About this file

This is a Utility Relocation Schedule document submitted by Peoples Gas System (a division of TECO) to Hillsborough County, Florida, regarding utility facility relocations for the Big Bend Road improvement project (CIP Number 69647.000). The project involves resurfacing and widening approximately 0.75 miles of Big Bend Road from US 41 to Covington Garden Drive, with an estimated project cost of $21,624,946.34. The utility relocation schedule outlines the work required to relocate existing gas infrastructure to accommodate the roadway construction. The schedule was signed and approved on July 10, 2026, and includes preliminary engineering (120 calendar days), material procurement (120 calendar days), and permitting (30 calendar days). All utility work is scheduled to occur prior to county project construction, with no work scheduled during construction operations.

The document details multiple gas main relocations consisting of 6-inch and 2-inch coated steel pipes at various station locations along the project corridor, requiring installation of new gas mains, removal of retired mains, and installation of three new gas valves. Dependent activities include permit approval, staking of storm structures and right-of-way, and testing and energizing of new infrastructure. The schedule is valid for one year from the execution date. Special conditions note that Peoples Gas maintains a 24-hour emergency number (1-877-832-6747), operates on a standard Monday through Friday 8 a.m. to 5 p.m. schedule with observed holidays, and requires 72-hour advance notice for work outside normal hours. An 18-inch separation clearance must be maintained with all existing gas mains, and the utility may grout-fill and retire gas mains under paved surfaces as an alternative to removal. Project representatives include Patrick Allen (Gas Design Project Manager) and Javier Vazquez (Field Representative).

View the file

Other files

File Type Posted
Attachment E- 69692000 BigBendWest Drainage Design Documentation Vol. II Final.pdf PDF
21-Attachment B- Geo Report - 69692000 100P Misc Structures 2025-11-20.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 Spectrum Revised URS 7.13.2026 TR LS.pdf PDF
Attachment B- Geo Report - 69692000 100P Misc Structures 2025-11-20.pdf PDF
Attachment H- Plans- Lighting.pdf PDF
41-Attachment L- CSX Coordination.pdf PDF
Attachment G- FDOT Grant Agreement.pdf PDF
Attachment I- Utility Relocation Schedule CIP 69647.000 Utility Cert Letter 7.15.26.pdf PDF
27-Attachment I- Utility Relocation Schedule 69647.000 100% REVISED - TEC UWS - REV4 7.13.26 TR LS.pdf PDF
13-AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
2-Florida Trench Safety Act, Certification and Disclosure Statement.pdf.pdf PDF
43-Attachment M- Work Class Percentage.pdf PDF
34-Attachment I- Utility Relocation Schedule 69647.000 Spectrum Revised URS 7.13.2026 TR LS.pdf PDF
46-Attachment G- FDOT Grant Agreement.pdf PDF
Attachment B- Geo Report - 69692000 PhIV Rdwy Soil Survey Report 2025-11-20.pdf PDF
40-Attachment K- Insurance Requirements.pdf PDF
52-Attachment H- Plans- ITS.pdf PDF
48-Attachment H- Location Map.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 100% REVISED - TEC UWS - REV4 7.13.26 TR LS.pdf PDF
Attachment H- Location Map.pdf PDF
11-Direct Deposit Authorization Form 5.15.2025.pdf.pdf PDF
AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
3-Allowance Authorization Release Form.pdf.pdf PDF
29-Attachment I- Utility Relocation Schedule CIP 69647.000 100% URS PGS7-10-2026 REV 1SignedTR.pdf PDF
Attachment D- Permits - SWFWMD ERP 43024488.004 Approved.pdf PDF
17-Attachment F- 69692000 6050BigBend ROE ChildcareBrandon 10-9-25 Signed.pdf PDF
Agreement - Construction - Stand Alone.docx.pdf PDF
54-Attachment K- CSX Insurance Receipt.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 BIG BEND US 41 TO COVINGTON FTR URS 071426 TR LS.pdf PDF
39-Attachment J- CSX1036508- Agreement.pdf PDF
Attachment B- Geo Report - 69692000 Kings Lake Dr Misc Struc 100% Geo Report SS.pdf PDF
8-Change Order Form.pdf.pdf PDF
42-Agreement - Construction - Stand Alone.docx.pdf PDF
Attachment E- 69692000 BigBendWest Drainage Design Documentation Vol. I Final SS (1).pdf PDF
14-Attachment D- Permits - SWFWMD ERP 43024488.004 Approved.pdf PDF
23-Attachment E- 69692000 Waterset-Kings Lake Drainage Memo.pdf PDF
Attachment F- 669692000 6089BigBend ROE HomeDepot 10-9-25 signed.pdf PDF
20-Attachment B- Geo Report - 69692000 PhIV Rdwy Soil Survey Report 2025-11-20.pdf PDF
Attachment B- Geo Report - 69692000 Waterset Trail 100% RSS SS.pdf PDF
47-Attachment H- Clear Letters 2.pdf PDF
18-Attachment F- 669692000 BayIndustrial ROE 10-9-25. signed.pdf PDF
30-Attachment I- Utility Relocation Schedule CIP 69647.000 URS Uniti Fiber REV 3 7.10.26 TR LS.pdf PDF
Attachment F- 669692000 BayIndustrial ROE 10-9-25. signed.pdf PDF
36-Bid Bond.doc.doc DOC document
9-Insurance Certificate.doc.doc DOC document
31-Attachment I- Utility Relocation Schedule MCI 69647.000 100% URS WSP-8-26 LS.pdf PDF
Attachment A- Construction Sign 2026.pdf PDF
32-Attachment I- Utility Relocation SchedCIP 69647 000 US 41 to Covington Garden Drive Zayo UWS 71326 TR LS.pdf PDF
1-Drug Free Workplace Form.doc.doc DOC document
Attachment E- 69692000 Waterset-Kings Lake Drainage Memo.pdf PDF
Show 40 more

