This document is a solicitation for design-bid-build services for the P-204 F-35 Training and Simulator Facility at Marine Corps Air Station Cherry Point in North Carolina. Proposals are due on April 9, 2020 at 2:00pm EDT, with pre-proposal inquiries due by March 30, 2020 at 5:00pm EDT. The magnitude of construction is estimated between $25-100 million. The NAICS code is 236210 for industrial building construction, with a small business size standard of $39.5 million. This acquisition will be conducted on an unrestricted basis with full and open competition. The wage determination is General Decision Number NC20200065 dated January 3, 2020.

View the file

Other files

File Type Posted
Amendment 0009.pdf PDF
Amendment 8 P204 Drawings-Specs.pdf PDF
Amendment 0008.pdf PDF
Amendment 8 Attachment I -Updated Price Proposal Form_REVISED.pdf PDF
Amendment 0007-Update Proposal Submission.pdf PDF
Amendment 6 Attachment I-REVISED Price Proposal Form.pdf PDF
Amendment 0006.pdf PDF
Amendment 5.pdf PDF
Amendment 0005 PPI Responses.pdf PDF
Amendment 5 PPI-31_P-204 Soil Guidance Section for NEPA-PAMS.pdf PDF
Amendment 5 M-602.pdf PDF
Amendment 4 B286_Photos.zip ZIP file
Amendment 4 P204 B286 B4038 B4162 Existing FFE List Floor Plans.pdf PDF
Amendment 4 B4038_2of2.zip ZIP file
Amendment 0004.pdf PDF
Amendment 4-B286_As-Built Drawings.pdf PDF
Amendment 4 P204 FF E List for Contractors.xlsx XLSX spreadsheet
Amendment 4 B4038_1of2.zip ZIP file
Amendment 3-Attachment I - Price Proposal Form_REVISED.docx DOCX document
Amendment 3-P-204_Hazardous Survey.pdf PDF
Amendment 3-B4038_As-Built Drawings_01.pdf PDF
Amendment 3-P-204_Site Investigation Report.pdf PDF
Amendment 0003.pdf PDF
Amendment 3-B4038_As-Built Drawings_02.pdf PDF
P-204_Amendment-003.pdf PDF
Amendment 3-B4162_As-Built Drawings.pdf PDF
Amendment 0002 Extend Proposal Due Date.pdf PDF
Amendment 0001 Site Visit Cancelled.pdf PDF
Attachment I - Price Proposal Form.docx DOCX document
Attachment D - Small Business Subcontracting Record.docx DOCX document
Attachment F - Past Performance Questionnaire.docx DOCX document
1596300dwg17of26_Interiors.pdf PDF
Attachment E - Small Business Participation and Commitment Strategy.docx DOCX document
1596300dwg03of26_Civil-C.pdf PDF
1596300dwg24of26_Electrical.pdf PDF
1596300dwg11of26_Civil-CS.pdf PDF
1596300dwg25of26_Telecom-AV.pdf PDF
1596300dwg14of26_Structural.pdf PDF
1596300dwg26of26_Telecom.pdf PDF
Attachment B - SECNAV 5512.pdf PDF
1596300dwg20of26_Mechanical.pdf PDF
1596300spc02of04.pdf PDF
1596300dwg09of26_Civil-CG.pdf PDF
Attachment J - Site Visit Map to B-163.pdf PDF
1596300dwg16of26_Architectural.pdf PDF
Attachment A - Pre-Proposal Inquiries Form.xlsx XLSX spreadsheet
1596300dwg23of26_Electrical.pdf PDF
1596300dwg06of26_Civil-CE.pdf PDF
RFP- P204.pdf PDF
Attachment G - Small Business Subcontracting Plan.docx DOCX document
Show 40 more

Latest 50 of 69 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WORK ORDER NO. 1590340

A/E CONTRACT NO.

N40085-18-D-0600

APPROPRIATION: MCON

P-204 F-35 TRAINING AND SIMULATOR FACILITY

Volume 4 of 4

At the

Marine Corps Air Station, Cherry Point, NC

(P-204)

SUBMITTED BY:

NAVFAC MIDLANT, CI Core 9324 Virginia Avenue

Norfolk, VA 23511

PREPARED BY:

Architectural: Erik Velazquez, R.A.

Structural: R. Christopher Pyle, P.E.

Plumbing/Mechanical: Ryan M. Browning P.E.

Electrical: Luther A. Woodruff, III, P.E.

Fire Protection: Andrew P Leahy, P.E.

Civil: Marty L. Crow, P.E.

Landscape Arch: Stephen L. Stritzl, RLA

Telecommunications: Luther A. Woodruff, III, RCDD

Design Manager (DM):

Rosie M. Shanks, RA, AIA, GPCP.

Date:

ACCEPTED BY:

For Commander, NAVFAC MIDLANT: ___________________________________

Date:

Name: Marty Crow, PE Discipline: Civil

Name: Stephen Stritzl, LS Discipline: Landscape

Name: Christopher Pyle, PE Discipline: Structural

Name: Erik Velazquez, RA Discipline: Architectural

Name: Andrew Leahy, PE Discipline: Fire Protection

Name: Charles W. Southall, PE Discipline: Plumbing, Mechanical

Name: Luther Woodruff, PE Discipline: Electrical

Name: Luther Woodruff, RCDD Discipline: Telecommunications

P-204 F-35 Training and Simulator Facility Work Order Number 1590340 MCAS Cherry Point, North Carolina

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 15 LIST OF DRAWINGS

00 22 13.00 20 SUPPLEMENTARY INSTRUCTIONS TO OFFERORS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 14 00 WORK RESTRICTIONS

01 20 00.00 20 PRICE AND PAYMENT PROCEDURES

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 30 01.00 22 DESIGN, PROCUREMENT, AND INSTALLATION OF FURNITURE,

FIXTURES, AND EQUIPMENT

01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT

MANAGEMENT SYSTEM

01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)

01 33 00 SUBMITTAL PROCEDURES

01 33 29 SUSTAINABILITY REPORTING

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 20 QUALITY CONTROL

01 45 35 SPECIAL INSPECTIONS

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS

01 58 00 PROJECT IDENTIFICATION

01 60 00.00 22 REQUIREMENTS FOR PESTICIDE AND HERBICIDE COORDINATION

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

01 78 24.00 20 FACILITY ELECTRONIC OPERATION AND MAINTENANCE SUPPORT

INFORMATION (eOMSI)

