Attachment I- Utility Relocation Schedule 69647.000 BIG BEND US 41 TO COVINGTON FTR URS 071426 TR LS.pdf

PDF 402 KB Posted

Attached to
Big Bend Road from US 41 to Covington Garden Dr.
Solicitation number
IFB-26-00378
Issued by
Hillsborough County, Florida

About this file

This is a Utility Relocation Schedule prepared by Hillsborough County for the Big Bend Road project (US 41 to Covington Garden Drive) involving Frontier Communications as the Utility Agency/Owner. The project is located on County Road 672 and is associated with CIP Number 69647.000, with plans dated June 12, 2026. The schedule details the relocation, adjustment, installation, and protection of Frontier Communications facilities along the 0.75-mile corridor. Non-construction items require 30 calendar days for engineering design, 15 days for permitting, and 30 days for material procurement. Construction-related utility work requires 184 calendar days prior to county project construction and 32 calendar days during county project construction. The scope includes removal of buried copper cables, four-inch and two-inch conduits with fiber optic cables, handholes, and pedestals, as well as installation of new two-inch and four-inch conduits, 51 new and existing handholes and manholes, and fiber splicing. Frontier's project representative is Randy James (813-892-9692) and field representative is Paul Lineberry (813-838-8867). The schedule was finalized July 15, 2026, with final approval by Hillsborough County Utility Coordination Manager Lisa Strout.

Frontier Communications' normal business hours are 8 a.m. to 5 p.m., Monday through Friday, with work outside these hours requiring a minimum 48-hour advance notice. The utility requires 60 days for engineering, budget approval, material procurement, and permitting before construction and requests a 24-hour notice for on-site meetings with the contractor. The document specifies that Frontier shall be notified when work occurs within two feet of its facilities and requires hand digging with shovel or small excavator for adjustments. The contractor must stake drainage locations prior to relocation work and obtain utility permits in compliance with Hillsborough County Utility Access Management regulations. This schedule is based on plans dated June 12, 2026, and any deviation by Hillsborough County or its contractor may render the work schedule null and void, requiring reassessment and negotiation of a revised schedule.

