27-Attachment I- Utility Relocation Schedule 69647.000 100% REVISED - TEC UWS - REV4 7.13.26 TR LS.pdf
PDF 66 KB Posted
- Attached to
- Big Bend Road from US 41 to Covington Garden Dr.
- Solicitation number
- IFB-26-00378
- Issued by
- Hillsborough County, Florida
About this file
This is a Utility Relocation Schedule document prepared by Tampa Electric Company (TECO) for Hillsborough County, Florida, regarding utility facility relocations on County Road 672 for the Big Bend Road project (CIP Number 69647.000). The project involves resurfacing and widening approximately 0.75 miles of existing 4-lane divided rural highway to a 6-lane urban typical section with curb and gutter, closed drainage system, 10-foot sidewalks on each side, and median, with an estimated project cost of $21,624,946.34. The utility relocation schedule specifies the location, relocation, adjustment, installation, and protection of TECO facilities along the project corridor. TECO requires a minimum of 30 calendar days to schedule work related to this project, including during-construction activities, line cover installations, overhead/underground outages, pole holding, and facility monitoring requests. Non-construction preliminary work is estimated at 30 calendar days prior to county project construction, with material procurement at 0 days and permitting at 14 days. Construction-related work activities total 50 calendar days prior to county project construction and 1 day during county project construction.
The schedule outlines disposition of multiple TECO facilities, including 13.2 KV overhead and buried electric lines, fiber optic cables, poles, conduits, and pullboxes to be installed and removed at specified stations along the project corridor. Work is dependent upon completion of related activities, with all installation work requiring execution of the Utility Work Schedule and Notice to Proceed, while removal work requires installation and energization of new facilities. TECO's normal work schedule is Monday through Friday from 8 a.m. to 5 p.m., excluding observed holidays, and line crews will not work in adverse weather conditions. The document notes that line crew availability may be affected by emergency response requirements. TECO reserves the right to require a new schedule if Hillsborough County does not begin construction within 12 months of the signature date, and pole removal cannot occur until all joint users (such as Frontier, Spectrum, and traffic signals) have been removed and the joint user has properly notified TECO's field representative.
View the file
Other files
Show 40 more
Latest 50 of 89 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Hillsborough County County Road: 672 Plans Dated: 6/12/2026 CIP Number: 69647.000 Project Name: BIG BEND RD FROM US 41 TO COVINGTON GARDEN DR Utility Agency/Owner (UAO): TAMPA ELECTRIC COMPANY
NON-CONSTRUCTION ITEMS ESTIMATED CONSTRUCTION ITEMS ESTIMATED
*CALENDAR DAYS *CALENDAR DAYS
Total Preliminary 30 Prior to County Project Construction 50 Total Material Procurement 0 During County Project Construction 1 Total Right-of-Way Acquisition 0 As-Built Information Total Permitting 14 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Hillsborough County, the roadway contractor, and other right-of-way users, the location, relocation, adjustment, installation, and/or protection of facilities, on this Hillsborough County project. The following data is based on the plans dated as listed in the Title Block.
Any deviation by Hillsborough County or its Contractor from plans, as provided may render this work schedule null and void.
Upon notification by, Hillsborough County of such change, this utility may require additional days for assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond the control of the UAO that could not reasonably be anticipated by the UAO and which could not be avoided by the UAO with the exercise of due diligence at the time of the occurrence. The UAO agrees to notify Hillsborough County in writing prior to starting, stopping, resuming, or completing work. The UAO is to provide As-Built information.
The UAO shall obtain a utility permit and comply with the requirements of the Hillsborough County UAM.
During the project, the UAO shall locate their facilities within 48 hours of notice to their Representative: Call 811 Sunshine
UAO Project Representative: Jason T. Payne Telephone Number: 813-275-3428 UAO Field Representative: Jerry Clementi Telephone Number: 313-283-0381 This document is a printout of a Hillsborough County form maintained in an electronic format and all revisions thereto by the UAO in the form of additions, deletions or substitutions are reflected only in an Appendix entitled “Changes to Form Document” and no change is made in the text of the document itself. Hand notations on affected portions of this document may refer to changes reflected in the above-named Appendix but are for reference purposes only and do not change the terms of the document. By signing this document, the UAO hereby represents that no change has been made to the text of this document except through the terms of the Appendix entitled “Changes to Form Document”.