01 78 30.00 22 GIS DATA DELIVERABLES

01 80 00 REPORTS

01 91 00.15 22 TOTAL BUILDING COMMISSIONING

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION

02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL

02 82 00 ASBESTOS REMEDIATION

02 83 00 LEAD REMEDIATION

02 84 16 HANDLING OF LIGHTING BALLASTS AND LAMPS CONTAINING PCBs

AND MERCURY

DIVISION 03 - CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

DIVISION 04 - MASONRY

04 20 00 UNIT MASONRY

DIVISION 05 - METALS

05 12 00 STRUCTURAL STEEL

05 21 00 STEEL JOIST FRAMING

05 30 00 STEEL DECKS

PROJECT TABLE OF CONTENTS Page 1

05 40 00 COLD-FORMED METAL FRAMING

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 51 33 METAL LADDERS

05 52 00 METAL RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

06 20 00 FINISH CARPENTRY

06 61 16 SOLID SURFACING FABRICATIONS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS

07 11 13 BITUMINOUS DAMPPROOFING

07 21 13 BOARD AND BLOCK INSULATION

07 22 00 ROOF AND DECK INSULATION

07 27 10.00 10 BUILDING AIR BARRIER SYSTEM

07 27 19.01 SELF-ADHERING AIR BARRIERS

07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS

07 27 36 SPRAY FOAM AIR BARRIERS

07 41 13 METAL ROOF PANELS

07 42 63 FABRICATED WALL PANEL ASSEMBLIES

07 60 00 FLASHING AND SHEET METAL

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 STEEL DOORS AND FRAMES

08 14 00 WOOD DOORS

08 31 00 ACCESS DOORS AND PANELS

08 33 23 OVERHEAD COILING DOORS

08 34 73 SOUND CONTROL DOOR ASSEMBLIES

08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

08 44 00 CURTAIN WALL AND GLAZED ASSEMBLIES

08 51 13 ALUMINUM WINDOWS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 91 00 METAL WALL LOUVERS

DIVISION 09 - FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC TILING

09 51 00 ACOUSTICAL CEILINGS

09 62 38 STATIC-CONTROL FLOORING

09 64 29 WOOD STRIP AND PLANK FLOORING

09 65 00 RESILIENT FLOORING

09 66 23.00 22 RESINOUS (EPOXY) TERRAZZO FLOORING

09 67 23.16 FUEL RESISTIVE RESINOUS FLOORING, 5-COAT SYSTEM

09 68 00 CARPETING

09 69 13 RIGID GRID ACCESS FLOORING

09 72 00 WALLCOVERINGS

09 84 20 ACOUSTICAL WALL PANELS

09 90 00 PAINTS AND COATINGS

DIVISION 10 - SPECIALTIES

PROJECT TABLE OF CONTENTS Page 2

10 11 00 VISUAL DISPLAY UNITS

10 14 00.10 EXTERIOR SIGNAGE

10 14 00.20 INTERIOR SIGNAGE

10 21 13 TOILET COMPARTMENTS

10 22 39 FOLDING PANEL PARTITIONS

10 26 00 WALL AND DOOR PROTECTION

10 28 13 TOILET ACCESSORIES

10 51 13 LOCKERS AND BENCHES

DIVISION 12 - FURNISHINGS

12 22 00 CURTAINS AND DRAPES

12 24 13 ROLLER WINDOW SHADES

12 36 00 COUNTERTOPS

12 48 13 ENTRANCE FLOOR MATS AND FRAMES

12 61 13 UPHOLSTERED AUDIENCE SEATING

DIVISION 21 - FIRE SUPPRESSION

21 13 13.00 20 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

21 30 00 FIRE PUMPS

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

22 05 48.00 20 MECHANICAL SOUND, VIBRATION, AND SEISMIC CONTROL

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS

23 05 48.00 40 VIBRATION CONTROLS FOR HVAC PIPING AND EQUIPMENT

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING

CONTROL SYSTEMS

23 09 93 SEQUENCES OF OPERATION FOR HVAC CONTROL

23 11 25 FACILITY GAS PIPING

23 25 00 CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS

23 52 43.00 20 LOW PRESSURE WATER HEATING BOILERS (UNDER 800,000 BTU/HR

OUTPUT)

23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE

23 64 26 CHILLED AND HEATING-HOT WATER PIPING SYSTEMS

23 81 23.00 20 COMPUTER ROOM AIR HANDLING UNITS (CRAH)

23 82 00.00 20 TERMINAL HEATING UNITS

DIVISION 25 - INTEGRATED AUTOMATION

25 05 11.01 CYBERSECURITY FOR MCAS ENERGY MONITORING AND CONTROL

SYSTEM (EMCS)

25 05 11.02 CYBERSECURITY FOR HEATING, VENTILATION, AIR CONDITIONING

(HVAC) CONTROL SYSTEM

25 05 11.03 CYBERSECURITY MCAS FIRE ALARM CONTROL SYSTEM (FACS)

25 10 10 UTILITY MONITORING AND CONTROL SYSTEM (UMCS) FRONT END

AND INTEGRATION

PROJECT TABLE OF CONTENTS Page 3

DIVISION 26 - ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 08 00 APPARATUS INSPECTION AND TESTING

26 08 01.00 10 POWER SYSTEM STUDY FOR NEW CONSTRUCTION PROJECTS

26 12 19.10 THREE-PHASE PAD-MOUNTED TRANSFORMERS

26 12 21 SINGLE-PHASE PAD-MOUNTED TRANSFORMERS

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 24 13 SWITCHBOARDS

26 27 14.00 20 ELECTRICITY METERING

26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS

26 32 13.00 20 SINGLE OPERATION GENERATOR SETS

26 36 23.00 20 AUTOMATIC TRANSFER SWITCHES

26 41 00 LIGHTNING PROTECTION SYSTEM

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 05 29.00 10 PROTECTIVE DISTRIBUTION SYSTEM (PDS) FOR SIPRNET

COMMUNICATION SYSTEMS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

27 54 00.00 20 COMMUNITY ANTENNA TELEVISION (CATV) SYSTEMS

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM

DIVISION 31 - EARTHWORK

31 05 19 GEOTEXTILE

31 11 00 CLEARING AND GRUBBING

31 21 13 VAPOR MITIGATION

31 23 00.00 20 EXCAVATION AND FILL

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID

PAVEMENTS

32 05 33 LANDSCAPE ESTABLISHMENT

32 12 13 BITUMINOUS TACK AND PRIME COATS

32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS

32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE

FACILITIES

32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 PAVEMENT MARKINGS

32 92 23 SODDING

32 93 00 EXTERIOR PLANTS

DIVISION 33 - UTILITIES

33 11 00 WATER UTILITY DISTRIBUTION PIPING

33 30 00 SANITARY SEWERAGE

33 40 00 STORM DRAINAGE UTILITIES

33 61 14 EXTERIOR BURIED PREINSULATED WATER PIPING

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 4

SECTION 23 25 00

CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS

11/08

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASME INTERNATIONAL (ASME)

