WASTEWATER PRETREATMENT PLANT OPERATION AND MAINTENANCE SERVICES
Solicitation number
2031ZA26R00023
Issued by

About this file

This is an Amendment of Solicitation/Modification of Contract (Standard Form 30) dated August 6, 2026, for solicitation number 2031ZA26R00023. The amendment updates Section L (Instructions, Conditions and Notices to Offerors), Section M (Evaluation for Award), Attachment C (Site Visit Information), and Attachment B (Pricing Sheet).

The solicitation is an 8(a) Set-aside for wastewater pretreatment and maintenance support services, bulk chemical procurement, wiping solution production, and wiping solution recycling at the Bureau of Engraving and Printing (BEP) Washington, DC facility. Offerors must submit Firm-Fixed Price proposals consisting of three volumes: Volume I (Technical Capability, 25-page limit), Volume II (Past Performance, 10-page limit), and Volume III (Price Quote). An optional site visit is scheduled for August 11, 2026. Clarification questions must be submitted by August 17, 2026 at 12:00 p.m. Eastern, and proposals are due by September 15, 2026 at 12:00 p.m. Eastern via email to marico.sellers@treasury.gov. Offerors must be registered in the System for Award Management (SAM) and must hold prices firm for 90 calendar days. Award will be made using a trade-off approach where Technical Capability (Volume 1) is weighted equally to Past Performance (Volume 2), with both factors combined being significantly more important than Price (Volume 3). The Government intends to award one contract without negotiations, though the right to conduct discussions is reserved. Proposals must demonstrate understanding of PWS requirements, relevant staffing qualifications with security clearances, technical methodology for regulatory compliance and quality assurance, and at least two references demonstrating relevant experience within the past five years.

View the file

Other files

File Type Posted
Attachment A - PWS Waste Water Pretreatment Plant Operation and Maintenance_6 Oct 2026.pdf PDF
2031ZA26R00023 0004.pdf PDF
Attachment B - Pricing Sheet - 21 Aug 2026.xlsx XLSX spreadsheet
WWPP - Request for Clarifications-Questions-Answers.xlsx XLSX spreadsheet
2031ZA26R00023 0003.pdf PDF
Attachment A - PWS Waste Water Pretreatment Plant Operation and Maintenance_v5 - 21 Aug 2026.pdf PDF
2031ZA26R00023 0002 - 07 Aug 2026.pdf PDF
Attachment D - Past Performance Questionnaire.docx DOCX document
Attachment B - Pricing Sheet - 6 Aug 2026.xlsx XLSX spreadsheet
Attachment C - Site Visit Information - 6 Aug 2026.docx DOCX document
2031ZA26R00023 WWPP Solicitation.pdf PDF
Att 24 - Nonreimburseable Tools - Janitorial - PPE Supplies.pdf PDF
Att 17 - Filter Aid Specification.pdf PDF
Att 2 - WSWPP Process Description.pdf PDF
Att 11 - Wage Determination.pdf PDF
Attachment A - PWS Waste Water Pretreatment Plant Operation and Maintenance_v4.pdf PDF
Att 13 - Restricted Materials at DCF.pdf PDF
Att 26 - Equipment.pdf PDF
Att 15 - Sulfuric Acid Specification.pdf PDF
Att 18 - Sodium Hydroxide Specification.pdf PDF
Att 21 - Pallets Specification.pdf PDF
Att 7 - BEP Furnished Equipment.pdf PDF
Attachment 27 - Corrosion Monitoring.pdf PDF
Att 9 - WSWPP Equipment List.pdf PDF
Att 20 - Boxes - Lids Specification.pdf PDF
Att 10 - PWPP Equipment List.pdf PDF
Att 1 - BEP 017-12.pdf PDF
Attachment B - Pricing Sheet.xlsx XLSX spreadsheet
Attachment 28 Staffing Plan.doc DOC document
Att 23 - Spare Parts and Supplies.pdf PDF
Att 3 - PWPP Process Description.pdf PDF
Att 5 - WSRP Process Description.pdf PDF
Att 16 - Sodium Bisulfite Specification.pdf PDF
Attachment 29 - Monthly Workforce Report.docx DOCX document
Att 19 - Sodium-Sulfated Castor Oil Specification.pdf PDF
Att 25 - Laboratory Analysis.pdf PDF
Att 22 - Process and Treatment Chemicals.pdf PDF
Att 14 - Bentonite Specification.pdf PDF
Att 4 - GTWPP Process Description.pdf PDF
Att 12 - EHS Requirements for Purchased Materials.pdf PDF
Attachment C - Site Visit Information.pdf PDF
Att 8 - EHS Contractor Requirements.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. If applic ble)

