27-Attachment I- Utility Relocation Schedule 69647.000 100% REVISED - TEC UWS - REV4 7.13.26 TR LS.pdf

PDF 66 KB Posted

Attached to
Big Bend Road from US 41 to Covington Garden Dr.
Solicitation number
IFB-26-00378
Issued by
Hillsborough County, Florida

About this file

This is a Utility Relocation Schedule document prepared by Tampa Electric Company (TECO) for Hillsborough County, Florida, regarding utility facility relocations on County Road 672 for the Big Bend Road project (CIP Number 69647.000). The project involves resurfacing and widening approximately 0.75 miles of existing 4-lane divided rural highway to a 6-lane urban typical section with curb and gutter, closed drainage system, 10-foot sidewalks on each side, and median, with an estimated project cost of $21,624,946.34. The utility relocation schedule specifies the location, relocation, adjustment, installation, and protection of TECO facilities along the project corridor. TECO requires a minimum of 30 calendar days to schedule work related to this project, including during-construction activities, line cover installations, overhead/underground outages, pole holding, and facility monitoring requests. Non-construction preliminary work is estimated at 30 calendar days prior to county project construction, with material procurement at 0 days and permitting at 14 days. Construction-related work activities total 50 calendar days prior to county project construction and 1 day during county project construction.

The schedule outlines disposition of multiple TECO facilities, including 13.2 KV overhead and buried electric lines, fiber optic cables, poles, conduits, and pullboxes to be installed and removed at specified stations along the project corridor. Work is dependent upon completion of related activities, with all installation work requiring execution of the Utility Work Schedule and Notice to Proceed, while removal work requires installation and energization of new facilities. TECO's normal work schedule is Monday through Friday from 8 a.m. to 5 p.m., excluding observed holidays, and line crews will not work in adverse weather conditions. The document notes that line crew availability may be affected by emergency response requirements. TECO reserves the right to require a new schedule if Hillsborough County does not begin construction within 12 months of the signature date, and pole removal cannot occur until all joint users (such as Frontier, Spectrum, and traffic signals) have been removed and the joint user has properly notified TECO's field representative.