ASME B40.100 (2013) Pressure Gauges and Gauge Attachments

ASTM INTERNATIONAL (ASTM)

ASTM D2688 (2015; E 2016) Standard Test Method for Corrosivity of Water in the Absence of Heat Transfer (Weight Loss Methods)

ASTM D596 (2001; R 2011) Reporting Results of Analysis of Water

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

NEMA MG 1 (2016; SUPP 2016) Motors and Generators

1.2 SUMMARY

This section covers the provisions and installation procedures necessary for a complete and totally functional water system(s) chemical treatment.

Provide and install the system with all necessary System Components, Accessories, Piping Components, and Supplemental Components/Services.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-03 Product Data

Water Treatment System; G

Water Analysis; G

Spare Parts

Field Instructions

SECTION 23 25 00 Page 1

Tests; G

SD-10 Operation and Maintenance Data

Water Treatment System

1.4 QUALITY CONTROL

1.4.1 Safety

Exposed moving parts, parts that produce high operating temperature, parts which may be electrically energized, and parts that may be a hazard to operating personnel shall be insulated, fully enclosed, guarded, or fitted with other types of safety devices. Install safety devices so that proper operation of equipment is not impaired.

1.4.2 Drawings

Because of the small scale of the drawings, it is not possible to indicate all offsets, fittings, and accessories that may be required. Carefully investigate the plumbing, fire protection, electrical, structural and finish conditions that would affect the work to be performed and arrange such work accordingly, furnishing required offsets, fittings, and accessories to meet such conditions.

1.5 DELIVERY, STORAGE, AND HANDLING

Protect all equipment delivered and placed in storage from the weather, humidity and temperature variations, dirt and dust, or other contaminants.

1.6 MAINTENANCE

Submit spare parts data for each different item of material and equipment specified, after approval of the detail drawings, not later than 1 months prior to the date of beneficial occupancy. The data shall include a complete list of parts and supplies, with source of supply

PART 2 PRODUCTS

2.1 STANDARD PRODUCTS

a. Provide materials and equipment which are standard products of a manufacturer regularly engaged in the manufacturing of such products, that are of a similar material, design and workmanship and that have been in satisfactory commercial or industrial use for two years prior to bid opening.

b. The two-year use shall include applications of equipment and materials under similar circumstances and of similar size. The two years experience shall have been satisfactorily completed by a product which has been sold or is offered for sale on the commercial market through advertisements, manufacturer's catalogs, or brochures. Products having less than a two-year field service record will be acceptable if a certified record of satisfactory field operation, for not less than 6000 hours exclusive of the manufacturer's factory tests, can be shown.

c. All products shall be supported by a service organization. Submit a certified list of qualified permanent service organizations for support of the equipment, including their addresses and

SECTION 23 25 00 Page 2 qualifications. These service organizations shall be reasonably convenient to the equipment installation and shall be able to render satisfactory service to the equipment on a regular and emergency basis during the warranty period of the contract.

d. The selected service organization shall provide the chemicals required, the concentrations required, and the water treatment equipment sizes and flow rates required. The company shall provide all chemicals required for the chilled water systems and fill the systems with chemicals to the levels specified. The chemical shall meet the requirements of this specification as well as the recommendations from the manufacturers of the condenser and cooling tower. Acid treatment chemicals shall not be used.

2.2 NAMEPLATES

Each major component of equipment shall have the manufacturer's name, address, type or style, and catalog or serial number on a plate securely attached to the item of equipment. Nameplates shall be provided for:

a. Pump(s)

b. Pump Motor(s)

2.3 ELECTRICAL WORK

Electrical equipment, motors, motor efficiencies, and wiring shall be in accordance with Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM. Provide electrical motor driven equipment specified complete with motors, motor starters, and controls. Electrical characteristics and enclosure type shall be as shown, and unless otherwise indicated, all motors of 1 horsepower and above with open, dripproof, or totally enclosed fan cooled enclosures, shall be high efficiency type. Field wiring shall be in accordance with manufacturer's instructions. Each motor shall conform to NEMA MG 1 and be of sufficient size to drive the equipment at the specified capacity without exceeding the nameplate rating of the motor.

All motors shall be continuous duty with the enclosure specified. Provide motor starters complete with thermal overload protection and other appurtenances necessary for the motor control indicated. Furnish motors with a magnetic across-the-line or reduced voltage type starter as required by the manufacturer. Motor starter shall be provided with NEMA 1 enclosures. Manual or automatic control and protective or signal devices required for the operation specified and any control wiring required for controls and devices specified, but not shown, shall be provided.

2.4 GAUGES

Gauges shall conform to ASME B40.100 , Class 1, 2, or 3, Style X, Type I or III as required, 4-1/2 inches in diameter with phenolic or metal case.

2.5 WATER ANALYSIS

Conditions of make-up water to be supplied to the boilers, cooling towers and chilled water systems reported in accordance with ASTM D596 are as follows:

SECTION 23 25 00 Page 3

Date of Sample

Temperature degrees C

Silica (SiO 2) ppm (mg/L)

Insoluble ppm (mg/L)

Iron, total (Fe) ppm (mg/L)

Aluminum (Al) ppm (mg/L)

Calcium (Ca) ppm (mg/L)

Magnesium (Mg) ppm (mg/L)

Carbonate (HCO 3) ppm (mg/L)

Sulfate (SO 4) ppm (mg/L)

Chloride (Cl) ppm (mg/L)

Nitrate (NO 3) ppm (mg/L)

Turbidity ntu pH

Residual Chlorine ppm (mg/L)

Total Alkalinity ppm (mg/L)

Non-Carbonate Hardness ppm (mg/L)

Total Hardness ppm (mg/L)

Dissolved Solids ppm (mg/L)

Conductivity micromho/cm

2.6 CHILLED WATER SYSTEM

A 2 gallon shot feeder shall be provided on the chilled water piping as indicated. The feeder shall be furnished with an air vent, gauge glass, funnel, valves, fittings, and piping.