7. ADMINISTERED BY If other than Item 6 ODE

STANDARD FORM 30 REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPR ATION DATA If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES such as changes in paying office, appropriation date, etc. SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER Type or print

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR No., street, county, State and ZIP Code X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

1 10

2. AMENDMENT/MODIFICATION

NO. 2031ZA26R00023 1

3. EFFECTIVE

DATE

08/06/2026

9A. AMENDMENT OF SOLICI ATION

NO. 2031ZA26R00023

9B. DATE SEE ITEM

11) 08/06/2026

14. DESCRIPTION OF AMENDMENT/MODIFICATION ( rganized by UCF section headings, including solicitation/contract subject matter where feasible.)

AMENDMENT CONTROL NUMBER : 2031ZA26R00023

SUMMARY OF CHANGES : The purpose of this modification is to;

1. Update Section L

2. Update Section M.

3. Update Attachment C - Site Visit Info

4. Update Attachment B- Pricing Sheet

Same As Issuing Office

SECTION L – INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

1.0 GENERAL INFORMATION

1.1 This procurement is a 8(a) Set-aside.

1.2 Price: Offeror shall submit a Firm-Fixed Price.

1.3 Offeror is expected to examine this entire request for quotation. Failure to do so will be at the Offeror's own risk.

1.4 The Government intends to evaluate proposals and may award a contract without discussions in accordance with FAR provision 52.215-1. Therefore, initial proposals should contain the offeror’s best terms from a technical and price standpoint. If the Contracting Officer determines that discussions are necessary, a competitive range will be established comprised of the most highly rated proposals. The Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly evaluated proposals (10 U.S.C. 3303; 41 U.S.C. 3703). Offerors excluded from the competitive range will be notified in writing in accordance with FAR 15.206-1(a).

1.5 The Government will not pay any Offeror for preparation of their proposal. This solicitation may be cancelled at the discretion of the Government.

1.6 Offeror shall set forth full, accurate, and complete information as required by this RFQ package. The penalty for making false statements is prescribed in 18 U.S.C. 1001.

1.7 Offeror is required to be registered in the System for Award Management (SAM) at the time an offer or quotation is submitted. Therefore, to be responsive, registration with SAM must be current. To register or update your company information, please go to SAM.gov.

2.0 PERIOD FOR ACCEPTANCE OF OFFER

The Offeror agrees to hold the prices in its quote firm for 90 calendar days from the date specified for receipt of quotes.

3.0 SITE VISIT

Prospective Offerors are welcome to attend an optional site visit tentatively scheduled with BEP representative(s) for 11 August 2026, at the Washington, DC site. Prospective Offerors will have the opportunity to view the general layout of buildings, elevators, and elevator machine rooms,, the possible route(s) and elevators that can be used to take equipment out to the street and/or parking lot. See site visit instructions in attachment C. Photos may/may not be allowed, it will be determined at the site visit.

4.0 REQUEST FOR CLARIFICATIONS

All requests for clarifications/questions related to the RFQ shall be submitted to marico.sellers@treasury.gov no later than 12:00 p.m. (Eastern), Wednesday, 17 August 2026.

Phone inquiries will not be accepted.

5.0 SUBMISSION OF OFFERS

Proposals shall be submitted via email to Marico Sellers @ marico.sellers@treasury.gov no later than 12:00 p.m. (Eastern), Wednesday, 15 September 2026.

6.0 PREPERATION COST

This RFP does not commit the government to pay for the preparation and submission of a quote.

The Contracting Officer is the only individual who can legally bind the Government to the expenditure of public funds in connection with this procurement.

7.0 Quotes Format

Offers shall be submitted through electronic means (via email) only. Page size, not including foldouts, shall be 8 ½" X 11", when printed. All pages shall have a 1" margin on all sides and shall be typed with at least single line spacing. No condensed fonts allowed. Times New Roman, Calibri, Arial font preferred. Text shall be a minimum font size of 12. Page numbers, company logos, headers and footers may be outside the page margins and are not bound by the 12-font size but shall be no smaller than 8-point. Each paragraph shall be separated by at least one blank line.

