This is a Utility Relocation Schedule prepared by Uniti Fiber LLC, a utility agency/owner, for Hillsborough County, Florida in connection with the Big Bend Road Improvement Project (CIP 69647.000). The project involves resurfacing and widening approximately 0.75 miles of Big Bend Road from US 41 to Covington Garden Drive, with an estimated project cost of $21,624,946.34. The utility relocation work is based on plans dated June 12, 2026, with a revised 100% project phase designation. Uniti Fiber has submitted a detailed work schedule identifying eleven separate utility disposition activities, including conduit installation, hand hole adjustments and removals, splicing operations, and protection measures for existing fiber optic and other utility infrastructure. The utility requires a 72-hour advance notice prior to commencing work and has designated Zach Oliver as its primary point of contact for facility location and project coordination within 48 hours of notice.

The utility relocation schedule specifies estimated calendar days for completion of various non-construction and construction-related tasks, with engineering design estimated at 10 calendar days prior to county project construction, permitting at 14 days, and material procurement at 30 days. Construction-phase work is estimated at 49 calendar days prior to and 8 days during county project construction. The document was authorized by Zach Oliver (Asset Protection Supervisor) on July 10, 2026, and approved by Engineer of Record Tamishe Rodriguez, P.E. and County Project Manager Manuel E. Santos, E.I. on July 13, 2026. Final approval by Hillsborough County's Capital Utility Coordinator, Lisa Strout, was also dated July 13, 2026. Uniti Fiber's project contacts include construction managers, asset protection personnel, and operations specialists across multiple regional locations, ensuring comprehensive coordination throughout the utility relocation process.

View the file

Other files

File Type Posted
Attachment E- 69692000 BigBendWest Drainage Design Documentation Vol. II Final.pdf PDF
21-Attachment B- Geo Report - 69692000 100P Misc Structures 2025-11-20.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 Spectrum Revised URS 7.13.2026 TR LS.pdf PDF
Attachment B- Geo Report - 69692000 100P Misc Structures 2025-11-20.pdf PDF
Attachment H- Plans- Lighting.pdf PDF
41-Attachment L- CSX Coordination.pdf PDF
Attachment G- FDOT Grant Agreement.pdf PDF
Attachment I- Utility Relocation Schedule CIP 69647.000 Utility Cert Letter 7.15.26.pdf PDF
27-Attachment I- Utility Relocation Schedule 69647.000 100% REVISED - TEC UWS - REV4 7.13.26 TR LS.pdf PDF
13-AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
2-Florida Trench Safety Act, Certification and Disclosure Statement.pdf.pdf PDF
43-Attachment M- Work Class Percentage.pdf PDF
34-Attachment I- Utility Relocation Schedule 69647.000 Spectrum Revised URS 7.13.2026 TR LS.pdf PDF
46-Attachment G- FDOT Grant Agreement.pdf PDF
Attachment B- Geo Report - 69692000 PhIV Rdwy Soil Survey Report 2025-11-20.pdf PDF
40-Attachment K- Insurance Requirements.pdf PDF
52-Attachment H- Plans- ITS.pdf PDF
48-Attachment H- Location Map.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 100% REVISED - TEC UWS - REV4 7.13.26 TR LS.pdf PDF
Attachment H- Location Map.pdf PDF
11-Direct Deposit Authorization Form 5.15.2025.pdf.pdf PDF
AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
3-Allowance Authorization Release Form.pdf.pdf PDF
29-Attachment I- Utility Relocation Schedule CIP 69647.000 100% URS PGS7-10-2026 REV 1SignedTR.pdf PDF
Attachment D- Permits - SWFWMD ERP 43024488.004 Approved.pdf PDF
17-Attachment F- 69692000 6050BigBend ROE ChildcareBrandon 10-9-25 Signed.pdf PDF
Agreement - Construction - Stand Alone.docx.pdf PDF
54-Attachment K- CSX Insurance Receipt.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 BIG BEND US 41 TO COVINGTON FTR URS 071426 TR LS.pdf PDF
39-Attachment J- CSX1036508- Agreement.pdf PDF
Attachment B- Geo Report - 69692000 Kings Lake Dr Misc Struc 100% Geo Report SS.pdf PDF
8-Change Order Form.pdf.pdf PDF
42-Agreement - Construction - Stand Alone.docx.pdf PDF
Attachment E- 69692000 BigBendWest Drainage Design Documentation Vol. I Final SS (1).pdf PDF
14-Attachment D- Permits - SWFWMD ERP 43024488.004 Approved.pdf PDF
23-Attachment E- 69692000 Waterset-Kings Lake Drainage Memo.pdf PDF
Attachment F- 669692000 6089BigBend ROE HomeDepot 10-9-25 signed.pdf PDF
20-Attachment B- Geo Report - 69692000 PhIV Rdwy Soil Survey Report 2025-11-20.pdf PDF
Attachment B- Geo Report - 69692000 Waterset Trail 100% RSS SS.pdf PDF
47-Attachment H- Clear Letters 2.pdf PDF
18-Attachment F- 669692000 BayIndustrial ROE 10-9-25. signed.pdf PDF
Attachment F- 669692000 BayIndustrial ROE 10-9-25. signed.pdf PDF
Attachment I- Utility Relocation Schedule CIP 69647.000 100% URS PGS7-10-2026 REV 1SignedTR.pdf PDF
36-Bid Bond.doc.doc DOC document
9-Insurance Certificate.doc.doc DOC document
31-Attachment I- Utility Relocation Schedule MCI 69647.000 100% URS WSP-8-26 LS.pdf PDF
Attachment A- Construction Sign 2026.pdf PDF
32-Attachment I- Utility Relocation SchedCIP 69647 000 US 41 to Covington Garden Drive Zayo UWS 71326 TR LS.pdf PDF
1-Drug Free Workplace Form.doc.doc DOC document
Attachment E- 69692000 Waterset-Kings Lake Drainage Memo.pdf PDF
Show 40 more