2.6.1 Chilled Water Treatment

Treat chilled water with either a borax/nitrite type treatment or a molybdate type treatment. Both types of treatment can be used with glycol. Borax/nitrite treatment shall be maintained at the limits of 600 to 1000 ppm nitrite, 40 - 50 ppm copper corrosion inhibitor (TT or MBT), and pH of 8.5 to 9.5. Molybdate treatment shall be maintained at the limits of 100 to 125 ppm molybdate, 40 - 50 ppm copper corrosion inhibitor

SECTION 23 25 00 Page 4

(TT or MBT), and pH of 8.0 to 9.0.

2.6.2 Chilled Water Test Kits

One test kit of each type required to determine the water quality as outlined within the operation and maintenance manuals shall be provided (e.g. pH and nitrite or molybdate).

2.7 LOW AND MEDIUM TEMPERATURE HOT WATER BOILERS AND HEAT EXCHANGERS

Low and medium temperature hot water boilers are defined as those operating below 350 degrees F, ( 250 degrees F for Low Temperature).

2.7.1 Chemical Feeder

A 5 gallon shot feeder shall be provided on the hot water piping as indicated. Size and capacity of feeder shall be based on local requirements and water analysis. The feeder shall be furnished with an air vent, gauge glass, funnel, valves, fittings, and piping.

2.7.2 Low and Medium Temperature Hot Water Treatment

Hot water shall be treated with either a borax/nitrite type treatment or a molybdate type treatment. Both types of treatment can be used with glycol. Borax/nitrite treatment shall be maintained at the limits of 600 to 1000 ppm nitrite, 40 - 50 ppm copper corrosion inhibitor (TT or MBT) and pH of 8.5 to 9.5. Molybdate treatment shall be maintained at the limits of 100 to 125 ppm molybdate, 40 - 50 ppm copper corrosion inhibitor (TT or MBT) and pH of 8.0 to 9.0.

2.7.3 Test Kit Requirements

One test kit of each type required to determine the water quality as outlined within the operation and maintenance manuals shall be provided (e.g. pH and nitrite or molybdate).

2.8 SUPPLEMENTAL COMPONENTS/SERVICES

Drain and makeup water piping shall comply with the requirements of Section 22 00 00 PLUMBING, GENERAL PURPOSE. Drains which connect to sanitary sewer systems shall be connected by means of an indirect waste.

PART 3 EXECUTION

3.1 EXAMINATION

After becoming familiar with all details of the work, verify all dimensions in the field, and advise the Contracting Officer of any discrepancy, before performing any work.

3.2 INSTALLATION

Provide all chemicals, equipment and labor necessary to bring all system waters in conformance with the specified requirements. Perform all work in accordance with the manufacturer's published diagrams, recommendations, and equipment warranty requirements.

SECTION 23 25 00 Page 5

3.3 PIPING

Connections between dissimilar metals shall be made with a dielectric union.

3.4 TESTS

If the waters of the mechanical systems are not in conformance with the specified requirements or in accordance with manufacturer's recommendations, the water treatment company shall take corrective action to enable compliance. Daily operational tests shall be performed in the directed frequencies to maintain required control to prevent corrosion, scaling and damage to equipment during operation Submit test schedules, at least 2 weeks prior to the start of related testing, for the condenser/chilled/boiler/condensate/feedwater water quality tests. The schedules shall identify the date, time, frequency and collection location for each test.

3.4.1 Chilled Water Testing (monthly)

Once a month, the following tests will be performed on chilled water.

pH

Nitrite or Molybdate ppm (mg/L)

Conductivity micromho/cm

3.4.2 Hot Water Boiler Water Quality Testing

3.4.2.1 Low and Medium Temperature Systems (monthly)

Monthly testing shall be completed and recorded for the following parameters.

pH

Nitrite or Molybdate ppm (mg/L)

3.4.3 Quality Assurance Testing

Conduct QA testing periodically by an independent water treatment lab/consultant to verify to managers that the mechanical and water treatment systems are being maintained properly. Provide the QA evaluation reports to the government COR.

3.4.3.1 Chilled Water Quality Assurance Testing (quarterly)

Quarterly, the following tests shall be performed on chilled water.

pH

SECTION 23 25 00 Page 6

Nitrite or Molybdate ppm (mg/L)

Conductivity micromho/cm

Iron (total, as Fe(2)O(3)) ppm (mg/L)

Written evaluation summary

3.4.3.2 Hot Water Boiler Water Quality Assurance Testing

a. Quarterly testing of Low and Medium Temperature Systems shall be completed and recorded for the following parameters.

pH

Nitrite or Molybdate ppm (mg/L)

Iron (total, as Fe(2)O(3)) ppm (mg/L)

Written evaluation summary

b. The hot water boiler water shall be analyzed once a month for a period of 1 year by an independent consultant. The analysis shall include the following information recorded in accordance with ASTM D596.

pH

Sulfite (Na2SO3) ppm (mg/L)

Hardness(as CaCO3) ppm (mg/L)

Iron (total, as Fe(2)O(3)) ppm (mg/L)

Written evaluation summary

3.4.4 Corrosion Testers

Install corrosion coupon and rack systems to verify corrosion control in the systems. Testers or coupons are installed in flowing system water through a sidestream or rack system. Both mild steel and copper metal samples are to be tested in the corrosion testers in accordance with ASTM D2688. Samples are to be replaced and analyzed every 3 months.

Rates of corrosion less than 3 mpy for steel and 0.2 mpy for copper are acceptable. Corrosion testers shall be installed on the piping systems of the following systems.

Chilled water system Hot water loop

SECTION 23 25 00 Page 7

3.5 INSPECTIONS

3.5.1 Inspection General Requirements

Thirty days after project completion, inspect the cooling tower and condenser for problems due to corrosion, scale, and biological growth. If the cooling tower and condenser are found not to conform to the manufacturer's recommended conditions, and the water treatment company recommendations have been followed; the water treatment company shall provide all chemicals and labor for cleaning or repairing the equipment as required by the manufacturer's recommendations.

