34-Attachment I- Utility Relocation Schedule 69647.000 Spectrum Revised URS 7.13.2026 TR LS.pdf
PDF 792 KB Posted
- Attached to
- Big Bend Road from US 41 to Covington Garden Dr.
- Solicitation number
- IFB-26-00378
- Issued by
- Hillsborough County, Florida
About this file
This is a Utility Relocation Schedule document submitted by Spectrum Sunshine State, LLC to Hillsborough County for the Big Bend Road project (CIP Number 69647.000), which involves resurfacing and widening approximately 0.75 miles of existing 4-lane divided rural highway to a 6-lane urban typical section with curb and gutter, closed drainage system, 10-foot sidewalks on each side, and median. The project scope includes milling and resurfacing of Kings Lake Drive and an estimated project cost of $21,624,946.34. The utility relocation work involves the installation of proposed Buried Fiber Optic Cable (BFOC) in 2-inch conduit at varying depths (4 feet to 9 feet) across multiple stations along Big Bend Road, removal of existing fiber optic cable (FOC) and CATV infrastructure, and installation of handholes at designated locations. The utility work is dependent upon permitting and proposed splicing/cutover activities. Non-construction items include engineering design (47 calendar days), permitting (14 calendar days), and material procurement (20 calendar days) prior to county project construction, while construction items include 105 calendar days prior to county construction and 2 calendar days during county construction.
The utility relocation schedule specifies that splicing time requires 23 days and impacts the splicing ticket, with all work dependent on permitting approvals. The UAO Project Representative is Paul Bustamante (813-538-2924), and the document was dated July 13, 2026, with approval signatures from Engineer of Record Tamishe J. Rodriguez, P.E., County Project Manager Manuel E. Santos, E.I., and Capital Utility Manager Lisa Strout, P.E. The utility is responsible for obtaining a utility permit and complying with Hillsborough County Utility Accommodation Manual requirements. The UAO must locate facilities within 48 hours of notice and provide as-built information upon project completion. The document indicates no changes were made to the form document itself, with all revisions reflected through an Appendix entitled "Changes to Form Document."
View the file
Other files
Show 40 more
Latest 50 of 89 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Hillsborough County County Road: 672 (Big Bend Rd) Plans Dated: 6/12/2026
CIP Number: 69647.000 Project Name: Big Bend Road from US 41 to Covington Garden Drive
Utility Agency/Owner (UAO): Spectrum Sunshine State, LLC
NON-CONSTRUCTION ITEMS
ESTIMATED
*CALENDAR DAYS
CONSTRUCTION ITEMS
ESTIMATED
*CALENDAR DAYS
Engineering Design 47 Prior to County Project Construction 105
Permitting 14 During County Project Construction 2
Material Procurement 20 As-Built Information _____________
Total Other 30 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Hillsborough County, the roadway contractor, and other right-of-way users, the location, relocation, adjustment, installation, and/or protection of facilities, on this Hillsborough County project. The following data is based on the plans dated as listed in the Title Block.
Any deviation by Hillsborough County or its Contractor from plans, as provided may render this work schedule null and void.
Upon notification by, Hillsborough County of such change, this utility may require additional days for assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond the control of the UAO that could not reasonably be anticipated by the UAO and which could not be avoided by the UAO with the exercise of due diligence at the time of the occurrence. The UAO agrees to notify Hillsborough County in writing prior to starting, stopping, resuming, or completing work. The UAO is to provide As-Built information.
The UAO shall obtain a utility permit and comply with the requirements of the Hillsborough County UAM.
During the project, the UAO shall locate their facilities within 48 hours of notice to their Representative: Paul Bustamante Telephone Number: 813-538-2927 -
UAO Project Representative: Paul Bustamante Telephone Number: 813-538-2924
UAO Field Representative: Paul Bustamante Telephone Number: 813-538-2924
This document is a printout of a Hillsborough County form maintained in an electronic format and all revisions thereto by the UAO in the form of additions, deletions or substitutions are reflected only in an Appendix entitled “Changes to Form Document” and no change is made in the text of the document itself. Hand notations on affected portions of this document may refer to changes reflected in the above-named Appendix but are for reference purposes only and do not change the terms of the document. By signing this document, the UAO hereby represents that no change has been made to the text of this document except through the terms of the Appendix entitled “Changes to Form Document”.