View the file

Other files

File Type Posted
Attachment E- 69692000 BigBendWest Drainage Design Documentation Vol. II Final.pdf PDF
21-Attachment B- Geo Report - 69692000 100P Misc Structures 2025-11-20.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 Spectrum Revised URS 7.13.2026 TR LS.pdf PDF
Attachment B- Geo Report - 69692000 100P Misc Structures 2025-11-20.pdf PDF
Attachment H- Plans- Lighting.pdf PDF
41-Attachment L- CSX Coordination.pdf PDF
Attachment G- FDOT Grant Agreement.pdf PDF
Attachment I- Utility Relocation Schedule CIP 69647.000 Utility Cert Letter 7.15.26.pdf PDF
27-Attachment I- Utility Relocation Schedule 69647.000 100% REVISED - TEC UWS - REV4 7.13.26 TR LS.pdf PDF
13-AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
2-Florida Trench Safety Act, Certification and Disclosure Statement.pdf.pdf PDF
43-Attachment M- Work Class Percentage.pdf PDF
34-Attachment I- Utility Relocation Schedule 69647.000 Spectrum Revised URS 7.13.2026 TR LS.pdf PDF
46-Attachment G- FDOT Grant Agreement.pdf PDF
Attachment B- Geo Report - 69692000 PhIV Rdwy Soil Survey Report 2025-11-20.pdf PDF
40-Attachment K- Insurance Requirements.pdf PDF
52-Attachment H- Plans- ITS.pdf PDF
48-Attachment H- Location Map.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 100% REVISED - TEC UWS - REV4 7.13.26 TR LS.pdf PDF
Attachment H- Location Map.pdf PDF
11-Direct Deposit Authorization Form 5.15.2025.pdf.pdf PDF
AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
3-Allowance Authorization Release Form.pdf.pdf PDF
29-Attachment I- Utility Relocation Schedule CIP 69647.000 100% URS PGS7-10-2026 REV 1SignedTR.pdf PDF
Attachment D- Permits - SWFWMD ERP 43024488.004 Approved.pdf PDF
17-Attachment F- 69692000 6050BigBend ROE ChildcareBrandon 10-9-25 Signed.pdf PDF
Agreement - Construction - Stand Alone.docx.pdf PDF
54-Attachment K- CSX Insurance Receipt.pdf PDF
39-Attachment J- CSX1036508- Agreement.pdf PDF
Attachment B- Geo Report - 69692000 Kings Lake Dr Misc Struc 100% Geo Report SS.pdf PDF
8-Change Order Form.pdf.pdf PDF
42-Agreement - Construction - Stand Alone.docx.pdf PDF
Attachment E- 69692000 BigBendWest Drainage Design Documentation Vol. I Final SS (1).pdf PDF
14-Attachment D- Permits - SWFWMD ERP 43024488.004 Approved.pdf PDF
23-Attachment E- 69692000 Waterset-Kings Lake Drainage Memo.pdf PDF
Attachment F- 669692000 6089BigBend ROE HomeDepot 10-9-25 signed.pdf PDF
20-Attachment B- Geo Report - 69692000 PhIV Rdwy Soil Survey Report 2025-11-20.pdf PDF
Attachment B- Geo Report - 69692000 Waterset Trail 100% RSS SS.pdf PDF
47-Attachment H- Clear Letters 2.pdf PDF
18-Attachment F- 669692000 BayIndustrial ROE 10-9-25. signed.pdf PDF
30-Attachment I- Utility Relocation Schedule CIP 69647.000 URS Uniti Fiber REV 3 7.10.26 TR LS.pdf PDF
Attachment F- 669692000 BayIndustrial ROE 10-9-25. signed.pdf PDF
Attachment I- Utility Relocation Schedule CIP 69647.000 100% URS PGS7-10-2026 REV 1SignedTR.pdf PDF
36-Bid Bond.doc.doc DOC document
9-Insurance Certificate.doc.doc DOC document
31-Attachment I- Utility Relocation Schedule MCI 69647.000 100% URS WSP-8-26 LS.pdf PDF
Attachment A- Construction Sign 2026.pdf PDF
32-Attachment I- Utility Relocation SchedCIP 69647 000 US 41 to Covington Garden Drive Zayo UWS 71326 TR LS.pdf PDF
1-Drug Free Workplace Form.doc.doc DOC document
Attachment E- 69692000 Waterset-Kings Lake Drainage Memo.pdf PDF
Show 40 more

Latest 50 of 89 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Updated 3/2026

Hillsborough County County Road: 672 Plans Date: 06/12/2026

CIP Number: 69647.000 Project Name: US 41 TO COVINGTON GARDEN DR Project Phase: 100%

Utility Agency/Owner (UAO): FRONTIER COMMUNICATIONS

NON-CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

Engineering Design 30 Prior to County Project Construction 184

Permitting 15 During County Project Construction 32

Material Procurement 30 Splicing

Other As-Built Information

* Calendar Days = UAO Workdays x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Hillsborough County, the roadway contractor, and other right-of-way users, the location, relocation, adjustment, installation, and/or protection of facilities, on this Hillsborough County project. The following data is based on the plans dated as listed in the Title Block.

Any deviation by Hillsborough County or its Contractor from plans, as provided may render this work schedule null and void.

Upon notification by, Hillsborough County of such change, this utility may require additional days for assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond the control of the UAO that could not reasonably be anticipated by the UAO and which could not be avoided by the UAO with the exercise of due diligence at the time of the occurrence. The UAO agrees to notify Hillsborough County in writing prior to starting, stopping, resuming, or completing work. The UAO is to provide As-Built information.

The UAO shall obtain a utility permit and comply with the requirements of the Hillsborough County UAM.

During the project, the UAO shall locate their facilities withing 48 hours of notice to their Representative.

UAO Project Representative: RANDY JAMES Telephone Number: 813-892-9692

UAO Field Representative: PAUL LINEBERRY Telephone Number: 813-838-8867

This document is a printout of a Hillsborough County form maintained in an electronic format and all revisions thereto by the UAO in the form of additions, deletions or substitutions are reflected only in an Appendix entitled “Changes to Form Document” and no change is made in the text of the document itself. Hand notations on affected portions of this document may refer to changes reflected in the above-named Appendix but are for reference purposes only and do not change the terms of the document. By signing this document, the UAO hereby represents that no change has been made to the text of this document except through the terms of the Appendix entitled “Changes to Form Document”.