3.5.2 Boiler/Piping Test

Thirty day after project completion, inspect the boiler and condensate piping for problems due to corrosion and scale. If the boiler is found not to conform to the manufacturer's recommendations, and the water treatment company recommendations have been followed, the water treatment company shall provide all chemicals and labor for cleaning or repairing the equipment as required by the manufacturer's recommendations. If corrosion is found within the condensate piping, proper repairs shall be made by the water treatment company.

-- End of Section --

SECTION 23 25 00 Page 8

SECTION 23 52 43.00 20

LOW PRESSURE WATER HEATING BOILERS (UNDER 800,000 BTU/HR OUTPUT)

05/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI Z21.13/CSA 4.9 (2017; Errata 2018) Gas-Fired Low Pressure Steam and Hot Water Boilers

ASME INTERNATIONAL (ASME)

ASME BPVC SEC IV (2017) BPVC Section IV-Rules for Construction of Heating Boilers

ASME CSD-1 (2016) Control and Safety Devices for Automatically Fired Boilers

ASTM INTERNATIONAL (ASTM)

ASTM A53/A53M (2018) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless

NATIONAL BOARD OF BOILER AND PRESSURE VESSEL INSPECTORS (NBBI)

NBBI NB-23 PART 1 (2013) National Board Inspection Code - Part 1 Installation

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

NEMA MG 1 (2016; SUPP 2016) Motors and Generators

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 31 (2016) Standard for the Installation of Oil-Burning Equipment

NFPA 54 (2018) National Fuel Gas Code

NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2;

TIA 17-3; TIA 17-4; TIA 17-5; TIA 17-6;

TIA 17-7; TIA 17-8; TIA 17-9; TIA 17-10;

TIA 17-11; TIA 17-12; TIA 17-13; TIA

17-14; TIA 17-15; TIA 17-16; TIA 17-17 )

National Electrical Code

U.S. DEPARTMENT OF DEFENSE (DOD)

UFC 3-430-07 (2019) Operations And Maintenance:

SECTION 23 52 43.00 20 Page 1

Inspection And Certification Of Boilers And Unfired Pressure Vessels, With Change 5

UNDERWRITERS LABORATORIES (UL)

UL 795 (2016) UL Standard for Safety Commercial-Industrial Gas Heating Equipment

1.2 RELATED REQUIREMENTS

Section 23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS, applies to this section, with the additions and modifications specified herein.

1.3 DESIGN REQUIREMENTS

Boiler must be suitable for installation in the space shown with ample room for opening doors and cleaning and removal and replacement of tubes.

Boiler must be designed and tested in accordance with ASME BPVC SEC IV , ASME CSD-1, NFPA 54 , NFPA 31 , NFPA 70 and ANSI Z21.13/CSA 4.9 . Boiler must be installed in accordance with NBBI NB-23 PART 1 . Paint boiler in accordance with manufacturer's recommendations. Boiler design working pressure must be 160 psig.

1.3.1 Boiler Installation Requirements

1.3.1.1 Location

Install Boiler(s) and associated hot water pumps in a mechanical room inside the facility in accordance with NBBI NB-23 PART 1 . Provide ample clearance around boilers to allow access for inspection, maintenance and repair. Passageways around all sides of boilers must have an unobstructed minimum width of 36 inches or the clearances recommended by the boiler manufacturer whichever is greater.

1.3.1.2 Combustion Air

Provide supply of air for combustion and ventilation. Provide directly vented air intake and combustion ductwork. Provide metallic air intake ductwork in accordance with Section 23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS with boiler manufacturer's written instructions. Insulate air intake ductwork in accordance with Section 23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS. Provide Boiler Flue Vent in accordance with Section 23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS and boiler manufacturer' written instructions.

1.3.2 Detail Drawings

1.3.2.1 Drawings

Show boiler hot water isolation valves, emergency disconnect switch, and complete boiler gas train on the contract drawings.

1.3.2.2 Fuel Train / Wiring Diagram

Submit fuel train and wiring diagram.

SECTION 23 52 43.00 20 Page 2

1.3.3 Water Analysis

Provide test reports of water analysis. UFC 3-240-13FN Industrial Water Treatment must be followed for all boiler installations.

1.4 SAFETY STANDARDS

Hot water boilers, burners and supplementary control devices, safety interlocks, or limit controls required under this specification, must meet requirements of the following standards as applicable:

a. Gas-Fired Units: ASME CSD-1, ASME BPVC SEC IV , NFPA 54 , NFPA 70 , ANSI Z21.13/CSA 4.9 or UL 795 .

Controls not covered by the above must have a UL label, UL listing mark, or must be listed in the Factory Mutual Approval Guide.

1.5 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-02 Shop Drawings

Fuel Train

Wiring Diagram

SD-03 Product Data

Boilers; G

Boiler Trim and Control Equipment; G

Burners and Control Equipment; G

SD-06 Test Reports

Operational Tests; G

Water Analysis

SD-07 Certificates

Boilers; G

Burners and Control Equipment

Boiler Trim and Control Equipment

SD-08 Manufacturer's Instructions

Boilers

SD-10 Operation and Maintenance Data

SECTION 23 52 43.00 20 Page 3

Energy Efficient Equipment for Boilers; S

Boilers, Data Package 4

Submit in accordance with Section 01 78 23 OPERATION AND

MAINTENANCE DATA.

SD-11 Closeout Submittals

Posted Operating Instructions for Heating Water Boilers

PART 2 PRODUCTS

2.1 PRODUCT SUSTAINABILITY CRITERIA

For products in this section, where applicable and to extent allowed by performance criteria, provide and document the following:

2.1.1 Energy Efficient Equipment for Boilers

Provide boilers meeting the efficiency requirements as stated within this section and provide documentation in conformance with Section 01 33 29 SUSTAINABILITY REPORTING paragraph ENERGY EFFICIENT EQUIPMENT.

