26-Attachment I- Utility Relocation Schedule 69647.000 BIG BEND US 41 TO COVINGTON FTR URS 071426 TR LS.pdf
PDF 402 KB Posted
- Attached to
- Big Bend Road from US 41 to Covington Garden Dr.
- Solicitation number
- IFB-26-00378
- Issued by
- Hillsborough County, Florida
About this file
This is a Utility Relocation Schedule document prepared by Hillsborough County, Florida for the Big Bend Road project (CIP Number 69647.000), which involves the resurfacing and widening of approximately 0.75 miles of existing roadway from US 41 to Covington Garden Drive. The document outlines the relocation, adjustment, installation, and protection of Frontier Communications facilities along the project corridor. The utility work is divided into non-construction and construction phases, with engineering design requiring 30 calendar days, permitting 15 days, and material procurement 30 days prior to county project construction. During county project construction, Frontier Communications work is estimated at 32 calendar days. The project is at 100% design phase as of the plans dated June 12, 2026. Frontier Communications' project representative is Randy James (813-892-9692) and the field representative is Paul Lineberry (813-838-8867). The schedule includes 60 disposition items detailing the removal, adjustment, and installation of various fiber optic cables, conduits, handholes, and other telecommunications infrastructure throughout the project limits.
Frontier Communications requires 60 days for engineering, budget approval, material procurement, and permitting before construction begins for conflict resolution. All work outside normal business hours (8 a.m. to 5 p.m., Monday through Friday) must be scheduled a minimum of 48 hours in advance, and the Frontier inspector must be notified when work occurs within 2 feet of Frontier facilities. Frontier must maintain access throughout the project duration to monitor and maintain facilities for service continuity. The utility requests on-site meetings with the contractor with 24 hours' notice and requires staking of drainage locations prior to relocation work. Adjusting work is to be performed by hand digging with a shovel or small excavator to move Frontier facilities horizontally or vertically to clear conflicts. The document was updated in March 2026 and includes signatures from Tamishe J. Rodriguez (Engineer of Record), Manuel E. Santos (Capital Utility Coordinator), and Lisa Strout (Capital Utility Manager) with final approval granted on July 15, 2026.
View the file
Other files
Show 40 more
Latest 50 of 89 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Updated 3/2026
Hillsborough County County Road: 672 Plans Date: 06/12/2026
CIP Number: 69647.000 Project Name: US 41 TO COVINGTON GARDEN DR Project Phase: 100%
Utility Agency/Owner (UAO): FRONTIER COMMUNICATIONS
NON-CONSTRUCTION ITEMS
ESTIMATED
*CALENDAR DAYS
CONSTRUCTION ITEMS
ESTIMATED
*CALENDAR DAYS
Engineering Design 30 Prior to County Project Construction 184
Permitting 15 During County Project Construction 32
Material Procurement 30 Splicing
Other As-Built Information
* Calendar Days = UAO Workdays x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Hillsborough County, the roadway contractor, and other right-of-way users, the location, relocation, adjustment, installation, and/or protection of facilities, on this Hillsborough County project. The following data is based on the plans dated as listed in the Title Block.
Any deviation by Hillsborough County or its Contractor from plans, as provided may render this work schedule null and void.
Upon notification by, Hillsborough County of such change, this utility may require additional days for assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond the control of the UAO that could not reasonably be anticipated by the UAO and which could not be avoided by the UAO with the exercise of due diligence at the time of the occurrence. The UAO agrees to notify Hillsborough County in writing prior to starting, stopping, resuming, or completing work. The UAO is to provide As-Built information.
The UAO shall obtain a utility permit and comply with the requirements of the Hillsborough County UAM.
During the project, the UAO shall locate their facilities withing 48 hours of notice to their Representative.
UAO Project Representative: RANDY JAMES Telephone Number: 813-892-9692
UAO Field Representative: PAUL LINEBERRY Telephone Number: 813-838-8867
This document is a printout of a Hillsborough County form maintained in an electronic format and all revisions thereto by the UAO in the form of additions, deletions or substitutions are reflected only in an Appendix entitled “Changes to Form Document” and no change is made in the text of the document itself. Hand notations on affected portions of this document may refer to changes reflected in the above-named Appendix but are for reference purposes only and do not change the terms of the document. By signing this document, the UAO hereby represents that no change has been made to the text of this document except through the terms of the Appendix entitled “Changes to Form Document”.