You MUST signify by selecting or checking which of the following applies:

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: **Engineer of Record (EOR): Hillsborough County PM:

(Signature) (Signature) (Signature)

RANDY JAMES TAMISHE J. RODRIGUEZ, P.E. MANUEL E. SANTOS, E.I.

(Printed Name) (Printed Name) (Printed Name)

ENGINEER, PUBLIC WORKS ENGINEER OF RECORD

CAPITAL UTILTIY

COORDINATOR

(Title) (Title) (Title)

(Date) (Date) (Date)

Final Approval by Hillsborough County Utility Coordination:

(Signature) (Date)

LISA STROUT CAPITAL UTILITY MANAGER

(Printed Name) (Title)

(**When requested by the County, the EOR will attest to compatibility of plans, specifications and Utility Work Schedule)

Rodriguez, Tamishe (ChinTa) Text Box 7/15/2026

Special Conditions and Constraints

Frontier and Frontier Contractors' normal business hours are from 8am to 5pm, Monday through Friday.

Any work outside of normal business hours to be scheduled a minimum of 48 hours in advance.

Frontier inspector is to be the point of contact during construction and to be notified when working within 2' of

Frontier faculties. Paul Lineberry 813-838-8867 paul.a.lineberry@ftr.com

Frontier is to have access throughout the duration of the project to monitor and maintain facilities for the ability to provide service

Frontier requires 60 days for Engineering, budget approval, material procurement and permitting before construction for conflict resolution.

Frontier requests to meet on site with contractor.

Frontier requires 24 hour notice to meet on site.

Frontier requests staking of Drainage locations for prior to relocation work.

Adjusting- To hand dig with shovel or small excavator to move Frontier facility horizontally or vertically to clear conflict.

mailto:paul.a.lineberry@ftr.com

Section C. Disposition of Facilities (List All Existing & Proposed) on Project

Act No.

Type / Size /

Material

From Station/Offset

To Station/Offset

Description Of

Utility Work

Dependent Activities

M.O.T.

Phase

Number

Consecutive Calendar

Days Prior

During

1. Engineering (Design) 30 0

2. Permitting 15 0

3.

Material

Procurement 30 0

4.

BURIED

COPPER CABLE

1076+40, 130’L 1078+17, 66’L

1- CABLE TO BE

REMOVED (177’)

NEW

FACILITIES

ARE

PLACED,

SPLICED,

AND CUT

OVER

N/A 2 0

5. HANDHOLE 1078+77, 81’RT 1078+77, 81’RT

PROPOSED

PLACEMENT OF

HANDHOLE

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 0.5 0

6.

2- 2” CONDUITS

WITH FIBER

1078+77, 66’RT 1078+77, 81’RT

PROPOSED

PLACEMENT OF 2-

2” CONDUITS

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 1 0

7.

2- 2” CONDUITS

WITH FIBER

1078+77, 66’RT 1081+64, 66’RT

PROPOSED

PLACEMENT OF 2-

2” CONDUITS

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 2 0

8.

2’X3’

HANDHOLE

1081+64, 66’RT 1081+64, 66’RT

PROPOSED

PLACEMENT OF

HANDHOLE

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 0.5 0

9.

REMOVE

BURIED (4) 4”

CONDUITS WITH

FIBER AND

COPPER CABLE

1078+80, 82’RT 1081+25, 82’RT

4- 4” CONDUITS

WITH COPPER

CABLES AND FIBER

TO BE REMOVED

NEW

FACILITIES

ARE

PLACED,

SPLICED,

AND CUT

OVER

N/A 2 0

10.

2- 2” CONDUITS

WITH FIBER

1085+90, 62’L 1086+77, 62’L

PROPOSED

PLACEMENT OF 2-

2” CONDUITS

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 2 0

11.

2’X3’

HANDHOLE

1085+90, 62’L 1085+90, 62’L

PROPOSED

PLACEMENT OF

HANDHOLE

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 0.5 0

To Station/Offset

Description Of

Utility Work

Dependent Activities

M.O.T.

Phase

Number

Consecutive Calendar

Days Prior

During

12.

2- 2” CONDUITS

WITH FIBER

1086+77, 62’L 1088+00, 90’ L

PROPOSED

PLACEMENT OF 2-

2” CONDUITS

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 1 0

13.