View the file

Other files

File Type Posted
Attachment E- 69692000 BigBendWest Drainage Design Documentation Vol. II Final.pdf PDF
21-Attachment B- Geo Report - 69692000 100P Misc Structures 2025-11-20.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 Spectrum Revised URS 7.13.2026 TR LS.pdf PDF
Attachment B- Geo Report - 69692000 100P Misc Structures 2025-11-20.pdf PDF
Attachment H- Plans- Lighting.pdf PDF
41-Attachment L- CSX Coordination.pdf PDF
Attachment G- FDOT Grant Agreement.pdf PDF
Attachment I- Utility Relocation Schedule CIP 69647.000 Utility Cert Letter 7.15.26.pdf PDF
13-AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
2-Florida Trench Safety Act, Certification and Disclosure Statement.pdf.pdf PDF
43-Attachment M- Work Class Percentage.pdf PDF
34-Attachment I- Utility Relocation Schedule 69647.000 Spectrum Revised URS 7.13.2026 TR LS.pdf PDF
46-Attachment G- FDOT Grant Agreement.pdf PDF
Attachment B- Geo Report - 69692000 PhIV Rdwy Soil Survey Report 2025-11-20.pdf PDF
40-Attachment K- Insurance Requirements.pdf PDF
52-Attachment H- Plans- ITS.pdf PDF
48-Attachment H- Location Map.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 100% REVISED - TEC UWS - REV4 7.13.26 TR LS.pdf PDF
Attachment H- Location Map.pdf PDF
11-Direct Deposit Authorization Form 5.15.2025.pdf.pdf PDF
AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
3-Allowance Authorization Release Form.pdf.pdf PDF
29-Attachment I- Utility Relocation Schedule CIP 69647.000 100% URS PGS7-10-2026 REV 1SignedTR.pdf PDF
Attachment D- Permits - SWFWMD ERP 43024488.004 Approved.pdf PDF
17-Attachment F- 69692000 6050BigBend ROE ChildcareBrandon 10-9-25 Signed.pdf PDF
Agreement - Construction - Stand Alone.docx.pdf PDF
54-Attachment K- CSX Insurance Receipt.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 BIG BEND US 41 TO COVINGTON FTR URS 071426 TR LS.pdf PDF
39-Attachment J- CSX1036508- Agreement.pdf PDF
Attachment B- Geo Report - 69692000 Kings Lake Dr Misc Struc 100% Geo Report SS.pdf PDF
8-Change Order Form.pdf.pdf PDF
42-Agreement - Construction - Stand Alone.docx.pdf PDF
Attachment E- 69692000 BigBendWest Drainage Design Documentation Vol. I Final SS (1).pdf PDF
14-Attachment D- Permits - SWFWMD ERP 43024488.004 Approved.pdf PDF
23-Attachment E- 69692000 Waterset-Kings Lake Drainage Memo.pdf PDF
Attachment F- 669692000 6089BigBend ROE HomeDepot 10-9-25 signed.pdf PDF
20-Attachment B- Geo Report - 69692000 PhIV Rdwy Soil Survey Report 2025-11-20.pdf PDF
Attachment B- Geo Report - 69692000 Waterset Trail 100% RSS SS.pdf PDF
47-Attachment H- Clear Letters 2.pdf PDF
18-Attachment F- 669692000 BayIndustrial ROE 10-9-25. signed.pdf PDF
30-Attachment I- Utility Relocation Schedule CIP 69647.000 URS Uniti Fiber REV 3 7.10.26 TR LS.pdf PDF
Attachment F- 669692000 BayIndustrial ROE 10-9-25. signed.pdf PDF
Attachment I- Utility Relocation Schedule CIP 69647.000 100% URS PGS7-10-2026 REV 1SignedTR.pdf PDF
36-Bid Bond.doc.doc DOC document
9-Insurance Certificate.doc.doc DOC document
31-Attachment I- Utility Relocation Schedule MCI 69647.000 100% URS WSP-8-26 LS.pdf PDF
Attachment A- Construction Sign 2026.pdf PDF
32-Attachment I- Utility Relocation SchedCIP 69647 000 US 41 to Covington Garden Drive Zayo UWS 71326 TR LS.pdf PDF
1-Drug Free Workplace Form.doc.doc DOC document
Attachment E- 69692000 Waterset-Kings Lake Drainage Memo.pdf PDF
Show 40 more

Latest 50 of 89 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Hillsborough County County Road: 672 Plans Dated: 6/12/2026 CIP Number: 69647.000 Project Name: BIG BEND RD FROM US 41 TO COVINGTON GARDEN DR Utility Agency/Owner (UAO): TAMPA ELECTRIC COMPANY

NON-CONSTRUCTION ITEMS ESTIMATED CONSTRUCTION ITEMS ESTIMATED

*CALENDAR DAYS *CALENDAR DAYS

Total Preliminary 30 Prior to County Project Construction 50 Total Material Procurement 0 During County Project Construction 1 Total Right-of-Way Acquisition 0 As-Built Information Total Permitting 14 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Hillsborough County, the roadway contractor, and other right-of-way users, the location, relocation, adjustment, installation, and/or protection of facilities, on this Hillsborough County project. The following data is based on the plans dated as listed in the Title Block.

Any deviation by Hillsborough County or its Contractor from plans, as provided may render this work schedule null and void.

Upon notification by, Hillsborough County of such change, this utility may require additional days for assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond the control of the UAO that could not reasonably be anticipated by the UAO and which could not be avoided by the UAO with the exercise of due diligence at the time of the occurrence. The UAO agrees to notify Hillsborough County in writing prior to starting, stopping, resuming, or completing work. The UAO is to provide As-Built information.

The UAO shall obtain a utility permit and comply with the requirements of the Hillsborough County UAM.

