This document is Amendment 05 for the Slip 36 Clean-Up and Waterfront Recapitalization project at USCG Base Seattle. The amendment provides Section 01 50 00 - Temporary Construction Facilities and Controls, which outlines detailed requirements for contractor temporary facilities, safety systems, and site management during the project. Key requirements include providing two separate trailers for government personnel with specific amenities such as heating/cooling, office equipment, furniture, safety gear, reference materials, and technological resources like computers, internet, and communication systems.
The section specifies extensive details for the trailers, including minimum space requirements, electrical outlets, plumbing facilities, storage containers, parking spaces, and furnishings. The contractor must maintain the facilities in good condition, ensure proper anchoring, provide safety equipment (25 hard hats, 50 safety glasses, safety vests, gloves), and restore the site to its original condition upon project completion. The document emphasizes strict protocols for site security, weather protection, communications, fencing, traffic control, and overall site management throughout the construction process.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
The purpose of this amendment is to provide an attachment (01 50 00 - Temporary Construction Facilities and Controls) mistakenly excluded in Amendment 04. All other terms and conditions remain unchanged. See continuation pages.
USCG SILC FD&CC Det Seattle 915 2nd Ave, Room 2664 Seattle, WA 98174
70Z05025R43000001
2031236104/04/2025
02/27/2025
1 917
70Z05025R4300000
SOLICITATION NO. 70Z05025R43000001 IS AMENDED AS FOLLOWS:
Enclosed documents:
Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
Task Order Announcement
NA
RFP, Drawings
REMOVE: NA
INSERT: NA
Specification Section
DELETE: NA
INSERT: NA
THE FOLLOWING QUESTIONS WERE RECEIVED IN RESPONSE TO THE
SOLICITATION:
PPI #217. Continuation Sheet 2 makes reference to some updated specifications and drawings, but we did not see where these were included with the amendment. Can you please send these updated documents?
Answer: See enclosed document Section 01 50 00 TEMPORARY CONSTRUCTION
FACILITIES AND CONTROLS
END
Section 01 50 00
TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C511 (2017; R 2021) Reduced-Pressure Principle Backflow Prevention Assembly
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2023; ERTA 7 2023; TIA 23-15) National Electrical Code
NFPA 241 (2022) Standard for Safeguarding Construction, Alteration, and Demolition Operations
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Health Requirements Manual
U.S. FEDERAL HIGHWAY ADMINISTRATION (FHWA)
MUTCD (2009; Rev 2012) Manual on Uniform Traffic Control Devices
1.2 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for information only.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Construction Site Plan; G
Traffic Control Plan; G
Haul Road Plan; G
Contractor-Owned And Operated Radio Telecommunications; G
SD-03 Product Data
Backflow Preventers; G
SD-06 Test Reports
Backflow Preventer Tests
SD-07 Certificates
Backflow Tester Certification
Backflow Preventers Certificate of Full Approval
1.3 CONSTRUCTION SITE PLAN
Prior to the start of work, submit for Government approval a site plan showing the locations and dimensions of temporary facilities (including layouts and details,) equipment and material storage areas (onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation. Identify any areas which may have to be graveled to prevent the tracking of mud. Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.
The drawings include potential laydown areas. Contractor shall confirm availability of these areas with the Contracting Officer or their designated representative.
1.4 BACKFLOW PREVENTERS CERTIFICATE
1.4.1 Backflow Tester Certificate
Prior to testing, submit to the Contracting Officer or their designated representative certification issued by the State or local regulatory agency attesting that the backflow tester has successfully completed a certification course sponsored by the regulatory agency. Tester must not be affiliated with a company participating in other phases of this Contract.
1.4.2 Backflow Prevention Training Certificate
Submit a certificate recognized by the State or local authority that states the Contractor has completed at least 10 hours of training in backflow preventer installations. The certificate must be current.
1.5 TELECOMMUNICATIONS DURING CONSTRUCTION
1.5.1 Temporary IP Networks
Temporary contractor-installed IP networks may be used during construction. When used, temporary contractor-installed IP networks must meet the following requirements:
1.5.1.1 Network Boundaries and Connections
The network must not extend outside the project site and must not connect to any IP network other than IP networks provided under this project or Government furnished IP networks provided for this purpose. Any and all network access from outside the project site is prohibited.