Latest 50 of 89 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Updated 01/2026

Hillsborough County County Road: 672 6/12/2026 Plans Dated: 6/12/2026 Project Phase: Revised 100% CIP Number: 69647.000 Project Name: Big Bend Road from US 41 to Covington Garden Drive Utility Agency/Owner (UAO): Uniti Fiber LLC

Sensitivity: Internal

NON-CONSTRUCTION ITEMS ESTIMATED

*CALENDAR DAYS

CONSTRUCTION ITEMS ESTIMATED

*CALENDAR DAYS

Engineering Design 10 Prior to County Project Construction 49 Permitting 14 During County Project Construction 8 Material Procurement 30 As-Built Information 10 Other 0 * Calendar Days = UAO Workdays x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Hillsborough County, the roadway contractor, and other right-of-way users, the location, relocation, adjustment, installation, and/or protection of facilities, on this Hillsborough County project. The following data is based on the plans dated as listed in the Title Block.

Any deviation by Hillsborough County or its Contractor from plans, as provided may render this work schedule null and void.

Upon notification by Hillsborough County of such change, this utility may require additional days for assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond the control of the UAO that could not reasonably be anticipated by the UAO and which could not be avoided by the UAO with the exercise of due diligence at the time of the occurrence. The UAO agrees to notify Hillsborough County in writing prior to starting, stopping, resuming, or completing work. The UAO is to provide As-Built information.

The UAO shall obtain a utility permit and comply with the requirements of the Hillsborough County UAM.

During the project, the UAO shall locate their facilities within 48 hours of notice to their Representative: Zach Oliver Telephone Number: 727-337-1381

UAO Project Representative: Zach Oliver Telephone Number: 727-337-1381 UAO Field Representative: Zach Oliver Telephone Number: 727-337-1381 This document is a printout of a Hillsborough County form maintained in an electronic format and all revisions thereto by the UAO in the form of additions, deletions or substitutions are reflected only in an Appendix entitled “Changes to Form Document” and no change is made in the text of the document itself. Hand notations on affected portions of this document may refer to changes reflected in the above-named Appendix but are for reference purposes only and do not change the terms of the document. By signing this document, the UAO hereby represents that no change has been made to the text of this document except through the terms of the Appendix entitled “Changes to Form Document”.

You MUST signify by selecting or checking which of the following applies:

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: **Engineer of Record (EOR): Acceptance by Hillsborough County PM:

(Signature) (Signature) (Signature)

Zach Oliver Tamishe Rodriguez, P.E. Manuel E. Santos, E.I.