During the project, the UAO shall locate their facilities within 48 hours of notice to their Representative: Call 811 Sunshine

UAO Project Representative: Jason T. Payne Telephone Number: 813-275-3428 UAO Field Representative: Jerry Clementi Telephone Number: 313-283-0381 This document is a printout of a Hillsborough County form maintained in an electronic format and all revisions thereto by the UAO in the form of additions, deletions or substitutions are reflected only in an Appendix entitled “Changes to Form Document” and no change is made in the text of the document itself. Hand notations on affected portions of this document may refer to changes reflected in the above-named Appendix but are for reference purposes only and do not change the terms of the document. By signing this document, the UAO hereby represents that no change has been made to the text of this document except through the terms of the Appendix entitled “Changes to Form Document”.

You MUST signify by selecting or checking which of the following applies:

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: **Engineer of Record (EOR): Acceptance by Hillsborough County:

(Signature) (Signature) (Signature)

Jason T. Payne Tamishe J. Rodriguez, P.E. Manuel Santos,E.I.

(Printed Name) (Printed Name) (Printed Name)

Project Manager E.O.R. County Project Manager (Title) (Title) (Title)

7/13/26 (Date) (Date) (Date)

Final Approval by Hillsborough County:

(Signature)

Lisa Strout (Printed Name)

(Date)

Capitol Utility Manager (Title)

(**When requested by the County, the EOR will attest to compatibility of plans, specifications and Utility Work Schedule)

Rodriguez, Tamishe (ChinTa) Text Box 7/13/2026

Utility Agency/Owner (UAO): TAMPA ELECTRIC COMPANY

Special Conditions and Constraints

SPECIAL NOTATIONS

1. TEC (TAMPA ELECTRIC COMPANY) REQUIRES A MINIMUM OF 30 CALENDAR DAYS TO SCHEDULE ANY TEC WORK RELATED TO THIS PROJECT, INCLUDING BUT NOT LIMITED TO "DURING CONSTRUCTION" WORK IDENTIFIED IN THIS RELOCATION SCHEDULE, REQUESTS FOR THE INSTALLATION OF LINE COVER, REQUESTS FOR OVERHEAD/UNDERGROUND ELECTRIC OUTAGE(S), REQUESTS FOR TEC POLE HOLDING, AND/OR REQUESTS TO MONITOR ANY TEC FACILITIES WITH SAID REQUESTS BEING INITIATED BY HILLSBOROUGH COUNTY, THE HILLSBOROUGH COUNTY CONTRACTOR AND/OR THEIR SUBCONTRACTOR. THIS NOTICE INCLUDES POLE REMOVAL ONCE A JOINT USER HAS VACATED THE FACILITY AND PROPERLY NOTICIFIED TEC FIELD REPRESENTATIVE TO ALLOW SCHEDULING OF ACTIVITY TO OCCUR.

2. FOR SAFETY REASONS, TEC LINE CREWS SHALL NOT WORK IN ADVERSE WEATHER CONDITIONS.

3. THE TEC LINE CREW AVAILABILITY SHALL BE AFFECTED AND/OR LIMITED DUE TO OUR REQUIRED RESPONSE TO EMERGENCY CONDITIONS.

THIS LIMITATION WILL BE DEPENDENT UPON THE SEVERITY OF THE EMERGENCY.

4. TEC AND/OR TEC'S SUBCONTRACTORS NORMAL WORK SCHEDULE IS MONDAY THROUGH FRIDAY FROM 8 A.M. TO 5 P.M., EXCLUDING TEC OBSERVED HOLIDAY'S WHICH INCLUDE NEW YEARS DAY, GOOD FRIDAY, MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY, THE

FRIDAY AFTER THANKSGIVING, CHRISTMAS EVE DAY AND CHRISTMAS DAY.

5. TEC CAN NOT REMOVE ANY TEC POLES THAT HAVE EXISTING JOINT USERS STILL ATTACHED. SUBSEQUENTLY, ALL JOINT USERS SUCH AS FRONTIER, SPECTRUM, TRAFFIC, ETC. MUST BE REMOVED BEFORE TEC CAN REMOVE THE POLE ITSELF.

6. IF A NEW TEC ELECTRIC SERVICE MUST BE ESTABLISHED, PLEASE EMAIL ONE SOURCE AT CEREPS@TECOENERGY.COM OR 813-635-1500 AND REQUEST THE "PROCEDURE FOR ESTABLISHING A NEW ELECTRIC SERVICE". ALSO INCLUDED IN THIS SAME TEC DOCUMENT IS THE

PROCEDURE FOR THE REMOVAL OF AN EXISTING TEC ELECTRIC SERVICE.