1.5.2 Government Access to Network
Government personnel, as defined, prescribed, and identified by the Contracting Officer or their designated representative, must be allowed to have complete and immediate access to the network at any time in order to verify compliance with this specification. Or if there is a Government agency that's responsible, identify that agency.
1.5.3 Temporary Wireless IP Networks
In addition to the other requirements on temporary IP networks, temporary wireless IP (WiFi) networks must not interfere with existing wireless network and must use WPA2 security. Network names (SSID) for wireless networks must be changed from their default values.
1.5.4 Passwords and Passphrases
The passwords and passphrases for all network devices and network access must be changed from their default values. Passwords must be a minimum of eight characters with a minimum of one uppercase letter, one lowercase letter, one number and one special character.
PART 2 PRODUCTS
2.1 TEMPORARY SIGNAGE
2.1.1 Bulletin Board
Prior to the commencement of work activities, provide a clear weatherproof covered bulletin board not less than 36 by 48 inches in size for displaying the Equal Employment Opportunity poster, a copy of the wage decision contained in the Contract, Wage Rate Information poster, Safety and Health Information as required by EM 385-1-1 and other information approved by the Contracting Officer. Coordinate requirements herein with 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS. Locate the bulletin board at the project site in a conspicuous place easily accessible to all employees, and in a location as approved by the Contracting Officer or their designated representative.
2.1.2 Project Identification Signs
Provide a sign as shown on the drawing attached to this specification, with graphics painted by a professional sign painter. Coat all exposed surfaces of supports, framing, and surface material with at least one coat of primer and one coat of exterior paint. Coordinate sign location with the Contracting Officer or their designated representative.
2.1.3 Warning Signs
Post temporary signs, tags, and labels to give workers and the public adequate warning and caution of construction hazards according to the EM 385-1-1. Attach signs to the perimeter fencing every 150 feet warning the public of the presence of construction hazards. Signs must require unauthorized persons to keep out of the construction site. Correct the data required by safety signs daily. Post signs at all points of entry designating the construction site as a hard hat area.
2.2 TEMPORARY TRAFFIC CONTROL
2.2.1 Haul Roads
Construct access and haul roads necessary for proper prosecution of the work under this Contract in accordance with EM 385-1-1. Construct with suitable grades and widths; avoid sharp curves, blind corners, and dangerous cross traffic. Submit haul road plan for approval. Provide necessary lighting, signs, barricades, and distinctive markings for the safe movement of traffic. The method of dust control, although optional, must be adequate to ensure safe operation at all times. Location, grade, width, and alignment of construction and haul roads are subject to approval by the Contracting Officer or their designated representative. Lighting must be adequate to assure full and clear visibility for full width of haul road and work areas during any night work operations.
2.2.2 Barricades
Erect and maintain temporary barricades to limit public access to hazardous areas. Barricades are required whenever safe public access to paved areas such as roads, parking areas or sidewalks is prevented by construction activities or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic. Securely place barricades clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night.
2.3 FENCING
Provide fencing along the construction site and at all open excavations and tunnels to control access by unauthorized personnel. Safety fencing must be highly visible to be seen by pedestrians and vehicular traffic. All fencing must meet the requirements of EM 385-1-1. Remove the fence upon completion and acceptance of the work.
2.3.1 Polyethylene Mesh Safety Fencing
Temporary safety fencing must be a high visibility orange colored, high density polyethylene grid, a minimum of 48 inches high and maximum mesh size of 2 inches. Fencing must extend from the grade to a minimum of 48 inches above the grade and be tightly secured to T-posts spaced as necessary to maintain a rigid and taut fence. Fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection.
2.3.2 Chain Link Panel Fencing
Temporary panel fencing must be galvanized steel chain link panels 6 feet high. Multiple fencing panels may be linked together at the bases to form long spans as needed. Each panel base must be weighted down using sand bags or other suitable materials in order for the fencing to withstand anticipated winds while remaining upright. Fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection.
2.3.3 Post-Driven Chain Link Fencing
Temporary post-driven fencing must be galvanized chain link fencing 6 feet high supported by and tightly secured to, galvanized steel posts driven below grade. Fence posts must be located on minimum 10 foot centers.
Posts may be set in various surfaces such as sand, soil, asphalt or concrete as necessary. Chain link fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection. Completely remove fencing and posts at the completion of construction and restore surfaces disturbed or damaged to its original condition. Locate and identify underground utilities prior to setting fence posts. Equip fence with a lockable gate. Gate must remain locked when construction personnel are not present.