You MUST signify by selecting or checking which of the following applies:
No changes to forms document.
Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.
Authorized Utility Agent: **Engineer of Record (EOR): Acceptance by Hillsborough County:
(Signature) (Signature) (Signature)
Jason T. Payne Tamishe J. Rodriguez, P.E. Manuel Santos,E.I.
(Printed Name) (Printed Name) (Printed Name)
Project Manager E.O.R. County Project Manager (Title) (Title) (Title)
7/13/26 (Date) (Date) (Date)
Final Approval by Hillsborough County:
(Signature)
Lisa Strout (Printed Name)
(Date)
Capitol Utility Manager (Title)
(**When requested by the County, the EOR will attest to compatibility of plans, specifications and Utility Work Schedule)
Rodriguez, Tamishe (ChinTa) Text Box 7/13/2026
Utility Agency/Owner (UAO): TAMPA ELECTRIC COMPANY
Special Conditions and Constraints
SPECIAL NOTATIONS
1. TEC (TAMPA ELECTRIC COMPANY) REQUIRES A MINIMUM OF 30 CALENDAR DAYS TO SCHEDULE ANY TEC WORK RELATED TO THIS PROJECT, INCLUDING BUT NOT LIMITED TO "DURING CONSTRUCTION" WORK IDENTIFIED IN THIS RELOCATION SCHEDULE, REQUESTS FOR THE INSTALLATION OF LINE COVER, REQUESTS FOR OVERHEAD/UNDERGROUND ELECTRIC OUTAGE(S), REQUESTS FOR TEC POLE HOLDING, AND/OR REQUESTS TO MONITOR ANY TEC FACILITIES WITH SAID REQUESTS BEING INITIATED BY HILLSBOROUGH COUNTY, THE HILLSBOROUGH COUNTY CONTRACTOR AND/OR THEIR SUBCONTRACTOR. THIS NOTICE INCLUDES POLE REMOVAL ONCE A JOINT USER HAS VACATED THE FACILITY AND PROPERLY NOTICIFIED TEC FIELD REPRESENTATIVE TO ALLOW SCHEDULING OF ACTIVITY TO OCCUR.
2. FOR SAFETY REASONS, TEC LINE CREWS SHALL NOT WORK IN ADVERSE WEATHER CONDITIONS.
3. THE TEC LINE CREW AVAILABILITY SHALL BE AFFECTED AND/OR LIMITED DUE TO OUR REQUIRED RESPONSE TO EMERGENCY CONDITIONS.
THIS LIMITATION WILL BE DEPENDENT UPON THE SEVERITY OF THE EMERGENCY.
4. TEC AND/OR TEC'S SUBCONTRACTORS NORMAL WORK SCHEDULE IS MONDAY THROUGH FRIDAY FROM 8 A.M. TO 5 P.M., EXCLUDING TEC OBSERVED HOLIDAY'S WHICH INCLUDE NEW YEARS DAY, GOOD FRIDAY, MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY, THE
FRIDAY AFTER THANKSGIVING, CHRISTMAS EVE DAY AND CHRISTMAS DAY.
5. TEC CAN NOT REMOVE ANY TEC POLES THAT HAVE EXISTING JOINT USERS STILL ATTACHED. SUBSEQUENTLY, ALL JOINT USERS SUCH AS FRONTIER, SPECTRUM, TRAFFIC, ETC. MUST BE REMOVED BEFORE TEC CAN REMOVE THE POLE ITSELF.
6. IF A NEW TEC ELECTRIC SERVICE MUST BE ESTABLISHED, PLEASE EMAIL ONE SOURCE AT CEREPS@TECOENERGY.COM OR 813-635-1500 AND REQUEST THE "PROCEDURE FOR ESTABLISHING A NEW ELECTRIC SERVICE". ALSO INCLUDED IN THIS SAME TEC DOCUMENT IS THE
PROCEDURE FOR THE REMOVAL OF AN EXISTING TEC ELECTRIC SERVICE.