Latest 50 of 89 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Hillsborough County County Road: 672 (Big Bend Rd) Plans Dated: 6/12/2026

CIP Number: 69647.000 Project Name: Big Bend Road from US 41 to Covington Garden Drive

Utility Agency/Owner (UAO): Peoples Gas System

NON-CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

Total Preliminary (Engineering) 0 Prior to County Project Construction 120

Total Material Procurement 120 During County Project Construction 0

Total Right-of-Way Acquisition 0 As-Built Information _____________

Total Other (Permitting) 30 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Hillsborough County, the roadway contractor, and other right-of-way users, the location, relocation, adjustment, installation, and/or protection of facilities, on this Hillsborough County project. The following data is based on the plans dated as listed in the Title Block.

Any deviation by Hillsborough County or its Contractor from plans, as provided may render this work schedule null and void.

Upon notification by, Hillsborough County of such change, this utility may require additional days for assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond the control of the UAO that could not reasonably be anticipated by the UAO and which could not be avoided by the UAO with the exercise of due diligence at the time of the occurrence. The UAO agrees to notify Hillsborough County in writing prior to starting, stopping, resuming, or completing work. The UAO is to provide As-Built information.

The UAO shall obtain a utility permit and comply with the requirements of the Hillsborough County UAM.

During the project, the UAO shall locate their facilities within 48 hours of notice to their Representative: Sunshine 811 Telephone Number: 811 -

UAO Project Representative: Patrick Allen Telephone Number: 813-460-0454

UAO Field Representative: Javier Vazquez Telephone Number: 813-275-3726

This document is a printout of a Hillsborough County form maintained in an electronic format and all revisions thereto by the UAO in the form of additions, deletions or substitutions are reflected only in an Appendix entitled “Changes to Form Document” and no change is made in the text of the document itself. Hand notations on affected portions of this document may refer to changes reflected in the above-named Appendix but are for reference purposes only and do not change the terms of the document. By signing this document, the UAO hereby represents that no change has been made to the text of this document except through the terms of the Appendix entitled “Changes to Form Document”.

You MUST signify by selecting or checking which of the following applies:

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: **Engineer of Record (EOR): Acceptance by Hillsborough

County:

(Signature) (Signature) (Signature)

Patrick Allen

Tamishe J. Rodriguez, P.E.

Manuel E. Santos, E.I.

(Printed Name) (Printed Name) (Printed Name)

Gas Design Project Manager

Engineer of Record

County Project Manager

(Title) (Title) (Title)

7/10/2026

(Date) (Date) (Date)

Final Approval by Hillsborough County:

(Signature) (Date)

Lisa Strout Capital Utility Manager (Printed Name) (Title)

(**When requested by the County, the EOR will attest to compatibility of plans, specifications and Utility Work Schedule)

Rodriguez, Tamishe (ChinTa) Text Box 7/10/2026

Special Conditions and Constraints

1. THE TECO PEOPLES GAS 24-HOUR EMERGENCY NUMBER 1-877-TECO-PGS (1-877-832-6747)

2. TECO PEOPLES GAS CREW AVAILABILITY MAY BE AFFECTED OR LIMITED DUE TO OUR REQUIRED

RESPONSE TO EMERGENCY CONDITIONS ELSEWHERE. THIS LIMITATION WILL BE DEPENDENT UPON THE

SEVERITY AND LOCATION OF THE EMERGENCY.

3. TECO PEOPLES GAS EMPLOYEES AND SUBCONTRACTORS NORMAL WORK SCHEDULE IS MONDAY

THROUGH FRIDAY FROM 8 A.M. TO 5 P.M., EXCLUDING TECO PEOPLES GAS OBSERVED HOLIDAYS (NEW YEARS

DAY, GOOD FRIDAY, MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY, THE FRIDAY AFTER

THANKSGIVING DAY, CHRISTMAS EVE DAY, AND CHRISTMAS DAY). ANY TECO PEOPLES GAS ASSISTANCE

REQUESTED FORM THE COUNTY, THEIR CONTRACTOR OF SUBCONTRACTOR OUTSIDE OF THESE NORMAL

WORKING HOURS MUST BE SCHEDULED 72 HOURS IN ADVANCE. TECO PEOPLES GAS REQUIRES VERIFICATION

THAT THE CREWS ARE STILL NEEDED ON THE ACTUAL WORKDAY (MONDAY THROUGH FRIDAY) THAT HAD

PREVIOUSLY BEEN REQUESTED OR THE LAST BUSINESS DAY BEFORE THE REQUESTED WEEKEND OR

HOLIDAY.