All text pages shall be oriented in portrait and printed black on white paper (black and white requirement does not apply to graphics, photos, etc., Company stationery and logos are acceptable). Landscape orientation is acceptable for tables and/or charts if required to properly present the information. A page shall be an 8 ½" X 11" sheet of paper. Letter size and spacing requirements for illustrations and tables can be at the discretion of the Offeror but must be easily readable. Offerors shall number each page to eliminate any confusion. In the event the Offeror creates an ambiguity in their numbering of pages, the Government may exercise its own discretion in counting pages.

Page Limit DOES NOT include covers for volumes, tables of contents, glossary of abbreviations and acronyms, indices, title pages, cross reference indices, resumes, and section dividers/tables if they are inserted solely to provide ease to the reader in locating parts/sections of the proposal.

8.0 CONTENT OF QUOTE SUBMISSION

Offerors shall also reference FAR Clause 52.212-1 Instructions to Offerors - Commercial Items (SEP 2023), included as reference in section I of this Solicitation.

Offerors shall submit a single quote which includes information to be evaluated for award. Quote shall consist of three (3) volumes, as follows:

QUOTATION ORGANIZATION

Volume Factor Page Limit Volume I Factor 1, Technical 25 Volume II Factor 2, Past Performance 10 Volume III Factor 3, Price Quote None

Volume I/Factor 1 Technical

Factor 1: Technical Capability: The offeror shall provide a technical approach clearly demonstrating how the Government's requirement will be met. (See Attachments A & 1-27) This section shall address:

Sub-factor 1.1 Experience

• The Offeror’s demonstrate a clear understanding of and ability to oversee and carry out, the objectives, scope, tasks and other requirements of the PWS and to perform at a level that meets or exceeds the BEP’s requirements for providing wastewater pretreatment and maintenance, support services.

• The Offeror shall demonstrate the ability to provide the services required for the procurement of bulk chemicals, production of wiping solution, and the recycling of wiping solution at a level that meets or exceeds the BEP’s Quality Assurance requirements as noted in the PWS.

• The Offeror shall demonstrate ability to provide services for wastewater pretreatment and maintenance, support services and emergency services (“Emergency services”) in support of the BEP’s Washington DC facility.

• The contractor shall demonstrate its ability to provide Emergency services requested by authorized and designated BEP personnel wherein services are required of the Contractor to respond to an unplanned/ unscheduled event.

Sub-factor 1.2 - Staffing Plan/Key Personnel Qualifications

• The contractor shall provide the support staffing in conjunction to Section 2 of the (PWS): Offerors shall demonstrate the ability of its proposed skill personnel to understand and carry out the requirements of the PWS and perform all tasks at a level that consistently meets or exceeds the performance standards.

• The Staffing Plan demonstrates how the positions, tasks to be performed, hours to be worked, and the education, certifications, experience and expertise of proposed skill set that will fill each position are relevant to the needs of the PWS and adequate to carry out the PWS requirements and perform all tasks at a level that consistently meets or exceeds the performance standards.

• Security clearances and background investigation will be required.

• Resumes, certifications should be provided for and required designated key personnel.

Sub-factor 1.3 Methodology: Demonstration of Regulatory Compliance, Technical Adaptability, and Quality Assurance

• The Offeror shall demonstrate the technical ability to meet the regulatory standards of the contract by providing methods of industrial wastewater treatment services, specifically to the treatment of industrial byproducts from nickel and chrome operations, wastewater with high organic loads, heavy pigments, resins, solids, and surfactants. This includes evidence of successful service provision that aligns with the BEP’s permit requirements and the operational needs as detailed in the PWS.

• The Offeror shall demonstrate the technical ability to operate and support the Wiping Solution Recycling Plant by demonstrating methods of chemical reclamation, mechanical reclamation, and the possible interferences that can occur with both types of product recovery.

• The Offeror shall demonstrate comprehensive technical expertise to modify and optimize wastewater treatment strategies in response to operational changes at the BEP, as referenced under Process Improvements in the PWS. This includes the ability to adapt treatment methodologies for new ink formulations, the addition of printing presses, the implementation of ultrafiltration technology, and evolving permit requirements. The Offeror's approach should show a clear understanding of the impact these factors have on treatment processes and the regulatory aspects, ensuring continued compliance and management of industrial byproducts.