7. THIS RELOCATION SCHEDULE WILL BE CONSIDERED VOID SHOULD HILLSBOROUGH COUNTY NOT BEGIN CONSTRUCTION WITHIN 12 MONTHS FROM SIGNATURE DATE OF TEC REPRESENTATIVE. IF SCHEDULE SHOULD BECOME VOID, TEC WILL THEN REQUIRE THE LATEST SET OF PLANS THAT REFLECT CURRENT FIELD CONDITIONS AT THAT TIME FOR REVIEW AND RE-WRITE OF SCHEDULE IF DEEMED NECESSARY BY
TEC.
8. IF A CSX FLAGGER IS REQUIRED, THE SCHEDULING OF SUCH SERVICES MAY NECESSITATE A LEAD TIME OF UP TO 6 MONTHS.
EMERGENCY NUMBER FOR NIGHTS, WEEKENDS & TECO HOLIDAYS - 877-588-1010
PROJECT MANAGEMENT: CSADMIN@TECOENERGY.COM
13KV DISTRIBUTION FACILITIES CONTACT: JERRY CLEMENTI 313-283-0381
Utility Agency/Owner (UAO): TAMPA ELECTRIC COMPANY
C. Disposition of Facilities (List All Existing & Proposed) on Project
TYPE / SIZE /
MATERIAL / OFFSET
TO BASELINE FROM
STA TO STA
DESCRIPTION
OF
UTILITY WORK
DEPENDENT
ACTIVITIES
M.O.T.
PHASE
NUMBER
CONSECUTIVE
CALENDAR
DAYS
Prior During
13.2 KV OE & 96 F
1077+47’ LT 65’ TO
1078+26’ LT 64’
INSTALL & SPLICE FIBER ONCE PROPOSED POLE(S) ARE
INSTALLED
PRIOR 1 0
POLE
1078+26’ LT 64’
INSTALL 50’ POLE & SET DEEPER ONCE EXECUTED UWS & NTP IS
RECEIVED
PRIOR 2 0
13.2 KV BE
1078+26’ LT 64’ TO
METER
INSTALL
INTERCEPT EXISTING 4”
CONDUIT
ONCE EXECUTED UWS & NTP IS
RECEIVED
PRIOR 5 0
13.2 KV OE & 96 F
1078+26’ LT 64’ TO
1079 +87’ LT 63’
INSTALL & SPLICE FIBER ONCE PROPOSED POLE(S) ARE
INSTALLED
PRIOR 1 0
13.2 KV OE & 96 F
1079 +92’ LT 62’ TO
1082+34’ LT 61’
INSTALL & SPLICE FIBER ONCE PROPOSED POLE(S) ARE
INSTALLED
PRIOR 1 0
13.2 KV OE & 96 F
1091+38’ LT 87’ TO
1093+06’ LT 92’
INSTALL & SPLICE FIBER ONCE PROPOSED POLE(S) ARE
INSTALLED
PRIOR 1 0
POLE
1093+06’ LT 92’
INSTALL 45’ POLE & SET
DEEPER
ONCE EXECUTED UWS & NTP IS
RECEIVED
PRIOR 2 0
13.2 KV OE & 96 F
1093+06’ LT 92’ TO
1093+47’ LT 93’
INSTALL & SPLICE FIBER ONCE PROPOSED POLE(S) ARE
INSTALLED
PRIOR 1 0
13.2 KV OE & 96 F
1093+06’ LT 92’ TO
1092+69’ LT 129’
INSTALL & SPLICE FIBER ONCE PROPOSED POLE(S) ARE
INSTALLED
PRIOR 1 0
POLE
1097 + 46, 106R
HOLD POLE SEE SPECIAL CONDITIONS 1 0 1
13.2KV BE
1102+70’ LT 108’ TO
1102+77’ RT 217’
INSTALL
(1) 4” CONDUIT
AT MINIMUM DEPTH OF 8’
ONCE EXECUTED UWS & NTP
IS RECEIVED
PRIOR 3 0
PULLBOX
1102+77’ RT 217’