4. TECO PEOPLES GAS MAY GROUT FILL AND RETIRE GAS MAINS THAT ARE UNDER PAVED ROADWAYS

AND

DRIVEWAYS AS AN ALTERNATIVE TO REMOVING THEM.

5. AN 18” SEPARATION CLEARANCE MUST BE MAINTAINED WITH ALL EXISTING TECO PEOPLES GAS

MAINS/FACILITIES.

6. THIS RELOCATION SCHEDULE IS VALID FOR 1 YEAR FROM THE DATE SIGNED BY THE AUTHORIZED

UTILITY AGENT.

C. Disposition of Facilities (List All Existing & Proposed) on Project

TYPE / SIZE /

MATERIAL / OFFSET

TO BASELINE FROM

STA TO STA

DESCRIPTION

OF

UTILITY WORK

DEPENDENT

ACTIVITIES

M.O.T.

PHASE

NUMBER

CONSECUTIVE

CALENDAR

DAYS

Prior During

GAS MAIN / 6” /

COATED STEEL /

STA. 1082+35, 56’ RT

TO

STA. 1090+00, 117’ RT

INSTALL NEW 6” COATED STEEL

GAS MAIN 2’ N OF ROW AT >10’

DEPTH BELOW EXISTING

GRADE

APPROVED PERMIT, STAKING

OF STORM STRUCTURES AND

ROW,

N/A 25 0

GAS MAIN / 6” /

COATED STEEL /

STA. 1082+40, 56’ RT

TO

STA. 1089+95, 56’ RT

REMOVE RETIRED 6” COATED

STEEL GAS MAIN

INSTALLATION, TESTING, AND

ENRGIZING OF NEW 6” COATED

STEEL GAS MAIN,

N/A 5 0

GAS MAIN / 6” /

COATED STEEL /

STA. 1095+40, 56’ RT

TO

STA. 1095+60, 56’ RT

INSTALL NEW 6” COATED STEEL

GAS MAIN AT >10’ DEPTH

BELOW EXISTING GRADE

APPROVED PERMIT, STAKING

OF S-37,

N/A 20 0

GAS MAIN / 6” /

COATED STEEL /

STA. 1095+45, 56’ RT

TO

STA. 1095+55, 56’ RT

REMOVE RETIRED 6” COATED

STEEL GAS MAIN

INSTALLATION, TESTING, AND

ENRGIZING OF NEW 6” COATED

STEEL GAS MAIN,

N/A 1 0

GAS MAIN / 6” /

COATED STEEL /

STA. 1100+80, 56’ RT

TO

STA. 1118+40, 52 RT

INSTALL NEW 6” COATED STEEL

GAS MAIN

APPROVED PERMIT, STAKING

OF STORM STRUCTURES AND

ROW,

N/A 30 0

GAS MAIN / 6” /

COATED STEEL /

STA. 1100+85, 56’ RT

TO

STA. 1118+35, 54’ RT

REMOVE RETIRED 6” COATED

STEEL GAS MAIN

INSTALLATION, TESTING, AND

ENRGIZING OF NEW 6” COATED

STEEL GAS MAIN,

N/A 15 0

GAS MAIN / 2” /

COATED STEEL /

STA. 1115+30, 86’ RT

TO

STA. 1115+60, 126’ RT

INSTALL NEW 2” COATED STEEL

GAS MAIN

APPROVED PERMIT, STAKING

OF STORM STRUCTURES AND

ROW,

N/A 20 0

GAS MAIN / 2” /

COATED STEEL /

STA. 1115+30, 57’ RT

TO

STA. 1115+60, 118’ RT

REMOVE RETIRED 2” COATED

STEEL GAS MAIN AND EXISTING

VALVE

INSTALLATION, TESTING, AND

ENRGIZING OF NEW 2” COATED

STEEL GAS MAIN,

N/A 1 0

GAS MAIN / 6” /

COATED STEEL /

STA. 1082+35, 60’ RT

INSTALL NEW GAS VALVE APPROVED PERMIT, STAKING

OF STORM STRUCTURES AND

ROW,

N/A 1 0

GAS MAIN / 6” /

STA. 1100+80, 60’ RT

ROW,

N/A 1 0

GAS MAIN / 2” /

STA. 1115+60, 100’ RT

ROW,

N/A 1 0

2026-07-10T08:52:32-0400
Patrick Allen
I have reviewed this document
2026-07-10T11:28:46-0400
Tamishe J Rodriguez
2026-07-10T13:59:17-0400
Manuel E. Santos
2026-07-10T15:11:56-0400
Lisa Strout