You MUST signify by selecting or checking which of the following applies:
No changes to forms document.
Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.
Authorized Utility Agent: **Engineer of Record (EOR): Hillsborough County PM:
(Signature) (Signature) (Signature)
RANDY JAMES TAMISHE J. RODRIGUEZ, P.E. MANUEL E. SANTOS, E.I.
(Printed Name) (Printed Name) (Printed Name)
ENGINEER, PUBLIC WORKS ENGINEER OF RECORD
CAPITAL UTILTIY
COORDINATOR
(Title) (Title) (Title)
(Date) (Date) (Date)
Final Approval by Hillsborough County Utility Coordination:
(Signature) (Date)
LISA STROUT CAPITAL UTILITY MANAGER
(Printed Name) (Title)
(**When requested by the County, the EOR will attest to compatibility of plans, specifications and Utility Work Schedule)
Rodriguez, Tamishe (ChinTa) Text Box 7/15/2026
Special Conditions and Constraints
Frontier and Frontier Contractors' normal business hours are from 8am to 5pm, Monday through Friday.
Any work outside of normal business hours to be scheduled a minimum of 48 hours in advance.
Frontier inspector is to be the point of contact during construction and to be notified when working within 2' of
Frontier faculties. Paul Lineberry 813-838-8867 paul.a.lineberry@ftr.com
Frontier is to have access throughout the duration of the project to monitor and maintain facilities for the ability to provide service
Frontier requires 60 days for Engineering, budget approval, material procurement and permitting before construction for conflict resolution.
Frontier requests to meet on site with contractor.
Frontier requires 24 hour notice to meet on site.
Frontier requests staking of Drainage locations for prior to relocation work.
Adjusting- To hand dig with shovel or small excavator to move Frontier facility horizontally or vertically to clear conflict.
mailto:paul.a.lineberry@ftr.com
Section C. Disposition of Facilities (List All Existing & Proposed) on Project
Act No.
Type / Size /
Material
From Station/Offset
To Station/Offset
Description Of
Utility Work
Dependent Activities
M.O.T.
Phase
Number
Consecutive Calendar
Days Prior
During
1. Engineering (Design) 30 0
2. Permitting 15 0
3.
Material
Procurement 30 0
4.
BURIED
COPPER CABLE
1076+40, 130’L 1078+17, 66’L
1- CABLE TO BE
REMOVED (177’)
NEW
FACILITIES
ARE
PLACED,
SPLICED,
AND CUT
OVER
N/A 2 0
5. HANDHOLE 1078+77, 81’RT 1078+77, 81’RT
PROPOSED
PLACEMENT OF
HANDHOLE
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 0.5 0
6.
2- 2” CONDUITS
WITH FIBER
1078+77, 66’RT 1078+77, 81’RT
PROPOSED
PLACEMENT OF 2-
2” CONDUITS
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 1 0
7.
2- 2” CONDUITS
WITH FIBER
1078+77, 66’RT 1081+64, 66’RT
PROPOSED
PLACEMENT OF 2-
2” CONDUITS
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 2 0
8.
2’X3’
HANDHOLE
1081+64, 66’RT 1081+64, 66’RT
PROPOSED
PLACEMENT OF
HANDHOLE
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 0.5 0
9.
REMOVE
BURIED (4) 4”
CONDUITS WITH
FIBER AND
COPPER CABLE
1078+80, 82’RT 1081+25, 82’RT
4- 4” CONDUITS
WITH COPPER
CABLES AND FIBER
TO BE REMOVED
NEW
FACILITIES
ARE
PLACED,
SPLICED,
AND CUT
OVER
N/A 2 0
10.
2- 2” CONDUITS
WITH FIBER
1085+90, 62’L 1086+77, 62’L
PROPOSED
PLACEMENT OF 2-
2” CONDUITS
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 2 0
11.
2’X3’
HANDHOLE
1085+90, 62’L 1085+90, 62’L
PROPOSED
PLACEMENT OF
HANDHOLE
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 0.5 0
To Station/Offset
Description Of
Utility Work
Dependent Activities
M.O.T.
Phase
Number
Consecutive Calendar
Days Prior
During
12.
2- 2” CONDUITS
WITH FIBER
1086+77, 62’L 1088+00, 90’ L
PROPOSED
PLACEMENT OF 2-
2” CONDUITS
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 1 0
13.