2.2 BOILERS

Shall conform to the applicable requirements of ASME BPVC SEC IV and ASME CSD-1. Boiler shall be natural gas fired, fully condensing, and fire tube design. The boiler shall be factory-fabricated, factory-assembled, and factory-tested, fire-tube condensing boiler with heat exchanger sealed pressure tight, built on a steel base; including insulated jacket;

flue-gas vent; combustion-air intake connections; water supply, return, and condensate drain connections; and controls. Provide each boiler complete with burner and fuel system, a forced or induced draft fan, an automatic electronic control system complete with combustion and flame safeguard controls, firing sequence programmer, safety interlocks, limit controls and central control panel, and such trim and appurtenances as are peculiar to water units as specified herein. Units shall be factory-wired and assembled except for such readily installed appurtenances as safety valves, water columns, and pressure gages. Units shall be complete and ready for operation when connected to water, fuel, and electrical supplies. The heater exchanger shall bear the ASME "H" stamp for 160 psi working pressure and shall be National Board listed. The heat exchanger shall be constructed of a fully welded 316L stainless steel or cast aluminum and of fire tube design. The heat exchanger shall be designed for a single or multi-pass water flow, but must meet the scheduled water side pressure drop. There shall be no banding material, bolts, gaskets or "O" rings in the heat exchanger design. The condensate collection basin shall be fully welded 316L stainless steel. Boiler shall include an intake air filter with a factory installed air pressure switch. The pressure switch will alert the end user on the screen of the boiler that the intake filter is dirty and needs to be changed. The pressure vessel shall be in accordance with ASME Section IV pressure vessel code.

SECTION 23 52 43.00 20 Page 4

2.3 BURNERS AND CONTROL EQUIPMENT

2.3.1 Gas-Fired Power Burner

Spark ignition with 100 percent main-valve shutoff with electronic flame supervision. Forced draft single burner premix design. The burner shall be capable of a minimum 5:1 gas train turndown without loss of combustion efficiency. Boiler shall be equipped with a modulating blower system to precisely control the fuel/air mixture to provide modulating boiler firing rates for maximum efficiency. The burner firing sequence of operation shall include pre-purge, firing, modulation, and post-purge operation.

Burner controls and safety equipment shall conform to the applicable requirements of ASME CSD-1, NFPA 54 , ANSI Z21.13/CSA 4.9 and UL 795 .

Mount controls; including operating switches, indicating lights, gages, alarms, motor starters, fuses, and circuit elements of control systems on a single control panel or cabinet designed for separate mounting not on the burner.

2.4 BOILER TRIM AND CONTROL EQUIPMENT

Boiler trim shall comply with ASME BPVC SEC IV and additional appurtenances specified below. Non-recycling control interlocks shall have the reset located on control interlock. Provide in accordance with ASME CSD-1 and ASME BPVC SEC IV .

2.4.1 Emergency Disconnect Switch

Provide and locate on wall outside boiler room entrance or just inside door, when boiler room door is on building exterior as required by ASME CSD-1 to allow rapid and complete shutdown of the boiler in the event of an emergency. Emergency switch must be a fuse-type safety switch.

Switch must be red and furnished with a label indicating function of switch.

2.4.2 Relief Valves

Provide relieving capacity for the full output of boiler installed.

Safety relief-valve piping must conform to ASTM A53/A53M, schedule 40 steel pipe and be piped full-size to a floor drain.

2.4.3 Condensate Neutralization Kit

Factory-supplied condensate trap with condensate trip sensor, high capacity condensate receiver prefilled with appropriate medium.

2.4.4 Primary Boiler Pump

Provide boiler with primary boiler pump as indicated on drawings and in accordance with Section 23 64 26 CHILLED AND HEATING-HOT WATER SYSTEMS.

2.4.5 Pressure Gage

Provide with a scale equivalent to 1.5 time outlet water pressure with a 6 inch diameter. Locate one on supply water piping and one on the return water piping. Provide in accordance with Section 23 64 26 CHILLED AND

HEATING-HOT WATER SYSTEMS.

SECTION 23 52 43.00 20 Page 5

2.4.6 Thermometer

Provide thermometer with a scale equivalent to 1.5 times outlet water temperature. Provide one located on supply water piping and one on return water piping. Provide in accordance with Section 23 64 26 CHILLED AND

HEATING-HOT WATER SYSTEMS.

2.4.7 Drain Tapping

Provide drain valve and piping to a floor drain.

2.4.8 Make-up Water Station

2.4.8.1 Pressure Reducing Station

Provide a water pressure-reducing valve and relief valve, or a combination of the two in the makeup water line to the boiler to maintain a water pressure of as indicated on the drawings of the hot water system.

Provide a 3/4 inch globe valve by-pass around this valve.

2.4.8.2 Backflow Preventers

Section 22 00 00 PLUMBING, GENERAL PURPOSE. Locate upstream of by-pass.

2.4.9 Feedwater Treatment Feeder

See Section 23 64 26 CHILLED AND HEATING-HOT WATER SYSTEMS and Section 23 25 00 CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS for chemical shot feeder requirements.

2.4.10 Combustion Regulator

Provide adjustable temperature, thermostatic immersion type that must limit boiler water temperature to a maximum of 250 degrees F. Control must actuate burner through an electric relay system to maintain boiler water temperature within normal prescribed limits at loads within rated capacity of boiler.

2.4.11 Air Vent Valve

Provide with screwed connection, stainless steel disk, and stainless steel seats to vent entrapped air.

2.4.12 High Temperature Limit Switch

Provide adjustable immersible aquastat type with a temperature setting above that of the combustion regulator and below that of the lowest relief valve setting. Aquastat must function to cause a safety shutdown by closing fuel valves, and shutting down burner equipment , activating a red indicating light, and sounding an alarm in the event that boiler water temperature rises to the high temperature limit setting. A safety shutdown due to high temperature must require manual reset before operation can resume and prevent recycling of burner equipment. Pre-set high temperature limit devices that cannot be easily tested are not allowed.

2.4.13 Low Water Level Cutoff Switch

Provide float actuated type. Low water level cutoff must cause a safety

SECTION 23 52 43.00 20 Page 6 shutdown by closing fuel valves, and shutting down burner equipment , activating a red indicating light, and sounding an alarm in the event that water level drops below the lowest safe permissible water level established by the boiler manufacturer and ASME BPVC SEC IV . A safety shutdown due to low water must require manual reset before operation can resume and prevent recycling of burner equipment.

2.4.14 Boiler Safety Control Circuits

Provide boiler safety control circuits, including control circuits for burner and draft fan, must be single-phase, two-wire one-side grounded, and not over 120 volts. Provide safety control switching in ungrounded conductors. Provide overcurrent protection. In addition to circuit grounds, ground metal parts which do not carry current to a grounding conductor.