2.4 TEMPORARY WIRING
Provide temporary wiring in accordance with EM 385-1-1, NFPA 241 and NFPA 70.
Include monthly inspection and testing of all equipment and apparatus.
2.5 BACKFLOW PREVENTERS
Certificate of Full Approval from FCCCHR List, University of Southern California, attesting that the design, size and make of each backflow preventer has satisfactorily passed the complete sequence of performance testing and evaluation for the respective level of approval. Certificate of Provisional Approval is not acceptable.
Reduced pressure principle type conforming to the applicable requirements AWWA C511. Provide backflow preventers complete with 150 pound flanged bronze or brass mounted gate valve and strainer and bronze internal parts.
PART 3 EXECUTION
3.1 EMPLOYEE PARKING
Construction Contract employees must park privately owned vehicles in an area designated by the Contracting Officer or their designated representative. Employee parking must not interfere with existing and established parking requirements of the Government installation.
3.2 AVAILABILITY AND USE OF UTILITY SERVICES
3.2.1 Temporary Utilities
Provide temporary utilities required for construction. Materials may be new or used, must be adequate for the required usage, not create unsafe conditions, and not violate applicable codes and standards.
3.2.2 Payment for Utility Services
a. The Government will make all reasonably required utilities available from existing outlets and supplies, as specified in the Contract. Water and electricity are available for the Contractor’s use at no additional cost. Carefully conserve utilities furnished.
b. The point at which the Government will deliver such utilities or services and the quantity available will be coordinated with the Base Facilities Engineering Department. Make connections, including providing backflow-preventing devices on connections to domestic water lines, providing transformers, and make disconnections. Under no circumstances will taps to base fire hydrants be allowed for obtaining domestic water.
3.2.3 Contractor-Owned and Operated Radio Telecommunications
A transmitter/receiver and antenna may be erected upon approval by the Contracting Officer or their designated representative. Submit for approval, 30 calendar days prior to the use of the equipment, the type of radio equipment power and band width of the equipment.
3.2.4 Sanitation
Provide and maintain within the construction area minimum field-type sanitary facilities in accordance with EM 385-1-1. Locate the facilities behind the construction fence or out of the public view. Clean units and empty wastes at least once a week or more frequently into a municipal, district, or station sanitary sewage system, or remove waste to a commercial facility. Obtain approval from the system owner prior to discharge into a municipal, district, or commercial sanitary sewer system.
Penalties or fines associated with improper discharge will be the responsibility of the Contractor. Coordinate with the Contracting Officer or their designated representative and follow station regulations and procedures when discharging into the station sanitary sewer system.
Maintain these conveniences at all times. Include provisions for pest control and elimination of odors. Government toilet facilities will not be available to Contractor's personnel.
3.2.5 Telephone
Make arrangements and pay all costs for telephone facilities desired.
3.2.6 Fire Protection
Provide temporary fire protection equipment for the protection of personnel and property during construction. Remove debris and flammable materials daily to minimize potential hazards.
3.3 TRAFFIC PROVISIONS
3.3.1 Maintenance of Traffic
a. Conduct operations in a manner that will not close a thoroughfare or interfere with traffic on railways or highways except with written permission of the Contracting Officer or their designated representative at least 15 calendar days prior to the proposed modification date and provide a Traffic Control Plan for Government approval detailing the proposed controls to traffic movement for approval. The plan must be in accordance with State and local regulations and the MUTCD, Part VI. Make all notifications and obtain all permits required for modification to traffic movements outside Station's jurisdiction. Contractor may move oversized and slow-moving vehicles to the worksite provided requirements of the highway authority have been met.
b. Conduct work so as to minimize obstruction of traffic, and maintain traffic on at least half of the roadway width at all times. Obtain approval from the Contracting Officer or their designated representative prior to starting any activity that will obstruct traffic.
c. Provide, erect, and maintain, at Contractor's expense, lights, barriers, signals, passageways, detours, Life Safety Signage, overhead protection, and other items that may be required by the authority having jurisdiction.
d. Provide cones, signs, barricades, lights, or other traffic control devices and personnel required to control traffic. Do not use foil-backed material for temporary pavement marking because of its potential to conduct electricity during accidents involving downed power lines.