7. THIS RELOCATION SCHEDULE WILL BE CONSIDERED VOID SHOULD HILLSBOROUGH COUNTY NOT BEGIN CONSTRUCTION WITHIN 12 MONTHS FROM SIGNATURE DATE OF TEC REPRESENTATIVE. IF SCHEDULE SHOULD BECOME VOID, TEC WILL THEN REQUIRE THE LATEST SET OF PLANS THAT REFLECT CURRENT FIELD CONDITIONS AT THAT TIME FOR REVIEW AND RE-WRITE OF SCHEDULE IF DEEMED NECESSARY BY

TEC.

8. IF A CSX FLAGGER IS REQUIRED, THE SCHEDULING OF SUCH SERVICES MAY NECESSITATE A LEAD TIME OF UP TO 6 MONTHS.

EMERGENCY NUMBER FOR NIGHTS, WEEKENDS & TECO HOLIDAYS - 877-588-1010

PROJECT MANAGEMENT: CSADMIN@TECOENERGY.COM

13KV DISTRIBUTION FACILITIES CONTACT: JERRY CLEMENTI 313-283-0381

Utility Agency/Owner (UAO): TAMPA ELECTRIC COMPANY

C. Disposition of Facilities (List All Existing & Proposed) on Project

TYPE / SIZE /

MATERIAL / OFFSET

TO BASELINE FROM

STA TO STA

DESCRIPTION

OF

UTILITY WORK

DEPENDENT

ACTIVITIES

M.O.T.

PHASE

NUMBER

CONSECUTIVE

CALENDAR

DAYS

Prior During

13.2 KV OE & 96 F

1077+47’ LT 65’ TO

1078+26’ LT 64’

INSTALL & SPLICE FIBER ONCE PROPOSED POLE(S) ARE

INSTALLED

PRIOR 1 0

POLE

1078+26’ LT 64’

INSTALL 50’ POLE & SET DEEPER ONCE EXECUTED UWS & NTP IS

RECEIVED

PRIOR 2 0

13.2 KV BE

1078+26’ LT 64’ TO

METER

INSTALL

INTERCEPT EXISTING 4”

CONDUIT

ONCE EXECUTED UWS & NTP IS

RECEIVED

PRIOR 5 0

13.2 KV OE & 96 F

1078+26’ LT 64’ TO

1079 +87’ LT 63’

INSTALL & SPLICE FIBER ONCE PROPOSED POLE(S) ARE

INSTALLED

PRIOR 1 0

13.2 KV OE & 96 F

1079 +92’ LT 62’ TO

1082+34’ LT 61’

INSTALL & SPLICE FIBER ONCE PROPOSED POLE(S) ARE

INSTALLED

PRIOR 1 0

13.2 KV OE & 96 F

1091+38’ LT 87’ TO

1093+06’ LT 92’

INSTALL & SPLICE FIBER ONCE PROPOSED POLE(S) ARE

INSTALLED

PRIOR 1 0

POLE

1093+06’ LT 92’

INSTALL 45’ POLE & SET

DEEPER

ONCE EXECUTED UWS & NTP IS

RECEIVED

PRIOR 2 0

13.2 KV OE & 96 F

1093+06’ LT 92’ TO

1093+47’ LT 93’

INSTALL & SPLICE FIBER ONCE PROPOSED POLE(S) ARE

INSTALLED

PRIOR 1 0

13.2 KV OE & 96 F

1093+06’ LT 92’ TO

1092+69’ LT 129’

INSTALL & SPLICE FIBER ONCE PROPOSED POLE(S) ARE

INSTALLED

PRIOR 1 0

POLE

1097 + 46, 106R

HOLD POLE SEE SPECIAL CONDITIONS 1 0 1

13.2KV BE

1102+70’ LT 108’ TO

1102+77’ RT 217’

INSTALL

(1) 4” CONDUIT

AT MINIMUM DEPTH OF 8’

