TOA CERCLA Price Form Amendment 04.pdf
PDF 113 KB Posted
- Solicitation number
- 20312361
About this file
This is a Price Proposal Form for a U.S. Coast Guard project at Base Seattle, Washington, involving a Comprehensive Environmental Response Compensation and Liability Act (CERCLA) cleanup and waterfront recapitalization (Project #20312361). The pricing document includes multiple base items with detailed unit pricing for various construction and environmental remediation activities, such as demolition of Building 3 and Pier 36B, pier utilities and mooring upgrades, small boat floating dock replacement, dredging, and sediment disposal.
The proposal breaks down costs into Base Item #1 for construction activities and Base Item #2 with multiple sub-items (2A-2G) for dredging and environmental treatment, including granular activated carbon treatment, engineered powdered activated carbon treatment, in-situ treatment cover material, residuals management, armor stone, and filter stone. The document emphasizes that betterments will not be accepted and all innovation must be included in the total price. This project is specifically designated for National Multiple Award Construction Contract III (NMACC III) Pool 1 awardees and supports the homeporting of new U.S. Coast Guard Polar Security Cutters.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACTOR PROPOSED CYBER/IT-RELATED SOLUTIONS FORM
Identify all cyber/IT-related hardware, software and/or services that are included as part of the proposal to meet the government’s requirement to store or process Coast Guard data or connect to Coast Guard networks or other assets by completing the table below. If none are included, check the box following the table.
Product Name or Service
Manufacturer or Company
Version (if any)
Release
Quantity
Brief Description
Cost (if not
FFP
contractor is responsible for also ensuring inclusion in the cost proposal)
Recurring or Non- Recurring?
If recurring, state frequency
No related hardware, software, or services are required to store or process Coast Guard Data or connect to Coast Guard networks or other assets.
PRICE PROPOSAL FORM
PROJECT #20312361
Base Seattle CERCLA PSC Homeport PH1A
TOA# 70Z025R43000001
IMPORTANT NOTE: Contractors who include language in their proposals containing conditions may be rejected.
Base Item #1: Construction activities at Base Seattle, Washington to include; Demolition of Bldg. 3 and Pier 36B. Pier 37 Utilities and mooring upgrades, Small Boat Floating Dock removal and replacement, and all other associated civil, utilities and site work.
Total Base Item #1: $______________________
Base Item #2: Dredging and sediment disposal IAW with CERCLA of Slip 36. Estimated dredge quantity. Quantities in Base Item #2 are estimated quantities and are subject to the procedures in FAR 52.211-18- Variation in Estimated Quantity (April 1984).
* For all these unit price items, the unit price provided shall include the fully burdened cost to supply, place, haul, dispose of, etc., the given material listed. For the dredging item, the unit price shall include the fully burdened cost to perform the dredging task from start to finish.
Base Item 2A: Dredging Costs $____________ per CY x 83,500 CY = $_______________________
Base Item 2B: Granular Activated Carbon and Sand In-Situ Treatment
$____________ per CY x 780 CY = $_______________________
Base Item 2C: Engineered Powdered Activated Carbon (AquaGate+PAC or similar) In-Situ Treatment
$____________ per CY x 130 CY = $_______________________
Base Item 2D: In-Situ Treatment Cover Material
$____________ per CY x 1,280 CY = $_______________________
Base Item 2E: Residuals Management Cover
$____________ per CY x 8,360 CY = $_______________________
Base Item 2F: Armor Stone: [Stone sizes and quantities as shown on the drawings and specifications.
This unit pricing shall include the fully burdened cost to supply and place the material].
$____________ per Short Ton x 13,343 Short Tons = $_______________________
Base Item 2G: Filter Stone (All Types): [Stone sizes and quantities as shown on the drawings and specifications. This unit pricing shall include the fully burdened cost to supply and place the material].
$____________ per Short Ton x 6,130 Sort Tons = $_______________________
Total Base Item #2 (2A – 2G): $______________________
The TOTAL BASE ITEMS shall be deemed to include all costs required for the specified work to be completed in accordance with the plans and specifications.
TOTAL ALL BASE ITEMS (Base Items 1, and 2 (2A - 2G) $__________________
BETTERMENTS WILL NOT BE ACCEPTED. ALL INNOVATION AND CREATIVITY IN
THE TECHNICAL APPROACH SHALL BE INCLUDED AS PART OF THE TOTAL
PRICE.
AMENDMENTS ACKNOWLEDGED:
Amendment No.
Date Amendment No.
Date
Offeror:
Address:
Phone:
Fax:
Email:
Name:
Signed:
Date:
File details come from the government source that posted it. Updated .