2- 2” CONDUITS

WITH FIBER

1088+00, 90’ L 1089+67, 94’ L

PROPOSED

PLACEMENT OF 2-

2” CONDUITS

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 1 0

14.

2’X3’

HANDHOLE

1089+67, 94’ L 1089+67, 94’ L

PROPOSED

PLACEMENT OF

HANDHOLE

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 0.5 0

15.

2- 2” CONDUITS

WITH FIBER

1085+90, 62’RT 1085+90, 82’RT

PROPOSED

PLACEMENT OF 2-

2” CONDUITS

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 2 0

16.

2’X3’

HANDHOLE

1085+90, 82’RT 1085+90, 82’RT

PROPOSED

PLACEMENT OF

HANDHOLE

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 1 0

17.

2- 2” CONDUITS

WITH FIBER

1085+90, 82’RT 1089+05, 82’RT

PROPOSED

PLACEMENT OF 2-

2” CONDUITS

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 2 0

18.

2- 2” CONDUITS

WITH FIBER

1089+05, 82’RT 1089+50, 63’RT

PROPOSED

PLACEMENT OF 2-

2” CONDUITS

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 1 0

19.

REMOVE

BURIED (2) 4”

CONDUITS WITH

FIBER AND

COPPER CABLE

1085+90, 62’RT 1085+50, 62’RT

2- 4” CONDUITS

WITH COPPER

CABLES AND FIBER

TO BE REMOVED

AND GROUTED

NEW

FACILITIES

ARE PLACED,

SPLICED, AND

CUT OVER

N/A 2 0

20.

FTR 2’X3’

HANDHOLE

1088+03, 63’RT 1088+03, 63’RT

REMOVE 2’X3’

HANDHOLE

NEW

FACILITIES

ARE PLACED,

SPLICED, AND

CUT OVER

N/A 1 0

21.

FTR 2’X3’

HANDHOLE

1089+32, 57’L 1089+32, 57’L

REMOVE 2’X3’

HANDHOLE

NEW

FACILITIES

ARE PLACED,

SPLICED, AND

CUT OVER

N/A 0.5 0

22. FTR PEDESTAL 1089+32, 55’ L 1089+32,55’ L REMOVE PEDESTAL

NEW

FACILITIES

ARE PLACED,

SPLICED, AND

CUT OVER

To Station/Offset

Description Of

Utility Work

Dependent Activities

M.O.T.

Phase

Number

Consecutive Calendar

Days Prior

During

23.

1 BURIED FIBER

CABLE

1091+80, 93’L 1092+25, 93’L

1 BURIED FIBER

CABLE, TO BE

ADJUSTED AND

MODIFIED

STAKING OF

PROPOSED

MES

PH I STG 2 0 1

24.

1 BURIED FIBER

CABLE

1091+80, 91’L 1092+25, 91’L

1 BURIED COPPER

CABLE, TO BE

ADJUSTED AND

MODIFIED

STAKING OF

PROPOSED

MES

PH I STG 2 0 1

25.

1 BURIED FIBER

CABLE

1092+55, 93’L 1092+75, 107’L

1 BURIED FIBER

CABLE, TO BE

ADJUSTED AND

MODIFIED

STAKING OF

PROPOSED

30” RCP &

MES

PH I STG 2 0 1

26.

1 BURIED

COPPER CABLE

1092+55, 93’L 1092+75, 107’L

1 BURIED COPPER

CABLE, TO BE

ADJUSTED AND

MODIFIED

STAKING OF

PROPOSED

30” RCP &

MES

PH I STG 2 0 1

27.

2 SLC’S AND

POWER METER

1097+30, 115’RT 1097+30,115’RT

REMOVAL OF 2

SLC’S AND POWER

METER

STAKING OF

POND 1A

SOUTH BY

CONTRACTOR

N/A 120 0

28.

4” CONDUITS W/

FIBER INSIDE

PLUS 2 BURIED

COPPER

CABLES

1095+25, 65’RT 1095+70, 65’RT

ADJUST AND

MODIFY FOR

PROPOSED

PLACEMENT OF 24”

RCP

STAKING OF

PROPOSED

24” RCP BY

CONTRACTOR

PH 1 STG 2 0 1

29.