(Printed Name) (Printed Name) (Printed Name)

Asset Protection Supervisor Engineer of Record County Project Manager (Title) (Title) (Title)

7/10/2026 (Date) (Date) (Date)

Final Approval by Hillsborough County Utility Coordination: (Signature) (Date)

Lisa Strout Capital Utility Coordinator (Printed Name) (Title)

(**When requested by the County, the EOR will attest to compatibility of plans, specifications and Utility Work Schedule)

Rodriguez, Tamishe (ChinTa) Text Box 7/13/2026

Plans Dated: 6/12/2026 Project Phase: Revised 100% CIP Number: 69647.000 Project Name: Big Bend Road from US 41 to Covington Garden Drive Utility Agency/Owner (UAO): Uniti Fiber LLC

Sensitivity: Internal

Special Conditions and Constraints UNITI FIBER LLC REQUEST A 72Hour NOTICE before work being performed for ACT:

Uniti Fiber Contacts South FL:

Construction Manager: Terry Young 251-422-3872 terry.young@uniti.com Orlando Construction Manager: James Mosley 251-654-8216 James.Mosley@uniti.com Asset Protection Manager: Zach Oliver 727-337-1381 zach.oliver@uniti.com OSP Engineer: John Middleton 727-281-0198 john.middleton@uniti.com OSP Engineer: Tim Pryor 727-293-0697 tim.pryor@uniti.com Field Operations Manager: Michael Hall 251-401-3879 michael.hall@uniti.com Asset Protection Specialist: Juan Hernandez 305-801-1983 Juan.Hernandez@uniti.com

Plans Dated: 6/12/2026 Project Phase: Revised 100% CIP Number: 69647.000 Project Name: Big Bend Road from US 41 to Covington Garden Drive Utility Agency/Owner (UAO): Uniti Fiber LLC

Sensitivity: Internal

Section C. Disposition of Facilities (List All Existing & Proposed) on Project

Act No. Type / Size /

Material

From Station/Offset

To Station/Offset

Description of Utility Work

Dependent Activities

M.O.T.

Phase

No.

Consecutive Calendar Days Prior During

1. Splicing N/A 20 0

2. Uniti Fiber 1-1.88”

FP Conduit

BFOC

STA:1077-45 LT

67.95’

Min. 15’ Depth

1089-20 LT

68.48’

Min. 15’ Depth

Joint Bore ROW and

STRUCTURE

STAKING

N/A 15 0

3. Remove Uniti Fiber

1-1.88” FP Conduit

BFOC

STA:1077-45

LT

1089-20 LT Remove Conduit NEW FOC SPLICIG

COMPELTE

N/A 10 0

4. Uniti Fiber Hand Hole

STA:1076+60

LT

63.23’

STA:1077+45

LT

63.23’

Add Hand Hole 24X36X34

Connect existing FOC to West side of new HH

For Joint Bore N/A 2 0

5. Uniti Fiber 1-1.88”

FP Conduit

BFOC

STA: 1077+00

LT

STA: 1077+00

LT

Hold and Protect S-1 and S-2 PH I 0 2

6. Uniti Fiber Hand Hole

1089+21 LT

67.95’

1089+22 LT

82.21’

Adjust Hand Hole Sidewalk Construction

PH I 0 2

7. ATT Conduit 1089+42 1089+42 Hold and Protect Water install PH I 0 2

8. T-Mobile Conduit

1089+42 1089+42 Hold and Protect Water Install PH I 0 2

9. Uniti Fiber Hand Hole

STA:1077+45

LT 59’

STA:1077+45

LT 59’

Remove Hand Hole NEW FOC SPLICIG

COMPELTE

N/A 1 0

10. Uniti Fiber Hand Hole

1084+18 LT 1084+18 LT Remove Hand Hole NEW FOC SPLICIG

COMPELTE

N/A 1 0

11.

12.

13.

14.

15.

2026-07-13T13:06:59-0400
Tamishe J Rodriguez
2026-07-13T14:53:37-0400
Lisa Strout
2026-07-13T14:57:11-0400
Manuel E. Santos