1SignedTR.pdf PDF
36-Bid Bond.doc.doc DOC document
9-Insurance Certificate.doc.doc DOC document
31-Attachment I- Utility Relocation Schedule MCI 69647.000 100% URS WSP-8-26 LS.pdf PDF
Attachment A- Construction Sign 2026.pdf PDF
32-Attachment I- Utility Relocation SchedCIP 69647 000 US 41 to Covington Garden Drive Zayo UWS 71326 TR LS.pdf PDF
1-Drug Free Workplace Form.doc.doc DOC document
Attachment E- 69692000 Waterset-Kings Lake Drainage Memo.pdf PDF
Show 40 more

Latest 50 of 89 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Hillsborough County County Road: 672 (Big Bend Rd) Plans Dated: 6/12/2026

CIP Number: 69647.000 Project Name: Big Bend Road from US 41 to Covington Garden Drive

Utility Agency/Owner (UAO): Peoples Gas System

NON-CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

Total Preliminary (Engineering) 0 Prior to County Project Construction 120

Total Material Procurement 120 During County Project Construction 0

Total Right-of-Way Acquisition 0 As-Built Information _____________

Total Other (Permitting) 30 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Hillsborough County, the roadway contractor, and other right-of-way users, the location, relocation, adjustment, installation, and/or protection of facilities, on this Hillsborough County project. The following data is based on the plans dated as listed in the Title Block.

Any deviation by Hillsborough County or its Contractor from plans, as provided may render this work schedule null and void.

Upon notification by, Hillsborough County of such change, this utility may require additional days for assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond the control of the UAO that could not reasonably be anticipated by the UAO and which could not be avoided by the UAO with the exercise of due diligence at the time of the occurrence. The UAO agrees to notify Hillsborough County in writing prior to starting, stopping, resuming, or completing work. The UAO is to provide As-Built information.

The UAO shall obtain a utility permit and comply with the requirements of the Hillsborough County UAM.

During the project, the UAO shall locate their facilities within 48 hours of notice to their Representative: Sunshine 811 Telephone Number: 811 -

UAO Project Representative: Patrick Allen Telephone Number: 813-460-0454

UAO Field Representative: Javier Vazquez Telephone Number: 813-275-3726

This document is a printout of a Hillsborough County form maintained in an electronic format and all revisions thereto by the UAO in the form of additions, deletions or substitutions are reflected only in an Appendix entitled “Changes to Form Document” and no change is made in the text of the document itself. Hand notations on affected portions of this document may refer to changes reflected in the above-named Appendix but are for reference purposes only and do not change the terms of the document. By signing this document, the UAO hereby represents that no change has been made to the text of this document except through the terms of the Appendix entitled “Changes to Form Document”.

You MUST signify by selecting or checking which of the following applies:

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: **Engineer of Record (EOR): Acceptance by Hillsborough

County:

(Signature) (Signature) (Signature)

Patrick Allen

Tamishe J. Rodriguez, P.E.

Manuel E. Santos, E.I.

(Printed Name) (Printed Name) (Printed Name)

Gas Design Project Manager

Engineer of Record

County Project Manager

(Title) (Title) (Title)

7/10/2026

(Date) (Date) (Date)

Final Approval by Hillsborough County:

(Signature) (Date)

Lisa Strout Capital Utility Manager (Printed Name) (Title)

(**When requested by the County, the EOR will attest to compatibility of plans, specifications and Utility Work Schedule)

Rodriguez, Tamishe (ChinTa) Text Box 7/10/2026

Special Conditions and Constraints

1. THE TECO PEOPLES GAS 24-HOUR EMERGENCY NUMBER 1-877-TECO-PGS (1-877-832-6747)

2. TECO PEOPLES GAS CREW AVAILABILITY MAY BE AFFECTED OR LIMITED DUE TO OUR REQUIRED

RESPONSE TO EMERGENCY CONDITIONS ELSEWHERE. THIS LIMITATION WILL BE DEPENDENT UPON THE

SEVERITY AND LOCATION OF THE EMERGENCY.

3. TECO PEOPLES GAS EMPLOYEES AND SUBCONTRACTORS NORMAL WORK SCHEDULE IS MONDAY

THROUGH FRIDAY FROM 8 A.M. TO 5 P.M., EXCLUDING TECO PEOPLES GAS OBSERVED HOLIDAYS (NEW YEARS

DAY, GOOD FRIDAY, MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY, THE FRIDAY AFTER

THANKSGIVING DAY, CHRISTMAS EVE DAY, AND CHRISTMAS DAY). ANY TECO PEOPLES GAS ASSISTANCE

REQUESTED FORM THE COUNTY, THEIR CONTRACTOR OF SUBCONTRACTOR OUTSIDE OF THESE NORMAL

WORKING HOURS MUST BE SCHEDULED 72 HOURS IN ADVANCE. TECO PEOPLES GAS REQUIRES VERIFICATION

THAT THE CREWS ARE STILL NEEDED ON THE ACTUAL WORKDAY (MONDAY THROUGH FRIDAY) THAT HAD

PREVIOUSLY BEEN REQUESTED OR THE LAST BUSINESS DAY BEFORE THE REQUESTED WEEKEND OR

HOLIDAY.