2- 2” CONDUITS
WITH FIBER
1088+00, 90’ L 1089+67, 94’ L
PROPOSED
PLACEMENT OF 2-
2” CONDUITS
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 1 0
14.
2’X3’
HANDHOLE
1089+67, 94’ L 1089+67, 94’ L
PROPOSED
PLACEMENT OF
HANDHOLE
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 0.5 0
15.
2- 2” CONDUITS
WITH FIBER
1085+90, 62’RT 1085+90, 82’RT
PROPOSED
PLACEMENT OF 2-
2” CONDUITS
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 2 0
16.
2’X3’
HANDHOLE
1085+90, 82’RT 1085+90, 82’RT
PROPOSED
PLACEMENT OF
HANDHOLE
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 1 0
17.
2- 2” CONDUITS
WITH FIBER
1085+90, 82’RT 1089+05, 82’RT
PROPOSED
PLACEMENT OF 2-
2” CONDUITS
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 2 0
18.
2- 2” CONDUITS
WITH FIBER
1089+05, 82’RT 1089+50, 63’RT
PROPOSED
PLACEMENT OF 2-
2” CONDUITS
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 1 0
19.
REMOVE
BURIED (2) 4”
CONDUITS WITH
FIBER AND
COPPER CABLE
1085+90, 62’RT 1085+50, 62’RT
2- 4” CONDUITS
WITH COPPER
CABLES AND FIBER
TO BE REMOVED
AND GROUTED
NEW
FACILITIES
ARE PLACED,
SPLICED, AND
CUT OVER
N/A 2 0
20.
FTR 2’X3’
HANDHOLE
1088+03, 63’RT 1088+03, 63’RT
REMOVE 2’X3’
HANDHOLE
NEW
FACILITIES
ARE PLACED,
SPLICED, AND
CUT OVER
N/A 1 0
21.
FTR 2’X3’
HANDHOLE
1089+32, 57’L 1089+32, 57’L
REMOVE 2’X3’
HANDHOLE
NEW
FACILITIES
ARE PLACED,
SPLICED, AND
CUT OVER
N/A 0.5 0
22. FTR PEDESTAL 1089+32, 55’ L 1089+32,55’ L REMOVE PEDESTAL
NEW
FACILITIES
ARE PLACED,
SPLICED, AND
CUT OVER
To Station/Offset
Description Of
Utility Work
Dependent Activities
M.O.T.
Phase
Number
Consecutive Calendar
Days Prior
During
23.
1 BURIED FIBER
CABLE
1091+80, 93’L 1092+25, 93’L
1 BURIED FIBER
CABLE, TO BE
ADJUSTED AND
MODIFIED
STAKING OF
PROPOSED
MES
PH I STG 2 0 1
24.
1 BURIED FIBER
CABLE
1091+80, 91’L 1092+25, 91’L
1 BURIED COPPER
CABLE, TO BE
ADJUSTED AND
MODIFIED
STAKING OF
PROPOSED
MES
PH I STG 2 0 1
25.
1 BURIED FIBER
CABLE
1092+55, 93’L 1092+75, 107’L
1 BURIED FIBER
CABLE, TO BE
ADJUSTED AND
MODIFIED
STAKING OF
PROPOSED
30” RCP &
MES
PH I STG 2 0 1
26.
1 BURIED
COPPER CABLE
1092+55, 93’L 1092+75, 107’L
1 BURIED COPPER
CABLE, TO BE
ADJUSTED AND
MODIFIED
STAKING OF
PROPOSED
30” RCP &
MES
PH I STG 2 0 1
27.
2 SLC’S AND
POWER METER
1097+30, 115’RT 1097+30,115’RT
REMOVAL OF 2
SLC’S AND POWER
METER
STAKING OF
POND 1A
SOUTH BY
CONTRACTOR
N/A 120 0
28.
4” CONDUITS W/
FIBER INSIDE
PLUS 2 BURIED
COPPER
CABLES
1095+25, 65’RT 1095+70, 65’RT
ADJUST AND
MODIFY FOR
PROPOSED
PLACEMENT OF 24”
RCP
STAKING OF
PROPOSED
24” RCP BY
CONTRACTOR
PH 1 STG 2 0 1
29.