INSTALL ONCE EXECUTED UWS & NTP
IS RECEIVED
PRIOR 2 0
120/240 BE
303+82’ RT 49’ TO
305+71’ RT 50’
INSTALL
(1) 2” CONDUIT
AT MINIMUM DEPTH OF 36”
ONCE ROW & MAST ARM HAS
BEEN STAKED BY
CONTRACTOR
PRIOR 5 0
120/240 BE
305+71’ RT 50’ TO
402+17’ LT 24’
INSTALL
(1) 2” CONDUIT
AT MINIMUM DEPTH OF 36”
ONCE ROW & MAST ARM HAS
BEEN STAKED BY
CONTRACTOR
PRIOR 5 0
13.2 KV OE & 96 F
1077+47’ LT 65’ TO
1078+24’ LT 64’
REMOVE ONCE NEW FACILITIES HAVE
BEEN INSTALLED AND
ENERGIZED
PRIOR 1 0
POLE
1078+24’ LT 64’
REMOVE ONCE NEW FACILITIES HAVE
BEEN INSTALLED AND
ENERGIZED
PRIOR 1 0
13.2 KV BE
1078+24’ LT 64’ TO
METER
REMOVE ONCE NEW FACILITES HAVE
BEEN INSTALLED AND
ENERGIZED
PRIOR 3 0
13.2 KV OE & 96 F
1078+24’ LT 64’ TO
1079+92’ LT 62’
REMOVE ONCE NEW FACILITES HAVE
BEEN INSTALLED AND
ENERGIZED
PRIOR 1 0
POLE
1079+92’ LT 62’
REMOVE CABLE AND PLACE
CONDUIT OUT OF SERVICE
ONCE NEW FACILITES HAVE
BEEN INSTALLED AND
ENERGIZED
PRIOR 1 0
Utility Agency/Owner (UAO): TAMPA ELECTRIC COMPANY
13.2 KV OE & 96 F
1091+38’ LT 87’ TO
1092 +74’ LT 91’
REMOVE ONCE NEW FACILITES HAVE
BEEN INSTALLED AND
ENERGIZED
PRIOR 1 0
POLE
1092 +74’ LT 91’
REMOVE ONCE NEW FACILITES HAVE
BEEN INSTALLED AND
ENERGIZED
PRIOR 1 0
13.2 KV OE & 96 F
1092 +74’ LT 91’ TO
1092+69’ LT 129’
REMOVE ONCE NEW FACILITES HAVE
BEEN INSTALLED AND
ENERGIZED
PRIOR 1 0
13.2 KV OE & 96 F
1092 +74’ LT 91’ TO
1093 +47’ LT 93’
REMOVE ONCE NEW FACILITES HAVE
BEEN INSTALLED AND
ENERGIZED
PRIOR 1 0
13.2KV BE
1102+70’ LT 108’ TO
1102+77’ RT 217’
REMOVE CABLE AND PLACE
CONDUIT OUT OF SERVICE
ONCE NEW FACILITES HAVE
BEEN INSTALLED AND
ENERGIZED
PRIOR 1 0
PULLBOX
1102+77’ RT 217’
REMOVE ONCE NEW FACILITES HAVE
BEEN INSTALLED AND
ENERGIZED
PRIOR 2 0
120/240 BE
303+82’ RT 49’ TO
305+71’ RT 50’
REMOVE CABLE AND PLACE
CONDUIT OUT OF SERVICE
ONCE NEW FACILITES HAVE
BEEN INSTALLED AND
ENERGIZED
PRIOR 3 0
120/240 BE
305+71’ RT 50’ TO
402+17’ LT 24’
REMOVE CABLE AND PLACE
CONDUIT OUT OF SERVICE
ONCE NEW FACILITES HAVE
BEEN INSTALLED AND
ENERGIZED
PRIOR 3 0
| 2026-07-13T15:29:48-0400 | |
| Tamishe J Rodriguez |
| 2026-07-14T06:36:44-0400 | |
| Lisa Strout |
| 2026-07-14T08:09:25-0400 | |
| Manuel E. Santos |
File details come from the government source that posted it. Updated .