4. TECO PEOPLES GAS MAY GROUT FILL AND RETIRE GAS MAINS THAT ARE UNDER PAVED ROADWAYS

AND

DRIVEWAYS AS AN ALTERNATIVE TO REMOVING THEM.

5. AN 18” SEPARATION CLEARANCE MUST BE MAINTAINED WITH ALL EXISTING TECO PEOPLES GAS

MAINS/FACILITIES.

6. THIS RELOCATION SCHEDULE IS VALID FOR 1 YEAR FROM THE DATE SIGNED BY THE AUTHORIZED

UTILITY AGENT.

C. Disposition of Facilities (List All Existing & Proposed) on Project

TYPE / SIZE /

MATERIAL / OFFSET

TO BASELINE FROM

STA TO STA

DESCRIPTION

OF

UTILITY WORK

DEPENDENT

ACTIVITIES

M.O.T.

PHASE

NUMBER

CONSECUTIVE

CALENDAR

DAYS

Prior During

GAS MAIN / 6” /

COATED STEEL /

STA. 1082+35, 56’ RT

TO

STA. 1090+00, 117’ RT

INSTALL NEW 6” COATED STEEL

GAS MAIN 2’ N OF ROW AT >10’

DEPTH BELOW EXISTING

GRADE

APPROVED PERMIT, STAKING

OF STORM STRUCTURES AND

ROW,

N/A 25 0

GAS MAIN / 6” /

COATED STEEL /

STA. 1082+40, 56’ RT

TO

STA. 1089+95, 56’ RT

REMOVE RETIRED 6” COATED

STEEL GAS MAIN

INSTALLATION, TESTING, AND

ENRGIZING OF NEW 6” COATED

STEEL GAS MAIN,

N/A 5 0

GAS MAIN / 6” /

COATED STEEL /

STA. 1095+40, 56’ RT

TO

STA. 1095+60, 56’ RT

INSTALL NEW 6” COATED STEEL

GAS MAIN AT >10’ DEPTH

BELOW EXISTING GRADE

APPROVED PERMIT, STAKING

OF S-37,

N/A 20 0

GAS MAIN / 6” /

COATED STEEL /

STA. 1095+45, 56’ RT

TO

STA. 1095+55, 56’ RT

REMOVE RETIRED 6” COATED

STEEL GAS MAIN

INSTALLATION, TESTING, AND

ENRGIZING OF NEW 6” COATED

STEEL GAS MAIN,

N/A 1 0

GAS MAIN / 6” /

COATED STEEL /

STA. 1100+80, 56’ RT

TO

STA. 1118+40, 52 RT

INSTALL NEW 6” COATED STEEL

GAS MAIN

APPROVED PERMIT, STAKING

OF STORM STRUCTURES AND

ROW,

N/A 30 0

GAS MAIN / 6” /

COATED STEEL /

STA. 1100+85, 56’ RT

TO

STA. 1118+35, 54’ RT

REMOVE RETIRED 6” COATED

STEEL GAS MAIN

INSTALLATION, TESTING, AND

ENRGIZING OF NEW 6” COATED

STEEL GAS MAIN,

N/A 15 0

GAS MAIN / 2” /

COATED STEEL /

STA. 1115+30, 86’ RT

TO

STA. 1115+60, 126’ RT

INSTALL NEW 2” COATED STEEL

GAS MAIN

APPROVED PERMIT, STAKING

OF STORM STRUCTURES AND

ROW,

N/A 20 0

GAS MAIN / 2” /

COATED STEEL /

STA. 1115+30, 57’ RT

TO

STA. 1115+60, 118’ RT

REMOVE RETIRED 2” COATED

STEEL GAS MAIN AND EXISTING

VALVE

INSTALLATION, TESTING, AND

ENRGIZING OF NEW 2” COATED

STEEL GAS MAIN,

N/A 1 0

GAS MAIN / 6” /

COATED STEEL /

STA. 1082+35, 60’ RT

INSTALL NEW GAS VALVE APPROVED PERMIT, STAKING

OF STORM STRUCTURES AND

ROW,

N/A 1 0

GAS MAIN / 6” /

STA. 1100+80, 60’ RT

ROW,

N/A 1 0

GAS MAIN / 2” /

STA. 1115+60, 100’ RT

ROW,

N/A 1 0

2026-07-10T08:52:32-0400
Patrick Allen
I have reviewed this document
2026-07-10T11:28:46-0400
Tamishe J Rodriguez
2026-07-10T13:59:17-0400
Manuel E. Santos
2026-07-10T15:11:56-0400
Lisa Strout

File details come from the government source that posted it. Updated .