BURIED
FACILITIES AND
SWITCHING
EQUIPMENT, TO
BE REMOVED
1097+32, 65’RT 1097+32, 116’RT
REMOVE CABLES
AND SWITCHING
EQUIPMENT FOR
PROPOSED POND
AREA
PROPOSED
POND
STAKED BY
CONTRACTOR
PH 1 STG 2 0 15
30.
4” CONDUITS
WITH FIBER
AND 2 BURIED
COPPER
CABLES
1099+05, 79’RT 1099+55, 82’RT
ADJUST AND
MODIFY FOR
PROPOSED
PLACEMENT OF 30”
RCP
STAKING OF
PROPOSED
30” RCP BY
CONTRACTOR
PH I STG 2 0 1
31.
3’X5’
HANDHOLE
1099+55, 84’RT 1099+55, 84’RT
PROPOSED
PLACEMENT OF
HANDHOLE
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 0.5 0
32.
2- 4” CONDUITS
WITH CABLES
INSIDE
1099+55, 84’RT 1099+55, 152’RT
PROPOSED
PLACEMENT OF 2-
4” CONDUITS
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 1 0
33.
3’X5’
HANDHOLE
1099+55, 152’RT 1099+55, 152’RT
PROPOSED
PLACEMENT OF
HANDHOLE
NOTICE TO
PROCEED,
PERMIT
To Station/Offset
Description Of
Utility Work
Dependent Activities
M.O.T.
Phase
Number
Consecutive Calendar
Days Prior
During
34.
2- 4” CONDUITS
WITH CABLES
INSIDE
1099+55, 152’RT 1106+50, 134’RT
PROPOSED
PLACEMENT OF 2-
4” CONDUITS
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 3 0
35.
3’X5’
HANDHOLE
1106+50, 134’RT 1106+50, 134’RT
PROPOSED
PLACEMENT OF
HANDHOLE
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 0.5 0
36.
2- 4” CONDUITS
WITH CABLES
INSIDE
1106+55, 134’RT 1106+50, 90’RT
PROPOSED
PLACEMENT OF 2-
4” CONDUITS
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 1 0
37.
3’X5’
HANDHOLE
1106+50, 90’RT 1106+50, 90’RT
PROPOSED
PLACEMENT OF
HANDHOLE
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 0.5 0
38.
4” CONDUIT W/
FIBER INSIDE
AND 2 BURIED
COPPER
CABLES
1099+55, 83’RT 1100+54, 86’RT
4” CONDUITS W/
FIBER INSIDE PLUS
2 BURIED CABLES,
TO BE REMOVED
NEW
FACILITIES
ARE PLACED,
SPLICED, AND
CUT OVER
PH 1 STG 2 0 1
39. FTR MANHOLE 1100+55, 86’RT 1100+55, 86’RT
FTR MANHOLE, TO
BE REMOVED
NEW
FACILITIES
ARE PLACED,
SPLICED, AND
CUT OVER
PH 1 STG 2 0 3
40.
4” CONDUITS
WITH FIBER
INSIDE
1100+54, 86’RT 1100+50, 89’RT
4” CONDUITS W/
FIBER INSIDE, TO
BE REMOVED
NEW
FACILITIES
ARE PLACED,
SPLICED, AND
CUT OVER
PH 1 STG 2 0 1
41.
4” CONDUITS
WITH FIBER
1115+10, 84’RT 1115+45, 84’RT
ADJUST AND
MODIFY FOR
PROPOSED
PLACEMENT OF S-
STAKING OF
PROPOSED
24” RCP BY
CONTRACTOR
PH I STG 2 0 1
42.
2’X3’
HANDHOLE
1117+10, 80’RT 1117+10, 80’RT
PROPOSED
PLACEMENT OF
HANDHOLE
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 0.5 0
43.
2- 2” CONDUITS
WITH FIBER
1117+10, 80’RT 1117+10, 90’L
PROPOSED
PLACEMENT OF 2-
2” CONDUITS
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 2 0
44.
2- 2” CONDUITS
WITH FIBER
1117+10, 90’L 1116+80, 98’L
PROPOSED
PLACEMENT OF 2-
2” CONDUITS
NOTICE TO
PROCEED,
PERMIT
N/A 1 0
To Station/Offset
Description Of
Utility Work
Dependent Activities
M.O.T.
Phase
Number
Consecutive Calendar
Days Prior
During
45.