You MUST signify by selecting or checking which of the following applies:
No changes to forms document.
Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.
Authorized Utility Agent:
**Engineer of Record (EOR): Acceptance by Hillsborough County:
(Signature) (Signature) (Signature)
Paul Bustamante
Tamishe J. Rodriguez, P.E.
Manuel E. Santos, E.I
(Printed Name) (Printed Name) (Printed Name)
Construction Coordinator
Engineer of Record
County Project Manager
(Title) (Title) (Title)
7.13.26
(Date) (Date) (Date)
Final Approval by Hillsborough County:
(Signature) (Date)
Lisa Strout, P.E. Capital Utility Manager (Printed Name) (Title)
Rodriguez, Tamishe (ChinTa) Text Box 7/13/2026
(**When requested by the County, the EOR will attest to compatibility of plans, specifications and Utility Work Schedule)
Special Conditions and Constraints
C. Disposition of Facilities (List All Existing & Proposed) on Project
TYPE / SIZE /
MATERIAL / OFFSET
TO BASELINE FROM
STA TO STA
DESCRIPTION
OF
UTILITY WORK
DEPENDENT
ACTIVITIES
M.O.T.
PHASE
NUMBER
CONSECUTIVE
CALENDAR
DAYS
Prior During
Sta 1076+72, 112’L to Sta 1087+97,59’L
Proposed new BFOC in 2’’ conduit At 6’ depth and place new HH
Permitting n/a 10 0
Sta 1086+97,59’L to Sta 1087+97,R crossing
Proposed new BFOC in 2’’ conduit At 6’ depth. Placing of handhole north & south side of BB
Permitting n/a 14 0
Sta 1086+97,59’L to Sta 1087+97,R crossing
Proposed new BFOC in 2’’ conduit At 6’ depth. Placing of handhole north & south side of BB
Permitting n/a 14 0
Sta 1086+97,59’L to Sta 1090+58,62’L
Proposed new UG CATV in 2’’ conduit at 9’ depth. Placing Hand hole
Permitting n/a 5 0
Sta 1086+97R Proposed new BFOC in 2’’ conduit.
Hand hole install
Permitting n/a 14 0
Sta 1107+41,97’Lto Sta 1109+57’L
Proposed new BFOC 2’’ conduit At depth 4’. Placement of H/H
Permitting n/a 4 0
Sta 1114,106’L to Sta 1117+20,105’L
Proposed new BFOC in 2’’ conduit at 4’ depth.
Permitting n/a 3 0
Sta 1115+63,121L to Sta 1115+63, 107’R
Proposed new BFOC in 2’’ conduit at crossing. 5’-11’ depth S-67,68,69
Permitting n/a 3 0
Sta 1114+97L Proposed new hand hole Permitting n/a .5 0
Sta 1117+20,105’L Proposed new hand hole Permitting n/a .5 0
Sta 1115+63,107R Proposed new hand hole Permitting n/a 1 0
Sta 1098+76,98’L Hold & monitor n/a 1 1 0
Sta 1076+72,112’L to Sta1087+97,59L&97’R
FOC to remove Permitting/proposed splicing cutover n/a 2 0
Sta 1087+60’L to Sta 1090+58,60’L
FOC/CATV to remove Permitting/proposed splicing cutover n/a 2 0
Sta 1087+97,43’L -to Sta 1087+97,57’R
FOC/CATV to remove and adjust existing HH
Permitting/proposed splicing cutover n/a 2 0
Sta 1107+41,100’L to Sta 1109+57,100’L
FOC to remove Permitting/proposed splicing cutover n/a 2 0
Sta 1114+105’L to 1117+35,104’L
FOC/CATV to remove Permitting/proposed splicing cutover n/a 2 0
Sta 1115+20,104’L to1115+64,55’R
FOC/CATV to remove Permitting/proposed splicing cutover n/a 2 0
Splicing Time
Required 23 day impacting splicing ticket n/a 23 0
| 2026-07-13T15:37:45-0400 | |
| Tamishe J Rodriguez |
| 2026-07-14T06:33:01-0400 | |
| Lisa Strout |
| 2026-07-14T08:08:35-0400 | |
| Manuel E. Santos |
File details come from the government source that posted it. Updated .