3.3.2 Protection of Traffic
Maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer or their designated representative. Measures for the protection and diversion of traffic, including the provision of watchmen and flagmen, erection of barricades, placing of lights around and in front of equipment the work, and the erection and maintenance of adequate warning, danger, and direction signs, will be as required by the State and local authorities having jurisdiction. Provide self-illuminated (lighted) barricades during hours of darkness. All personnel working in roadways will wear brightly-colored vests or other high visibility apparel in accordance with EM 385-1-1. Protect the traveling public from damage to person and property. Minimize the interference with public traffic on roads selected for hauling material to and from the site. Investigate the adequacy of existing roads and their allowable load limit. Contractor is responsible for the repair of damage to roads caused by construction operations. The main roadways that provide access to all areas of USCG property shall be maintained at all times. If construction activities require the closure of any existing roadways, request approval from the Contracting Officer or their designated representative at least 15 days prior to the proposed closure.
3.3.3 Rush Hour Restrictions
Do not interfere with the peak traffic flows preceding and during normal operations as stated in Section 01 14 00 WORK RESTRICTIONS.
3.3.4 Dust Control
Dust control methods and procedures must be approved by the Contracting Officer or their designated representative. Coordinate dust control methods with 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS.
3.4 REDUCED PRESSURE BACKFLOW PREVENTERS
Provide an approved reduced pressure backflow prevention assembly at each location where the Contractor taps into the Government potable water supply.
Perform backflow preventer tests using test equipment, procedures, and certification forms conforming to those outlined in the latest edition of the Manual of Cross-Connection Control published by the FCCCHR Manual.
Test and tag each reduced pressure backflow preventer upon initial installation (prior to continued water use) and quarterly thereafter. Tag must contain the following information: make, model, serial number, dates of tests, results, maintenance performed, and signature of tester. Record test results on certification forms conforming to requirements cited earlier in this paragraph.
3.5 CONTRACTOR'S TEMPORARY FACILITIES
Contractor is responsible for security of their property. Provide adequate outside security lighting at the temporary facilities. Trailers must be anchored to resist high winds and meet applicable state or local standards for anchoring mobile trailers. Coordinate anchoring with EM 385-1-1. The Contract Clause entitled "FAR 52.236-10, Operations and Storage Areas" and the following apply:
Slip 36 Clean-Up and Waterfront Recap PH1A-IFB USCG Base Seattle
Project No. 20312361 January 24, 2025
SECTION 35 31 19 Page 8
3.5.1 Administrative Field Offices
Provide and maintain administrative field office facilities within the construction area at the designated site. Government office and warehouse facilities will not be available to the Contractor's personnel.
3.5.2 Temporary Contracting Officer's Representative/Construction Inspector Office and Equipment
a. Provide and maintain throughout the contract, for the exclusive use of the Government, two freestanding and separate trailers. The trailers shall be weather tight and provided with heating and cooling to maintain up to 70 degrees F in winter and 68 degrees F in summer. Place trailers where directed by the COR within your lay down area.
b. A weather-tight building, 23’-6” feet wide, minimum 1,440 square feet, with a heating/air-conditioning system capable of maintaining a temperature of 68 degrees. Two entrance doors, with a standard handset and lock and dead bolt, with two keys for each lock. One ADA ramp to one of the trailer doors, a set of stairs to the other. Skirting installed around the air gap between the bottom of trailer and the ground, painted to match the trailer color. This office trailer is to be used by the Contracting Officer's Representative/Construction Inspector and their guests.
c. A second weather-tight building, 9’-6” feet wide, minimum 160 square feet, with a heating/air-conditioning system capable of maintaining a temperature of 68 degrees. One entrance door, with a standard handset and lock and dead bolt, with two keys for each lock. One ADA ramp to the trailer door. This office is to be used by the EPA Inspector.
a. Example Trailer Floor Plans: These included trailer plans for an example of the desired layout with walls and doors included. Contractor to submit proposed trailer sizes and floor plan layout for government review and approval prior to purchase, ^Example trailer floor plan for larger trailer: submit full floor plan with fewer wall options to government for review and approval prior to purchasing.