2.4.15 Indicating Lights

Each safety interlock requiring a manual reset must have an individually labeled red indicating light. Non-recycling control interlocks must have the reset located on the control itself. Red indicating lights on the control panel may be omitted if the burner combustion control system has a Keyboard Display Module installed that will identify the lockout information required in Item c. below. Indicating lights must have colors as follows:

a. Amber: Ignition on

b. Green: Main fuel safety shut-off valves open

c. Red (One for Each): Safety lockout, flame failure, low water level, and high temperature

d. Blue: Draft

Boiler Control Panel

Boiler controls shall feature a standard, factory-installed LCD screen display with the following standard features:

a. Password Security: Boiler shall have a different password security code for the User and the Installer to access adjustable parameters.

b. Indicating Lights: LCD screen shall display all indicating lights.

c. Service reminder: Boiler shall have the ability to display a yellow colored service notification screen based upon months of installation, hours of operation, and number of boiler cycles. All notifications are adjustable by the installer.

d. Anti-cycling control: Boiler shall have the ability to set a time delay after a heating demand is satisfied allowing the boiler to block a new call for heat. The boiler will display an anti-cycling blocking on the screen until the time has elapsed or the water temperature drops below the anti-cycling differential parameter. The anti-cycling control parameter is adjustable by the installer.

e. Primary pump control: Boiler shall have the ability to control the primary pump to maintain boiler required flow.

SECTION 23 52 43.00 20 Page 7

f. BMS integration with 0-10 volts dc input: The Control shall allow an option to Enable and control set point temperature or control firing rate by sending the boiler a 0-10 volts input signal.

g. Data logging: Boiler shall have non-volatile data logging memory including last 10 lockouts, hours running and ignition attempts and should be able to view on boiler screen.

h. Cascade Controller: The boiler shall have a built in Cascade controller to sequence and rotate lead boiler to ensure equal runtime while maintaining modulation of all boilers without utilization of an external controller.

The factory installed, internal cascade controller shall include:

(1) Lead lag.

(2) Efficiency optimization: The Control module shall allow multiple boilers to fire at minimum firing rate in lieu of Lead/Lag.

(3) Front end loading.

(4) Rotation of lead boiler: The Control module shall change the lead boiler every hour for the first 24 hours after initializing the Cascade.

Following that, the leader will be changed once every 24 hours.

i. Building Automation System Interface: Factory installed BACnet gateway interface to enable building automation system to monitor, control, and display boiler status and alarms.

2.4.16 Alarm Bell

Provide alarm bell, electrically operated, with a manual disconnect switch. Disconnect switch must be type and wired so that switching off alarm following a safety shutdown will not prevent alarm from sounding again upon recurrence of a subsequent safety shutdown condition.

2.4.17 Post-Combustion Purge

Provide controls and wiring necessary to ensure operation of draft fan for a period of not less than 15 seconds or of sufficient duration to provide four complete air changes in the boiler combustion chamber (whichever is greater) following shutdown of burner upon satisfaction of heat demand and in accordance with ASME CSD-1 . Upon completion of post-combustion purge period, draft fan must automatically shutdown until next restart.

2.4.18 Draft

Intake ductwork in accordance with Section 23 00 00 AIR SUPPLY,DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS and boiler manufacturer's written instructions. Insulate air intake ductwork in accordance with Section 23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS.

Boiler Flue, Combustion Intake Supports

Provide in accordance with Section 23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS.

SECTION 23 52 43.00 20 Page 8

2.5 ELECTRIC MOTORS

Electric motors must meet requirements of NEMA MG 1. Motors less than 1 hp must meet NEMA High Efficiency requirements. Motors 1 hp and larger must meet NEMA Premium Efficiency requirements. Motors which are an integral part of the packaged boiler system must be the highest efficiency available by the manufacturer of the packaged boiler. Motors must be variable speed.

PART 3 EXECUTION

3.1 EQUIPMENT INSTALLATION

Install equipment in accordance with manufacturer's installation instructions and NBBI NB-23 PART 1 . Grout equipment mounted on concrete foundations before installing piping. Install piping in such a manner as not to place a strain on equipment. Do not bolt flanged joints tight unless they match. Grade, anchor, guide, and support piping without low pockets. Feedwater treatment feeders must be mounted so that the top of the feeder is no higher than 48 inches above the finished floor.

3.2 EQUIPMENT FOUNDATIONS

Locate equipment foundations as indicated, designed, and made of sufficient size and weight to preclude shifting of equipment under operating conditions or under abnormal conditions that could be imposed upon the equipment. Foundations must meet requirements of the equipment manufacturer. Concrete and grout must conform to Section 03 30 00

CAST-IN-PLACE CONCRETE.

3.3 MANUFACTURER'S FIELD SERVICES

Furnish the services of an engineer or technician approved by the boiler manufacture for installation inspection, startup, and tests of equipment as specified below. After installation of equipment the engineer or technician shall provide a signed certificate or certified written statement that the equipment is installed in accordance with the manufacturer's recommendations. Services of more than one engineer or technician may be required based on types of specific equipment. One engineer or technician as appointed by the Contractor shall supervise and be responsible for the overall installation, start-up, test, and check-out of systems. This person shall remain on the job until each unit has been in successful operation for 3 days and accepted.

3.4 BOILER CLEANING

Before being placed in service, flush out boiler with potable water, drain, and charge with chemically treated water. Protect boiler and appurtenances against internal corrosion until testing is completed and boiler is accepted. Professional services are required for cleaning/treatment process.

3.5 FIELD QUALITY CONTROL

Perform and furnish everything required for inspections and tests as specified herein to demonstrate that boiler and auxiliary equipment, as installed, are in compliance with contract requirements. Start-up and operate the system. During this time, clean strainers until no further accumulation of foreign material occurs. Exercise care to minimize loss

SECTION 23 52 43.00 20 Page 9 of water when strainers are cleaned. Adjust safety and automatic control instruments as necessary to place them in proper operation and sequence.

Test instrumentation must be calibrated and have full scale readings from

1.5 to 2 times test values.

3.5.1 Operational Tests

Furnish the services of an engineer or technician approved by the boiler manufacturer of installation, startup, operational and safety testing.

This person must remain on the job until each boiler has been successfully operated. Furnish and perform everything required for inspections and tests of the boiler and auxiliary equipment. Test instrumentation must be calibrated and have full-scale reading from 1.5 to 2 times test values.

