Attachment I- Utility Relocation Schedule CIP 69647.000 Utility Cert Letter 7.15.26.pdf

PDF 17 KB Posted

Attached to
Big Bend Road from US 41 to Covington Garden Dr.
Solicitation number
IFB-26-00378
Issued by
Hillsborough County, Florida

About this file

This is a Utility Certification letter dated July 15, 2026, issued by Tamishe Rodriguez, P.E., Engineer of Record, to Manuel Santos, Hillsborough County Project Manager, confirming the completion of utility negotiations for CIP 69647.000, the Big Bend Road resurfacing and widening project in Hillsborough County, Florida. The certification confirms that all necessary utility arrangements have been completed and coordinated with the physical construction schedule, with detailed utility relocation schedules provided in the Special Provisions Plans Package. Eight utility companies—Frontier Florida, LLC; Level 3 Communications, LLC; MCI Metro Access Transmission Services, LLC; Peoples Gas System, Inc.; Spectrum Sunshine State LLC; Tampa Electric Company; Uniti Fiber, LLC; and Zayo Group, LLC—have utility relocation schedules in place. Verizon Wireless reported no conflicts, while CenturyLink Communications, LLC; Peoples Gas System, Inc. Transmission; and Tampa Bay Water were noted as not involved in the project.

The certification represents a critical milestone in project readiness, documenting that utility coordination requirements have been satisfied prior to construction commencement. The letter was copied to Jeanna Dean, Utility Coordinator at Harbor Coordination Solutions, Inc., indicating third-party coordination oversight. This utility certification supports the larger Big Bend Road project, which involves resurfacing and widening approximately 0.75 miles of existing four-lane divided rural highway to a six-lane urban typical section with associated infrastructure improvements and milling/resurfacing of Kings Lake Drive, with an estimated project cost of $21,624,946.34.

View the file

Other files

File Type Posted
Attachment E- 69692000 BigBendWest Drainage Design Documentation Vol. II Final.pdf PDF
21-Attachment B- Geo Report - 69692000 100P Misc Structures 2025-11-20.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 Spectrum Revised URS 7.13.2026 TR LS.pdf PDF
Attachment B- Geo Report - 69692000 100P Misc Structures 2025-11-20.pdf PDF
Attachment H- Plans- Lighting.pdf PDF
41-Attachment L- CSX Coordination.pdf PDF
Attachment G- FDOT Grant Agreement.pdf PDF
27-Attachment I- Utility Relocation Schedule 69647.000 100% REVISED - TEC UWS - REV4 7.13.26 TR LS.pdf PDF
13-AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
2-Florida Trench Safety Act, Certification and Disclosure Statement.pdf.pdf PDF
43-Attachment M- Work Class Percentage.pdf PDF
34-Attachment I- Utility Relocation Schedule 69647.000 Spectrum Revised URS 7.13.2026 TR LS.pdf PDF
46-Attachment G- FDOT Grant Agreement.pdf PDF
Attachment B- Geo Report - 69692000 PhIV Rdwy Soil Survey Report 2025-11-20.pdf PDF
40-Attachment K- Insurance Requirements.pdf PDF
52-Attachment H- Plans- ITS.pdf PDF
48-Attachment H- Location Map.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 100% REVISED - TEC UWS - REV4 7.13.26 TR LS.pdf PDF
Attachment H- Location Map.pdf PDF
11-Direct Deposit Authorization Form 5.15.2025.pdf.pdf PDF
AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
3-Allowance Authorization Release Form.pdf.pdf PDF
29-Attachment I- Utility Relocation Schedule CIP 69647.000 100% URS PGS7-10-2026 REV 1SignedTR.pdf PDF
Attachment D- Permits - SWFWMD ERP 43024488.004 Approved.pdf PDF
17-Attachment F- 69692000 6050BigBend ROE ChildcareBrandon 10-9-25 Signed.pdf PDF
Agreement - Construction - Stand Alone.docx.pdf PDF
54-Attachment K- CSX Insurance Receipt.pdf PDF
Attachment I- Utility Relocation Schedule 69647.000 BIG BEND US 41 TO COVINGTON FTR URS 071426 TR LS.pdf PDF
39-Attachment J- CSX1036508- Agreement.pdf PDF
Attachment B- Geo Report - 69692000 Kings Lake Dr Misc Struc 100% Geo Report SS.pdf PDF
8-Change Order Form.pdf.pdf PDF
42-Agreement - Construction - Stand Alone.docx.pdf PDF
Attachment E- 69692000 BigBendWest Drainage Design Documentation Vol. I Final SS (1).pdf PDF
14-Attachment D- Permits - SWFWMD ERP 43024488.004 Approved.pdf PDF
23-Attachment E- 69692000 Waterset-Kings Lake Drainage Memo.pdf PDF
Attachment F- 669692000 6089BigBend ROE HomeDepot 10-9-25 signed.pdf PDF
20-Attachment B- Geo Report - 69692000 PhIV Rdwy Soil Survey Report 2025-11-20.pdf PDF
Attachment B- Geo Report - 69692000 Waterset Trail 100% RSS SS.pdf PDF
47-Attachment H- Clear Letters 2.pdf PDF
18-Attachment F- 669692000 BayIndustrial ROE 10-9-25. signed.pdf PDF
30-Attachment I- Utility Relocation Schedule CIP 69647.000 URS Uniti Fiber REV 3 7.10.26 TR LS.pdf PDF
Attachment F- 669692000 BayIndustrial ROE 10-9-25. signed.pdf PDF
Attachment I- Utility Relocation Schedule CIP 69647.000 100% URS PGS7-10-2026 REV 1SignedTR.pdf PDF
36-Bid Bond.doc.doc DOC document
9-Insurance Certificate.doc.doc DOC document
31-Attachment I- Utility Relocation Schedule MCI 69647.000 100% URS WSP-8-26 LS.pdf PDF
Attachment A- Construction Sign 2026.pdf PDF
32-Attachment I- Utility Relocation SchedCIP 69647 000 US 41 to Covington Garden Drive Zayo UWS 71326 TR LS.pdf PDF
1-Drug Free Workplace Form.doc.doc DOC document
Attachment E- 69692000 Waterset-Kings Lake Drainage Memo.pdf PDF
Show 40 more

Latest 50 of 89 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

July 15, 2026

TO: Manuel Santos Hillsborough County Project Manager 601 E. Kennedy Blvd Tampa, FL 33602

SUBJECT : Utility Certification

CIP : 69647.000

County : Hillsborough Description : Big Bend Road from US 41 to Covington Garden Drive

Dear Mr. Santos, This CERTIFICATION means that all UTILITY negotiations have been completed and/or that the necessary arrangements have been made for the work to be undertaken and completed, as required, for proper coordination with the physical Construction Schedule. Appropriate notification which identifies all the UTILITY Work required for this Project, together with the status and/or schedule of completion, have been made a part of the Special Provisions Plans Package.

Utility Relocation Schedules: Frontier Florida, LLC Level 3 Communications, LLC MCI Metro Access Transmission Services, LLC Peoples Gas System, Inc Spectrum Sunshine State LLC Tampa Electric Company Uniti Fiber, LLC Zayo Group, LLC

No Conflicts: Verizon Wireless

Not Involved: CenturyLink Communications, LLC Peoples Gas System, Inc. – Transmission Tampa Bay Water

Sincerely

Tamishe Rodriguez, P.E.

Engineer of Record

Enclosures

CC: Jeanna Dean, Utility Coordinator, Harbor Coordination Solutions, Inc.

File

File details come from the government source that posted it. Updated .