Project No. 20312361
SECTION 35 31 19 Page 9
^Example trailer floor plan for smaller trailer: submit full floor plan options to government for review and approval prior to purchasing.
d. [5] parking spaces for the government personnel, labeled with signage “Parking for US Coast Guard Project Team.”
e. Sample storage container of 13 Cubic Feet, capable of storing samples to 40 degrees and minimum 1 square feet capable of storing samples to 30 degrees.
f. Office area for the COR of not less than 120 square feet,
g. Office area for the construction inspector, no less than 120 square feet,
h. Office area for the second inspector, no less than 120 square feet,
i. One conference table area 12-ft long by 5-ft wide, along with 10 folding conference chairs,
j. Six sliding windows, minimum six square feet each. Venetian blinds on all windows in the trailer.
k. Install 40 LF of 14-inch wide wall mounted shelving where identified by COR & COR,
l. Lighting providing a minimum illumination of 60 foot candles in each room.
m. Duplex electrical receptacles: four per office, eight for general use, one under the conference table (15-amp, 120 VAC),
n. Provide and install [1] self-contained indoor plumbing facility;
sink, toilet, hot and cold water. Provide necessary maintenance to ensure uninterrupted usage of plumbing facilities. This includes providing pumping services for trailer holding tanks on a weekly schedule so that the tank is never too full to be used.
Service schedule should be frequent enough so as to never exceed 50% of the tank’s capacity based on 4-person daily use. This also includes toilet paper and seat covers, 3 rolls of 2-ply toilet paper per week, 1 package of seat covers per week. Provide soap dispenser with weekly soap refills. Also provide minimum 100CFM bathroom exhaust fan, also capable of minimum of 40 CFM of whole house ventilation. Also provide and install a separate kitchen sink, minimum of: 22” wide, 12” long, 10” deep. Provide this kitchen sink integrated into a countertop, countertop minimum of 24” deep by 6-ft long, minimum 1” thick. Ensure at least two electrical outlets are available above the installed countertop.
Provide open shelving below this countertop, two rows of shelving- heights to be submitted to government for review and approval.
Project No. 20312361
SECTION 35 31 19 Page 10
o. A hot and cold bottled water dispenser, capable of dispensing water at 60 degrees or 150 degrees on demand. Provide five gallons of bottled water per week.
If a trailer-type mobile office is used, securely anchor the trailer to the ground at all four corners to guard against movement during high winds.
Coordinate requirements for proper anchoring with EM 385-1-1.
3.5.2.2 Sweep out and mop the office trailer every week minimum, coordinate cleaning with Contracting officer or their designated representative.
3.5.2.3 Contracting Officer's Representative/Construction Inspector Office Furnishings
3.5.2.3.1 Provide furnishings for Contracting Officer's
Representative/Construction Inspector office as follows:
a. One 3 by 6 foot plan table, with 30-inch adjustable, high back, upholstered drafting stool with footrest and rollers,
b. Trailers shall be no older than 3 years from date of manufacture,
c. Three motorized desks capable of raising and lowering to accommodate seated and standing work positions,
d. Three rolling, well cushioned office chairs with upholstered arm pads, adjustable lumbar support, tilt options, adjustable height, seat depth, and adjustable back support,
e. Four waste baskets, one large paper recycling bin,
f. One plan rack with capacity for 10 sets of full-size plans,
g. Two file cabinets, legal size-with four drawers,
h. One 2 by 6 foot table for scanner, fax and copier,
i. A hot and cold bottled water dispenser, capable of dispensing water at 60 degrees or 150 degrees on demand. Provide five gallons of bottled water per week.
j. Deliver to the Coast Guard—prior to the Pre-construction Meeting— two new laptop style computers with the appropriate USB-C docking stations and cords to extend the display to external monitors.
Computers shall contain the applicable software to run, display and edit the Project Schedule and to transfer the schedule by e-mail. The computers will remain in the possession of the Coast Guard until Final Acceptance and will be returned to you at that time. Laptops will have an integrated smart card reader slot.
Computers will have these minimum performance specifications: fast processors such as an Intel Core i7 or i9, or an AMD Ryzen 7 or 9, 32GB of RAM, SSD hard drives, advanced graphics cards such as an NVIDIA GeForce RTX or AMD Radeon RX, 13-inch screen with a high-definition display with a minimum resolution of 1980x1080.