BURIED

FACILITIES AND

SWITCHING

EQUIPMENT, TO

BE REMOVED

1097+32, 65’RT 1097+32, 116’RT

REMOVE CABLES

AND SWITCHING

EQUIPMENT FOR

PROPOSED POND

AREA

PROPOSED

POND

STAKED BY

CONTRACTOR

PH 1 STG 2 0 15

30.

4” CONDUITS

WITH FIBER

AND 2 BURIED

COPPER

CABLES

1099+05, 79’RT 1099+55, 82’RT

ADJUST AND

MODIFY FOR

PROPOSED

PLACEMENT OF 30”

RCP

STAKING OF

PROPOSED

30” RCP BY

CONTRACTOR

PH I STG 2 0 1

31.

3’X5’

HANDHOLE

1099+55, 84’RT 1099+55, 84’RT

PROPOSED

PLACEMENT OF

HANDHOLE

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 0.5 0

32.

2- 4” CONDUITS

WITH CABLES

INSIDE

1099+55, 84’RT 1099+55, 152’RT

PROPOSED

PLACEMENT OF 2-

4” CONDUITS

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 1 0

33.

3’X5’

HANDHOLE

1099+55, 152’RT 1099+55, 152’RT

PROPOSED

PLACEMENT OF

HANDHOLE

NOTICE TO

PROCEED,

PERMIT

To Station/Offset

Description Of

Utility Work

Dependent Activities

M.O.T.

Phase

Number

Consecutive Calendar

Days Prior

During

34.

2- 4” CONDUITS

WITH CABLES

INSIDE

1099+55, 152’RT 1106+50, 134’RT

PROPOSED

PLACEMENT OF 2-

4” CONDUITS

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 3 0

35.

3’X5’

HANDHOLE

1106+50, 134’RT 1106+50, 134’RT

PROPOSED

PLACEMENT OF

HANDHOLE

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 0.5 0

36.

2- 4” CONDUITS

WITH CABLES

INSIDE

1106+55, 134’RT 1106+50, 90’RT

PROPOSED

PLACEMENT OF 2-

4” CONDUITS

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 1 0

37.

3’X5’

HANDHOLE

1106+50, 90’RT 1106+50, 90’RT

PROPOSED

PLACEMENT OF

HANDHOLE

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 0.5 0

38.

4” CONDUIT W/

FIBER INSIDE

AND 2 BURIED

COPPER

CABLES

1099+55, 83’RT 1100+54, 86’RT

4” CONDUITS W/

FIBER INSIDE PLUS

2 BURIED CABLES,

TO BE REMOVED

NEW

FACILITIES

ARE PLACED,

SPLICED, AND

CUT OVER

PH 1 STG 2 0 1

39. FTR MANHOLE 1100+55, 86’RT 1100+55, 86’RT

FTR MANHOLE, TO

BE REMOVED

NEW

FACILITIES

ARE PLACED,

SPLICED, AND

CUT OVER

PH 1 STG 2 0 3

40.

4” CONDUITS

WITH FIBER

INSIDE

1100+54, 86’RT 1100+50, 89’RT

4” CONDUITS W/

FIBER INSIDE, TO

BE REMOVED

NEW

FACILITIES

ARE PLACED,

SPLICED, AND

CUT OVER

PH 1 STG 2 0 1

41.

4” CONDUITS

WITH FIBER

1115+10, 84’RT 1115+45, 84’RT

ADJUST AND

MODIFY FOR

PROPOSED

PLACEMENT OF S-

STAKING OF

PROPOSED

24” RCP BY

CONTRACTOR

PH I STG 2 0 1

42.

2’X3’

HANDHOLE

1117+10, 80’RT 1117+10, 80’RT

PROPOSED

PLACEMENT OF

HANDHOLE

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 0.5 0

43.

2- 2” CONDUITS

WITH FIBER

1117+10, 80’RT 1117+10, 90’L

PROPOSED

PLACEMENT OF 2-

2” CONDUITS

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 2 0

44.

2- 2” CONDUITS

WITH FIBER

1117+10, 90’L 1116+80, 98’L

PROPOSED

PLACEMENT OF 2-

2” CONDUITS

NOTICE TO

PROCEED,

PERMIT

N/A 1 0

To Station/Offset

Description Of

Utility Work

Dependent Activities

M.O.T.

Phase

Number

Consecutive Calendar

Days Prior

During

45.