Demonstrate proper operability of combustion control, flame safeguard control and safety interlocks. Provide a detailed description of all boiler startup and operational tests in the Commissioning Plan.

3.5.1.1 Preliminary Operational Test

Operate the boilers continuously for a period of at least 8 hours to demonstrate proper operability of the combustion control, flame safeguard control, and safety interlocks.

3.5.1.2 Acceptance Operational Test and Inspection

Prior to requesting an acceptance test, conduct a satisfactory operational test for at least 8 hours, and provide a certified statement that the equipment is installed per all requirements of this guide. Contracting Officer, upon receipt of the notice from the Contractor, will request a boiler inspection by a Naval Facilities Engineering and Expeditionary Warfare Center (EXWC) NAVFAC boiler inspector. Fifteen days advance notice is required for scheduling inspector to conduct acceptance operational test and inspection. All boilers and pressure vessels require certifications in accordance to UFC 3-430-07 prior to turning over to the Government. Request in writing that the government start the certification and acceptance testing procedure 120 days prior to the anticipated turnover date. The government boiler inspector shall be present and witness the startup of boiler systems. The Contractor is responsible for coordinating with the Boiler Inspector.

SECTION 23 52 43.00 20 Page 10

SECTION 23 64 10

WATER CHILLERS, VAPOR COMPRESSION TYPE

11/16

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AIR-CONDITIONING, HEATING AND REFRIGERATION INSTITUTE (AHRI)

AHRI 550/590 I-P (2015; ERTA 2016) Performance Rating Of Water-Chilling and Heat Pump Water-Heating Packages Using the Vapor Compression Cycle

AMERICAN BEARING MANUFACTURERS ASSOCIATION (ABMA)

ABMA 11 (2014) Load Ratings and Fatigue Life for Roller Bearings

ABMA 9 (2015) Load Ratings and Fatigue Life for Ball Bearings

AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING

ENGINEERS (ASHRAE)

ANSI/ASHRAE 15 & 34 (2016) ANSI/ASHRAE Standard 15-Safety Standard for Refrigeration Systems and ANSI/ASHRAE Standard 34-Designation and Safety Classification of Refrigerants

AMERICAN WELDING SOCIETY (AWS)

AWS Z49.1 (2012) Safety in Welding and Cutting and Allied Processes

ASME INTERNATIONAL (ASME)

ASME BPVC SEC VIII D1 (2017) BPVC Section VIII-Rules for Construction of Pressure Vessels Division 1

ASTM INTERNATIONAL (ASTM)

ASTM A307 (2014; E 2017) Standard Specification for Carbon Steel Bolts, Studs, and Threaded Rod 60 000 PSI Tensile Strength

ASTM B117 (2016) Standard Practice for Operating Salt Spray (Fog) Apparatus

ASTM D520 (2000; R 2011) Zinc Dust Pigment

ASTM E84 (2018a) Standard Test Method for Surface Burning Characteristics of Building

SECTION 23 64 10 Page 1

Materials

ASTM F104 (2011) Standard Classification System for Nonmetallic Gasket Materials

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

NEMA MG 1 (2016; SUPP 2016) Motors and Generators

NEMA MG 11 (1977; R 2012) Energy Management Guide for Selection and Use of Single Phase Motors

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

40 CFR 82 Protection of Stratospheric Ozone

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-03 Product Data

Self-Contained Water Chillers, Vapor Compression Type; G

Posted Instructions

Verification of Dimensions

Refrigerant

Demonstrations

Water Chiller - Field Acceptance Test Plan; G

SD-06 Test Reports

Field Acceptance Testing; G

Water Chiller - Field Acceptance Test Plan; G

Water Chiller - Field Acceptance Test Report

Water Chiller - Field Acceptance Test Report

System Performance Tests; G

SD-07 Certificates

Refrigeration System; G

Ozone Depleting Substances Technician Certification

SD-08 Manufacturer's Instructions

SECTION 23 64 10 Page 2

Water Chiller - Installation Instructions; G

SD-10 Operation and Maintenance Data

Operation and Maintenance Manuals; G

SD-11 Closeout Submittals

Indoor Air Quality During Construction; S

1.3 CERTIFICATIONS

1.3.1 Ozone Depleting Substances Technician Certification

All technicians working on equipment that contain ozone depleting refrigerants must be certified as a Section 608 Technician to meet requirements in 40 CFR 82 , Subpart F. Provide copies of technician certifications to the Contracting Officer at least 14 calendar days prior to work on any equipment containing these refrigerants.

1.4 SAFETY REQUIREMENTS

Exposed moving parts, parts that produce high operating temperature, parts which may be electrically energized, and parts that may be a hazard to operating personnel must be insulated, fully enclosed, guarded, or fitted with other types of safety devices. Safety devices must be installed so that proper operation of equipment is not impaired. Welding and cutting safety requirements must be in accordance with AWS Z49.1 .

1.5 DELIVERY, STORAGE, AND HANDLING

Stored items must be protected from the weather, humidity and temperature variations, dirt and dust, or other contaminants. Proper protection and care of all material both before and during installation will be the Contractor's responsibility. Any materials found to be damaged must be replaced at the Contractor's expense. During installation, piping and similar openings must be capped to keep out dirt and other foreign matter.

1.6 PROJECT REQUIREMENTS

1.6.1 Verification of Dimensions

The Contractor must become familiar with all details of the work, verify all dimensions in the field, and advise the Contracting Officer of any discrepancy before performing any work.

PART 2 PRODUCTS

2.1 STANDARD COMMERCIAL PRODUCTS

Materials and equipment will be standard Commercial cataloged products of a manufacturer regularly engaged in the manufacturing of such products, which are of a similar material, design and workmanship. These products must have a two year record of satisfactory field service prior to bid opening. The two year record of service must include applications of equipment and materials under similar circumstances and of similar size.

Products having less than a two year record of satisfactory field service will be acceptable if a certified record of satisfactory field service for not less than 6000 hours can be shown. The 6000 hour service record must

SECTION 23 64 10 Page 3 not include any manufacturer's prototype or factory testing. Satisfactory field service must have been completed by a product that has been, and presently is being sold or offered for sale on the commercial market through the following copyrighted means: advertisements, manufacturer's catalogs, or brochures.

2.2 MANUFACTURER'S STANDARD NAMEPLATES

Nameplates are required on major components if the manufacturer needs to provide specific engineering and manufacturing…