2- 2” CONDUITS
WITH FIBER
1128+90, 95’RT 1128+90, 95’L
PROPOSED
PLACEMENT OF 2-
2” CONDUITS
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 2 0
46.
2’X3’
HANDHOLE
1128+90, 95’L 1128+90, 95’L
PROPOSED
PLACEMENT OF
HANDHOLE
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 0.5 0
47.
2- 2” CONDUITS
WITH FIBER
1128+90, 95’RT 1128+90, 100’RT
PROPOSED
PLACEMENT OF 2-
2” CONDUITS
NOTICE TO
PROCEED,
PERMIT
APPROVAL
N/A 1 0
48. FIBER SPLICING
PLACE NEW FIBER
AND SPLICE
NEW
FACILITIES
ARE PLACED
N/A 15 0
49.
4- 4” CONDUIT
W/ FIBER
INSIDE AND 2
BURIED
COPPER
CABLES
1117+10, 80’RT 1128+90, 85’RT
4” CONDUITS W/
FIBER INSIDE PLUS
2 BURIED CABLES,
TO BE REMOVED
NEW
FACILITIES
ARE PLACED,
SPLICED, AND
CUT OVER
N/A 5 0
50.
FTR MANHOLE
6’X9’X12’
1122+00, 80’RT 1122+00, 80’RT
FTR MANHOLE, TO
BE REMOVED
NEW
FACILITIES
ARE PLACED,
SPLICED, AND
CUT OVER
N/A 5 0
51. 4- 4” CONDUITS 1122+00, 77’L 1122+00, 80’RT
GROUT FILL 4- 4”
CONDUITS
NEW
FACILITIES
ARE PLACED,
SPLICED, AND
CUT OVER
N/A 2 0
52. FTR MANHOLE 1122+00, 78’L 1122+00, 78’L
MANHOLE, TO
REMAIN, ADJUST
LID TO FINAL
GRADE
FINAL GRADE
STAKED BY
CONTRACTOR
PH I STG 2 0 0.5
53. FTR MANHOLE 136+96, 91’L 136+96, 91’L
MANHOLE, TO
REMAIN, ADJUST
LID TO FINAL
GRADE
FINAL GRADE
STAKED BY
CONTRACTOR
PH I STG 2 0 0.5
54. FTR MANHOLE 1097+32, 65’RT 1097+32, 65’RT
MANHOLE, TO
REMAIN, ADJUST
LID TO FINAL
GRADE
FINAL GRADE
STAKED BY
CONTRACTOR
PH I STG 2 0 0.5
55. FTR MANHOLE 1108+20, 87’RT 1108+20, 87’RT
MANHOLE, TO
REMAIN, ADJUST
LID TO FINAL
GRADE
FINAL GRADE
STAKED BY
CONTRACTOR
PH I STG 2 0 0.5
To Station/Offset
Description Of
Utility Work
Dependent Activities
M.O.T.
Phase
Number
Consecutive Calendar
Days Prior
During
56. FTR MANHOLE 1115+95, 83’RT 1115+95, 83’RT
MANHOLE, TO
REMAIN, ADJUST
LID TO FINAL
GRADE
FINAL GRADE
STAKED BY
CONTRACTOR
PH I STG 2 0 0.5
57.
FTR
HANDHOLES
1129+10, 131’RT 1129+10, 131’RT
2 HANDHOLES, TO
REMAIN, ADJUST
LID TO FINAL
GRADE
FINAL GRADE
STAKED BY
CONTRACTOR
PH I STG 2 0 1
58.
FTR HANDHOLE
AND FIBER HUB
212+20, 55’L 212+20, 55’L
HANDHOLE AND
FIBER HUB, TO
REMAIN, ADJUST
LID TO FINAL
GRADE
FINAL GRADE
STAKED BY
CONTRACTOR
PH I STG 2 0 0.5
59. FTR HANDHOLE 212+98, 55’L 212+98, 55’L
HANDHOLE, TO
REMAIN, ADJUST
LID TO FINAL
GRADE
FINAL GRADE
STAKED BY
CONTRACTOR
PH I STG 2 0 0.5
60.
61.
62.
63.
64.
65.
66.
| 2026-07-15T09:42:19-0400 | |
| Tamishe J Rodriguez |
| 2026-07-15T09:52:04-0400 | |
| Lisa Strout |
| 2026-07-15T10:15:32-0400 | |
| Manuel E. Santos |
File details come from the government source that posted it. Updated .