k. Microsoft office suite loaded onto both computers (Outlook, Excel, Word, PowerPoint, teams, OneNote, planner), Project No. 20312361
SECTION 35 31 19 Page 11
l. The following software loaded onto both computers: Adobe Acrobat Pro, Bluebeam Revu [latest version], MS Project, Project scheduling software used to create the project schedule,
m. Provide and pay for a 5G wireless hotspot, unlimited data use for the trailer,
n. Four 24-inch LED curved computer monitors with the latest high-definition display capabilities and the associated cords to connect to the laptop docking stations,
o. Two Bluetooth keyboards and two Bluetooth computer mice,
p. Provide and pay for one high-speed internet connection, minimum of 500 mbps download speeds and 250 mbps upload speed, with a modem / router capable of connecting up to 6 dedicated drops at a time, capable of providing one wireless network, also capable of providing the minimum Coast Guard security requirements,
q. Two 500GB flash drives,
r. One video conferencing camera system with the following baseline requirements: camera output resolution 1080p HD, field of view 360-degrees, video pickup radius up to 10-ft, 2 integrated microphones with an audio pickup radius of 18-ft, built-in speaker(s) for 360-degree coverage and clear in-room sound, speaker output level 80 db,
s. TV screen mounted to the wall [where directed by the government], screen shall be LED, high definition with 4K minimum resolution, minimum of 65” in size. Provide and install all the necessary adapter cables to integrate this screen with the video conferencing system mentioned above.
t. One 12-pot drip coffee maker,
u. A separate self-feeding copier/scanner/printer machine. Provide a machine capable of reduction and enlargement, printing/copying/scanning capabilities up to 11 by 17 inches.
Printer should also be capable of wireless printing. Provide maintenance and service as required with one-day service time (downtime) maximum. Provide minimum of 8 reams of 8-1/2”x11 paper and 3 reams of 11x17” paper per month. Provide constant supply of toner cartridges for the duration of the project.
v. [Qty 3] 3 by 5 foot white board with three packets of colored pens and three erasers (mounted per Contracting Officer or their Designated Representative/Construction Inspector). [Qty 2] Whiteboards with a monthly calendar template. All white boards shall have pen trays attached.
w. Large sign posted in trailer that reads "ALL OFFICE FURNISHINGS AND
EQUIPMENT FOR EXCLUSIVE USE BY THE GOVERNMENT"
x. Three four shelf bookcases, 3 by 4 feet.
Project No. 20312361
SECTION 35 31 19 Page 12
3.5.2.4 References & Safety Equipment
3.5.2.4.1 Provide the following latest edition items for the exclusive use of the Government within 60 days of Contract Award.
a. International Building Code with Local City and State Amendments
b. International Plumbing Code with Local City and State Amendments
c. International Electrical Code with Local City and State Amendments
d. International Mechanical Code with Local City and State Amendments
e. ACI Manual of Concrete Practice Part 3
f. AISC Manual of Steel Construction (ASD)
g. ASTM Standards in Building Codes
h. Gypsum Construction Handbook (US Gypsum Company)
i. National Electrical Code NFPA-70
j. National Electrical Code Handbook
k. SMACNA Architectural Sheet Metal Manual
l. US Corps of Engineers, Engineering Manual 385-1-1
m. OSHA - Labor 29 Part 1926
3.5.2.4.2 Provide the following safety equipment: 25 adjustable hard hats with a fluorescent pink stripe painted down the middle [painted by the contractor], 50 pairs of safety glasses, and 20 safety vests with surveyors pocket in the back, 20 medium safety gloves, 50 large safety gloves, 40 XL safety gloves, climbing harnesses [if any will be needed for the COR or Construction Inspector, sizes to be specified by the government, foul weather class 3 hi-visibility raincoats with hoods, sizes to be specified by the government. Submit to the government storage containers to hold all these items, government review and approval required before purchase.
3.5.3 Storage Areas
Construct a temporary 6 foot high chain link fence around trailers and materials. Include plastic strip inserts, colored green, so that visibility through the fence is obstructed. Fence posts may be driven, in lieu of concrete bases, where soil conditions permit. Do not place or store trailers, materials, or equipment outside the fenced area unless such trailers, materials, or equipment are assigned a separate and distinct storage area by the Contracting Officer or their designated representative away from the vicinity of the construction site but within the installation boundaries. Trailers, equipment, or materials must not be open to public view with the exception of those items which are in support of ongoing work on the current day. Do not stockpile materials outside the fence in preparation for the next day's work. Park mobile equipment, such as tractors, wheeled lifting equipment cranes, trucks, and like equipment within the fenced area at the end of each work day.