ONCE EXECUTED UWS & NTP

IS RECEIVED

PRIOR 3 0

PULLBOX

1102+77’ RT 217’

INSTALL ONCE EXECUTED UWS & NTP

IS RECEIVED

PRIOR 2 0

120/240 BE

303+82’ RT 49’ TO

305+71’ RT 50’

INSTALL

(1) 2” CONDUIT

AT MINIMUM DEPTH OF 36”

ONCE ROW & MAST ARM HAS

BEEN STAKED BY

CONTRACTOR

PRIOR 5 0

120/240 BE

305+71’ RT 50’ TO

402+17’ LT 24’

INSTALL

(1) 2” CONDUIT

AT MINIMUM DEPTH OF 36”

ONCE ROW & MAST ARM HAS

BEEN STAKED BY

CONTRACTOR

PRIOR 5 0

13.2 KV OE & 96 F

1077+47’ LT 65’ TO

1078+24’ LT 64’

REMOVE ONCE NEW FACILITIES HAVE

BEEN INSTALLED AND

ENERGIZED

PRIOR 1 0

POLE

1078+24’ LT 64’

REMOVE ONCE NEW FACILITIES HAVE

BEEN INSTALLED AND

ENERGIZED

PRIOR 1 0

13.2 KV BE

1078+24’ LT 64’ TO

METER

REMOVE ONCE NEW FACILITES HAVE

BEEN INSTALLED AND

ENERGIZED

PRIOR 3 0

13.2 KV OE & 96 F

1078+24’ LT 64’ TO

1079+92’ LT 62’

REMOVE ONCE NEW FACILITES HAVE

BEEN INSTALLED AND

ENERGIZED

PRIOR 1 0

POLE

1079+92’ LT 62’

REMOVE CABLE AND PLACE

CONDUIT OUT OF SERVICE

ONCE NEW FACILITES HAVE

BEEN INSTALLED AND

ENERGIZED

PRIOR 1 0

Utility Agency/Owner (UAO): TAMPA ELECTRIC COMPANY

13.2 KV OE & 96 F

1091+38’ LT 87’ TO

1092 +74’ LT 91’

REMOVE ONCE NEW FACILITES HAVE

BEEN INSTALLED AND

ENERGIZED

PRIOR 1 0

POLE

1092 +74’ LT 91’

REMOVE ONCE NEW FACILITES HAVE

BEEN INSTALLED AND

ENERGIZED

PRIOR 1 0

13.2 KV OE & 96 F

1092 +74’ LT 91’ TO

1092+69’ LT 129’

REMOVE ONCE NEW FACILITES HAVE

BEEN INSTALLED AND

ENERGIZED

PRIOR 1 0

13.2 KV OE & 96 F

1092 +74’ LT 91’ TO

1093 +47’ LT 93’

REMOVE ONCE NEW FACILITES HAVE

BEEN INSTALLED AND

ENERGIZED

PRIOR 1 0

13.2KV BE

1102+70’ LT 108’ TO

1102+77’ RT 217’

REMOVE CABLE AND PLACE

CONDUIT OUT OF SERVICE

ONCE NEW FACILITES HAVE

BEEN INSTALLED AND

ENERGIZED

PRIOR 1 0

PULLBOX

1102+77’ RT 217’

REMOVE ONCE NEW FACILITES HAVE

BEEN INSTALLED AND

ENERGIZED

PRIOR 2 0

120/240 BE

303+82’ RT 49’ TO

305+71’ RT 50’

REMOVE CABLE AND PLACE

CONDUIT OUT OF SERVICE

ONCE NEW FACILITES HAVE

BEEN INSTALLED AND

ENERGIZED

PRIOR 3 0

120/240 BE

305+71’ RT 50’ TO

402+17’ LT 24’

REMOVE CABLE AND PLACE

CONDUIT OUT OF SERVICE

ONCE NEW FACILITES HAVE

BEEN INSTALLED AND

ENERGIZED

PRIOR 3 0

2026-07-13T15:29:48-0400
Tamishe J Rodriguez
2026-07-14T06:36:44-0400
Lisa Strout
2026-07-14T08:09:25-0400
Manuel E. Santos

File details come from the government source that posted it. Updated .