2- 2” CONDUITS

WITH FIBER

1128+90, 95’RT 1128+90, 95’L

PROPOSED

PLACEMENT OF 2-

2” CONDUITS

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 2 0

46.

2’X3’

HANDHOLE

1128+90, 95’L 1128+90, 95’L

PROPOSED

PLACEMENT OF

HANDHOLE

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 0.5 0

47.

2- 2” CONDUITS

WITH FIBER

1128+90, 95’RT 1128+90, 100’RT

PROPOSED

PLACEMENT OF 2-

2” CONDUITS

NOTICE TO

PROCEED,

PERMIT

APPROVAL

N/A 1 0

48. FIBER SPLICING

PLACE NEW FIBER

AND SPLICE

NEW

FACILITIES

ARE PLACED

N/A 15 0

49.

4- 4” CONDUIT

W/ FIBER

INSIDE AND 2

BURIED

COPPER

CABLES

1117+10, 80’RT 1128+90, 85’RT

4” CONDUITS W/

FIBER INSIDE PLUS

2 BURIED CABLES,

TO BE REMOVED

NEW

FACILITIES

ARE PLACED,

SPLICED, AND

CUT OVER

N/A 5 0

50.

FTR MANHOLE

6’X9’X12’

1122+00, 80’RT 1122+00, 80’RT

FTR MANHOLE, TO

BE REMOVED

NEW

FACILITIES

ARE PLACED,

SPLICED, AND

CUT OVER

N/A 5 0

51. 4- 4” CONDUITS 1122+00, 77’L 1122+00, 80’RT

GROUT FILL 4- 4”

CONDUITS

NEW

FACILITIES

ARE PLACED,

SPLICED, AND

CUT OVER

N/A 2 0

52. FTR MANHOLE 1122+00, 78’L 1122+00, 78’L

MANHOLE, TO

REMAIN, ADJUST

LID TO FINAL

GRADE

FINAL GRADE

STAKED BY

CONTRACTOR

PH I STG 2 0 0.5

53. FTR MANHOLE 136+96, 91’L 136+96, 91’L

MANHOLE, TO

REMAIN, ADJUST

LID TO FINAL

GRADE

FINAL GRADE

STAKED BY

CONTRACTOR

PH I STG 2 0 0.5

54. FTR MANHOLE 1097+32, 65’RT 1097+32, 65’RT

MANHOLE, TO

REMAIN, ADJUST

LID TO FINAL

GRADE

FINAL GRADE

STAKED BY

CONTRACTOR

PH I STG 2 0 0.5

55. FTR MANHOLE 1108+20, 87’RT 1108+20, 87’RT

MANHOLE, TO

REMAIN, ADJUST

LID TO FINAL

GRADE

FINAL GRADE

STAKED BY

CONTRACTOR

PH I STG 2 0 0.5

To Station/Offset

Description Of

Utility Work

Dependent Activities

M.O.T.

Phase

Number

Consecutive Calendar

Days Prior

During

56. FTR MANHOLE 1115+95, 83’RT 1115+95, 83’RT

MANHOLE, TO

REMAIN, ADJUST

LID TO FINAL

GRADE

FINAL GRADE

STAKED BY

CONTRACTOR

PH I STG 2 0 0.5

57.

FTR

HANDHOLES

1129+10, 131’RT 1129+10, 131’RT

2 HANDHOLES, TO

REMAIN, ADJUST

LID TO FINAL

GRADE

FINAL GRADE

STAKED BY

CONTRACTOR

PH I STG 2 0 1

58.

FTR HANDHOLE

AND FIBER HUB

212+20, 55’L 212+20, 55’L

HANDHOLE AND

FIBER HUB, TO

REMAIN, ADJUST

LID TO FINAL

GRADE

FINAL GRADE

STAKED BY

CONTRACTOR

PH I STG 2 0 0.5

59. FTR HANDHOLE 212+98, 55’L 212+98, 55’L

HANDHOLE, TO

REMAIN, ADJUST

LID TO FINAL

GRADE

FINAL GRADE

STAKED BY

CONTRACTOR

PH I STG 2 0 0.5

60.

61.

62.

63.

64.

65.

66.

2026-07-15T09:42:19-0400
Tamishe J Rodriguez
2026-07-15T09:52:04-0400
Lisa Strout
2026-07-15T10:15:32-0400
Manuel E. Santos

File details come from the government source that posted it. Updated .