Keep fencing in a state of good repair and proper alignment. If the Contractor elects to traverse grassed or unpaved areas which are not established roadways with construction equipment or other vehicles, cover
Project No. 20312361
SECTION 35 31 19 Page 13 the grassed or unpaved areas with a layer of gravel as necessary to prevent rutting and the tracking of mud onto paved or established roadways; gravel gradation must be at the Contractor's discretion. Mow and maintain grass located within the boundaries of the construction site for the duration of the project. Grass and vegetation along fences, structures, under trailers, and in areas not accessible to mowers must be edged or trimmed neatly.
3.5.4 Supplemental Storage Area
Upon request, and pending availability, the Contracting Officer or their designated representative may designate another or supplemental area for the use and storage of trailers, equipment, and materials. This area may not be in close proximity of the construction site but will be within the installation boundaries. Maintain the area in a clean and orderly fashion and secured if needed to protect supplies and equipment. Utilities will not be provided to this area by the Government.
3.5.5 Appearance of Trailers
a. Trailers must be roadworthy and comply with all appropriate state and local vehicle requirements. Trailers which are rusted, have peeling paint or are otherwise in need of repair will not be allowed on Installation property. Trailers must present a clean and neat exterior appearance and be in a state of good repair.
b. Maintain the temporary facilities. Failure to do so will be sufficient reason to require their removal at the Contractor's expense.
3.5.6 Trailers or Storage Buildings
a. Trailers or storage buildings will be permitted, where space is available, subject to the approval of the Contracting Officer or their designated representative.
b. Mount a sign not smaller than 24 by 24 inches on the trailer or building that shows the company name, business phone number, emergency phone number and conforms to the following requirements and sketch:
Graphic panel Aluminum, painted blue
Copy Screen painted or vinyl die-cut, white
Typeface Universe 65 u/lc
See Sketch No. 01500 (graphic).
Project No. 20312361
SECTION 35 31 19 Page 14
3.5.7 Safety Systems
Protect the integrity of all installed safety systems or personnel safety devices. Obtain prior approval from the Contracting Officer or their designated representative if entrance into systems serving safety devices is required. If it is temporarily necessary to remove or disable personnel safety devices in order to accomplish Contract requirements, provide alternative means of protection prior to removing or disabling any permanently installed safety devices or equipment and obtain approval from the Contracting Officer or their designated representative.
3.5.8 Weather Protection of Temporary Facilities and Stored Materials
Take necessary precautions to ensure that roof openings and other critical openings in the building are monitored carefully. Take immediate actions required to seal off such openings when rain or other detrimental weather is imminent, and at the end of each workday. Ensure that the openings are completely sealed off to protect materials and equipment in the building from damage.
3.5.8.1 Building and Site Storm Protection
When a warning of gale force winds is issued, take precautions to minimize danger to persons, and protect the work and nearby Government property.
Precautions must include, but are not limited to, closing openings;
removing loose materials, tools and equipment from exposed locations; and removing or securing scaffolding and other temporary work. Close openings in the work when storms of lesser intensity pose a threat to the work or
Project No. 20312361
SECTION 35 31 19 Page 15 any nearby Government property.
3.6 PLANT COMMUNICATIONS
Whenever the individual elements of the plant are located so that operation by normal voice between these elements is not satisfactory, install a satisfactory means of communication, such as telephone or other suitable devices and make available for use by Government personnel.
3.7 TEMPORARY PROJECT SAFETY FENCING
As soon as practicable, but not later than 15 days after the date established for commencement of work, furnish and erect temporary project safety fencing at the work site. Maintain the safety fencing during the life of the Contract and, upon completion and acceptance of the work, remove from the work site.
3.8 CLEANUP
Remove construction debris, waste materials, packaging material and the like from the work site daily. Any dirt or mud which is tracked onto paved or surfaced roadways must be cleaned away. Store all salvageable materials resulting from demolition activities within the fenced area described above or at the supplemental storage area. Neatly stack stored materials not in trailers, whether new or salvaged.
3.9 RESTORATION OF STORAGE AREA
Upon completion of the project remove the bulletin board, signs, barricades, haul roads, and all other temporary products from the site.
After removal of trailers, materials, and equipment from within the fenced area, remove the fence. Restore areas used during the performance of the Contract to the original or better condition. Remove gravel used to traverse grassed areas and restore the area to its original condition, including topsoil and seeding as necessary.
-- End of Section --
| SF 30 Amendment 05 |
| Amendment 05 Continuation Page |
| 01 50 00- Temp Construction Facilities_Controls Amendment 05 |
File details come from the government source that posted it. Updated .