• The Offeror shall demonstrate the capability to collaborate with cross-functional teams, such as Quality Assurance, Product Development, Manufacturing, and Facilities Divisions to address and resolve issues related to production. This includes providing technical support and expertise to troubleshoot problems, ensuring that all manufacturing processes adhere to quality standards. Demonstration should illustrate successful resolution of manufacturing challenges.

Volume 2/Factor 2 Past Performance

The Government will assess the offerors capability to perform under this agreement by evaluating the offerors past performance experience on previous same or similar contracts.

Offerors shall identify at least two (2) Federal, State, Local, or Commercial contracts that demonstrate recent and relevant experience. Recent is defined as within the last five (5) years.

Relevant is defined as work similar in size, scope, and complexity to the work identified in the PWS. Offerors shall provide the following information:

• Project Title

• Owner

• Occupants(s)/Tenant(s)

• Location

• Description of the Project

• Contract Number

• Contract Amount

• Contracting Officer's name, address, telephone number and email address

• Current status, e.g. completed and/or in progress, start and estimated completion dates

• Contractors & key personnel assigned full-time to the project.

• Two reference, along with the references’ title, official duties, email addresses, phone numbers, and mailing address.

• A brief narrative of why your firm believes this reference is relevant to the proposed tasks

The offeror is responsible for ensuring that the names, telephone numbers, e-mail addresses and addresses of all references provided are correct, and that references will respond to the Government’s inquiries.

BEP may contact those references during the evaluation process to verify accuracy of the information provided by the Offeror. The BEP may, at its discretion, obtain and evaluate information from sources other than those provided by the Offeror.

Volume 3/Factor 3 Price Quote

Offeror shall complete and submit Attachment B, Pricing Schedule. Offeror must price all ordering periods with Firm Fixed Price. Failure to provide pricing for all items will render the offer unacceptable and ineligible for award consideration.

SECTION M – EVALUATION FOR AWARD

EVALUATION-COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021)

(a) Award will be made using the Tradeoff approach. As this acquisition is utilizing a ‘trade-off” methodology, the relative order of importance of the Volumes delineated accordingly: Technical Capability (Volume 1) is equal to Past Performance (Volume 2). Finally, in accordance with Revolutionary FAR Overhaul (RFO) 15.103-3(a), all evaluation Factors other than Price (Volume 3), when combined, are significantly more important that price. The Government intends to award one contract as a result of this solicitation. In using the tradeoff approach, the Government seeks to award to the Offeror who gives the Agency the greatest confidence that it will best meet or exceed our requirements in a way that will be advantageous to the Government. This may result in an award to a higher rated, higher priced Offeror where the decision is consistent with the evaluation factors and the Contracting Officer (CO) reasonably determines that the past and present performance of the higher priced Offeror outweighs the price difference. However, the degree of importance of cost/price as a factor in determining award could become greater depending upon the equality of the proposals evaluated in the non-cost/price Volumes. The greater the equality of proposals within the non-cost/price factors, the more important cost/price becomes in selecting the best value to the Government.

To arrive at a decision, the CO will integrate the technical team’s evaluations of the factors described in this provision. While the Government will strive for maximum objectivity, the tradeoff process, by its nature, is subjective; therefore, professional judgment is implicit throughout the selection process. Award will be made to the responsible Offeror whose proposal conforms to all required terms and conditions, includes all required representations and certifications, meets all requirements set forth in the solicitation, and also provides the best value to the Government based on the results of the evaluation as described below.

It is the Government’s intention to award without negotiations. Offerors are encouraged to present their best proposal and prices in their initial proposal submission. However, in accordance with RFO Part 15.204, the Government reserves the right to hold negotiations if necessary. The Offeror is reminded that the Government reserves the right to award this effort based on the initial proposal, as received, without negotiations.

The following factors shall be used to evaluate offers:

Volume 1/Factor 1 Technical Capability

Factor 1: Technical Capability: The Government will evaluate the degree to which the technical approach demonstrates a thorough understanding of the requirements and provides a viable plan and means for successful completion, including methodology for completion of the requirements in the PWS.

