About this file

This document is an Amendment (Amendment 07) to a federal solicitation for the National Multiple Award Construction Contract III (NMACC III) Pool One project. The amendment extends the proposal submission deadlines, moving the non-price proposal due date from April 22, 2025, to April 29, 2025, and the price proposal due date from April 30, 2025, to May 7, 2025, both at 4:00 PM PST.

The amendment also introduces new Homeland Security Acquisition Regulation (HSAR) requirements related to contract terminations for contracts over $1,000,000, specifically for the United States Coast Guard (USCG). It includes provisions for contractors to maintain work products for at least one year after notification of potential contract termination and establishes a potential civil penalty of up to $25,000 per day for non-compliance. Additionally, the amendment updates the response to a vendor question about material price protection, clarifying that FAR Clause 52.229-3 allows recovery of tariffs imposed after contract award under certain conditions.

View the file

Other files

File Type Posted
Amendment 09_Drawing CN101-CN102 Markups_Revised Dredge Placement Areas.pdf PDF
Amendment 09_General Wage Decision WA20250125 14Mar2025.pdf PDF
Amendment 09 5.2.25.pdf PDF
Amendment 09_Drawing AB200 Markup_for PPI 110.pdf PDF
Amendment 09_Debris Survey Technical Memo_PPI 197.pdf PDF
Amendment 10_5.6.25.pdf PDF
70Z05025R43000001_Amendment 08 4.25.25.pdf PDF
70Z05025R43000001_06_ 06 4.14.25.pdf PDF
NMACC Site Visit_27Feb2025 (Final).pdf PDF
FPAS Rated Order Letter to Contractors_Amendment 04.pdf PDF
Amendment 03FPAS-SILC-NMACC III Electrical Equipment 2025_03_11_sign.pdf PDF
Amendment 03Base Seattle Boat Haulout - As Builts.pdf PDF
2025.02_BA_USCG_BaseSeattle.pdf PDF
SF 30 4.2.2025 Amendment 04.pdf PDF
Continuation Sheets_Amendment 4.pdf PDF
Amendment 03 Seattle PH1A Continuation Sheets 03.pdf PDF
Amendment 2 13Mar25.pdf PDF
TOA CERCLA Price Form Amendment 04.pdf PDF
USCG Base Seattle IDP Flow Chart.pdf PDF
Amendment 2 Continuation Pages.pdf PDF
Amendment 03SF 30 3.26.25.pdf PDF
FPAS-Electrical Equipment 2025_03_11_sign Amendment 04.pdf PDF
Amendment 2 Cover Page.pdf PDF
Amendment 05 4.4.25.pdf PDF
Base Seattle CERCLA PSC Homeport PH1A - Pre Proposal Site Visit - Attendees.pdf PDF
Amendment 01 3.5.25.pdf PDF
TOA CERCLA 2.27.25.pdf PDF
FAR Class Deviation 25-02 Waiver of PLA Requirements.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

The purpose of this amendment is to extend the due date for non-price proposals from April 22, 2025 at 4:00 PM (PST) to April 29, 2025 at 4:00 PM (PST) and to extend the due date for price proposals from April 30, 2025 at 4:00 PM (PST) to May 7, 2025 at 4:00 PM (PST). This amendment also adds HSAR Subpart 3049.9001 Policy, HSAR Subpart 3049.9002 Contract Clause and changes the response for PPI 42. See the continuation page(s). All other terms and conditions remain the same.

USCG SILC FD&CC Det Seattle 915 2nd Ave, Room 2664 Seattle, WA 98174

70Z05025R43000001

2031236104/17/2025

02/27/2025

1 3

70Z05025R43000001

SOLICITATION NO. 70Z05025R43000001 IS AMENDED AS FOLLOWS:

Enclosed documents: NA

Task Order Announcement

INSERT HSAR 3049.9001 Policy (USCG) and HSAR 3049.9002 Contract Clause (USCG):

HSAR 3049.9001 Policy (USCG).

(a) Applicability. This section implements 14 U.S.C. 1155 and provides the policy for the USCG to use for contract terminations. This contract termination policy applies to USCG contract terminations, including contracts for commercial items, with a total value of more than $1,000,000.

(b) Notification. Before terminating a contract with a total value of more than $1,000,000, the Commandant of the Coast Guard shall notify the contractor and the contractor shall be required to maintain all work product related to the contract until the earlier of—

(1) not less than 1 year after the date of the notification; or

(2) the date the Commandant notifies the vendor that maintenance of such work product is no longer required.

(c) Work Product Defined. The term “work product”—

(1) Means tangible and intangible items and information produced or possessed as a result of a contract referred to in subsection (b); and

(2) Includes—

(i) Any completed end items;

(ii) Any uncompleted end items; and

(iii) Any property in the Contractor's possession in which the United States Government has an interest.

(d) Penalty. A Contractor that fails to maintain work product as required under subsection (b) is liable to the United States for a civil penalty of not more than $25,000 for each day on which such work product is unavailable.

(e) Requirement. The Contractor shall insert the substance of this clause in contracts and subcontracts, including contracts and for commercial items, with a total value of more than $1,000,000.

HSAR 3049.9002 Contract Clause (USCG).

USCG contracting officers shall insert the clause at 3052.249-90, Contract Termination (USCG), in all solicitations and contracts, including contracts for commercial items, with a total value of more than $1,000,000.

RFP, Drawings

REMOVE: NA

INSERT: NA

70Z05025R43000001

Specification Section

DELETE: NA

INSERT: NA

THE FOLLOWING QUESTIONS WERE RECEIVED IN RESPONSE TO THE

SOLICITATION:

PPI 42: With the current chaos surrounding tariffs, we are having a difficult time getting pricing from vendors. Most vendors are only willing to hold their pricing for 7 days. Given the length of time that it will take the Coast Guard to evaluate offers, we request that some sort of material price index language or similar protection be included in this contract. In the absence of some sort of material price protection, contractors will have no choice but to include a huge material price escalation factor in their bids. Please advise.

Delete PPI 42 answer: We recognize the existence of price instability, and we appreciate your request to insert specific language and terminology to define how material prices are adjusted based on market and economic prices/indices. Unfortunately, the ongoing instability surrounding tariffs does not impact this firm fixed price project, so we ask that Offerors’ initial proposals contain the Offeror’s best terms from a price (and technical standpoint).

Replace PPI 42 answer: FAR Clause 52.229-3, which is included in your Base Contract for National Multiple Award Construction Contract (NMACC III), allows recovery of tariffs imposed after contract award at 52.229-3(c) “The contract price shall be increased by the amount of any after-imposed Federal tax, provided the Contractor warrants in writing that no amount for such newly imposed Federal excise tax or duty or rate increase was included in the contract price, as a contingency reserve or otherwise.” A tariff qualifies as an “after-imposed” Federal tax, if tariff is instated after the award date of the contract. Tariffs imposed after proposal submission, but before contract award, will not be considered newly imposed under FAR 52.229-3.