The Offeror’s Technical will be evaluated as Outstanding, Good, Acceptable, Marginal or Unacceptable. To receive consideration for award, a rating of no less than “Acceptable” must be achieved for the Technical Capability Volume. If an Offeror’s Technical Volume is found to be below Acceptable, it will not be further evaluated.

VOLUME 1 Technical Capability: The Technical Capability evaluation provides an assessment of the Offeror’s capability to satisfy the Government’s requirements. The evaluation will focus on the strengths, weaknesses, significant weaknesses, and deficiencies of the Offeror's proposal.

The Contractor will be evaluated on its ability to: 1) Demonstrate a clear understanding of the work to be performed; 2) Meet the Government’s objective; 3) Perform the tasks and deliverables of the PWS within the period of performance; 4) Deliver a management and staffing approach to support the PWS.

Table 1. Technical Volume Risk Rating Method

Combined Technical/Risk Rating. The combined technical/risk rating includes consideration of risk in conjunction with the strengths, weaknesses, significant weaknesses, uncertainties and deficiencies in determining technical ratings. Combined technical/risk evaluations shall utilize the combined technical/risk ratings listed in Table 1. Each Technical Capability will receive one of the adjectival ratings defined below. Any Volume that receives a marginal or unacceptable rating will result in an overall marginal or unacceptable rating and will not eligible for award.

Adjectival Rating Description

Outstanding Proposal demonstrates an exceptional approach and understanding of the requirements and contains multiple strengths and/or at least one significant strength, and risk of unsuccessful performance is low.

Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength or significant strength, and risk of unsuccessful performance is low to moderate.

Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate

Marginal

Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.

Unacceptable Proposal does not meet requirements of the solicitation and, thus, contains one or more deficiencies and is unawardable, and/or risk of performance is unacceptably high.

Factor 2 Past Performance

The Government will assess the Offeror capability to perform under this agreement by evaluating the Offerors past performance experience on previous same or similar contracts. The BEP may contact any references provided by the Offeror during the evaluation process to verify recent and relevant experience and the level of performance. The BEP may, at its discretion, obtain and evaluate information from sources other than those provided by the Offeror, such as those found in the Contractor Performance Assessment Reporting System (CPARS).

The Past Performance rating will be based on an "Acceptable" / "Unacceptable" basis. The following definitions will be used in evaluating the degree the offeror will satisfactorily provide the required services based on past and current performance records. An Acceptable or Unacceptable rating will be determined as follows:

Rating Description Acceptable Based on the offeror's performance record, the Government has reasonable expectation that the offeror will successfully perform the required effort, or the offeror's performance record is unknown. (See note below)

Unacceptable Based on the offeror's performance record, the Government does not have a reasonable expectation that the offeror will be able to successfully perform the required effort.

Note: In the case of an Offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance. Therefore, the offeror shall be determined to have neutral past performance. In the context of acceptability/unacceptability, "neutral" shall be considered "acceptable."

Factor 3 Price Quote

The total evaluated price shall be the sum of all prices listed in the price schedule for the three-year ordering periods. The Government will evaluate price to determine fair and reasonableness.

The Government will use any combination of the price analysis techniques stipulated under FAR Subpart 13.106-3.

Basis for award

Award will be made on the basis of ‘trade-off”, the relative order of importance of the Volumes delineated accordingly: Technical Capability (Volume 1) is equal to Past Performance (Volume 2). All evaluation Factors other than Price (Volume 3), when combined, are significantly more important that price when meeting or exceeding the acceptability standards for non-cost (i.e., Technical and Past Performance) factors. All proposals will undergo a review of the Technical Approach and Past Performance while simultaneously undergoing an evaluation of price. An offer is technically acceptable if it is fully compliant with all of the requirements of terms and conditions herein.

(a) Competitive range and discussions. If discussions are conducted, only offerors in the competitive range will be invited to participate. The competitive range may be narrowed to maintain an efficient competition among the most highly rated proposals (see 10 U.S.C. 3303; 41 U.S.C. 3703). Written notice of exclusion will be provided per RFO 15.204. The competitive range may be reestablished, if necessary, to maintain efficiency.

(b) Options. The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. The Government may determine that an offer is unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate the Government to exercise the option (s).

(c) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer's specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.

(End of provision)

File details come from the government source that posted it. Updated .