This federal solicitation requests proposals for the design and construction of an F-35 training and simulator facility at Marine Corps Air Station Cherry Point in North Carolina. The project scope includes constructing a 64,700 square foot facility for simulators, classrooms, administrative space, and related site work. Proposals are due on April 9, 2020. The magnitude of construction is between $25 million and $100 million. The NAICS code is 236210 for industrial building construction, and the small business size standard is $39.5 million. This is an unrestricted solicitation with full and open competition.
The document provides instructions to offerors, including requirements for the price and non-price proposal submissions, evaluation criteria, and past performance information. Price factors include the base work and options for demolition, parking lots, electronic security systems, furniture/fixtures/equipment, and audio/visual work. Non-price factors for evaluation are corporate experience, small business utilization, safety, and past performance. Submission requirements and response due dates are also outlined.
View the file
Other files
Show 40 more
Latest 50 of 69 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION NO. N40085-20-R-0015 DESIGN-BID-BUILD (DBB) P-204 F-35 TRAINING AND SIMULATOR FACILITY, MARINE CORPS AIR
STATION CHERRY POINT, NORTH CAROLINA
PROPOSALS ARE DUE ON THURSDAY, 09 APRIL 2020, AT 2:00 EDT. REFER TO SECTION 00 21 16 FOR PROPOSAL DELIVERY INFORMATION.
PRE-PROPOSAL INQUIRIES (PPI) CUT-OFF IS 10 DAYS PRIOR TO PROPOSAL DUE DATE, AT 5:00 PM EDT. ALL PPIS SHALL BE SUBMITTED TO
CRYSTAL CHATMON VIA EMAIL AT CRYSTAL.CHATMON@NAVY.MIL
MAGNITUDE OF CONSTRUCTION FOR THIS PROJECT IS BETWEEN $25,000,000 AND $100,000,000 IN ACCORDANCE WITH DFARS 236.204.
NAICS CODE IS 236210 – INDUSTRIAL BUILDING CONSTRUCTION, AND THE SMALL BUSINESS SIZE STANDARD IS $39,500,000. THIS ACQUISITION IS BEING SOLICITED ON AN UNRESTRICTED BASIS WITH FULL AND OPEN COMPETITION.
WAGE DETERMINATION GENERAL DECISION NUMBER: NC20200065 01/03/2020
CRYSTAL Y. CHATMON 757-341-1999
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
12-Mar-2020
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
X
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______15 calendar days and complete it w ithin ________577 calendar days after receiving aw ard, notice to proceed. This performance period is mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________4 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________09 Apr 2020 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
NAVFAC MID ATLANTIC
ACQUISITION CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
N4008520R0015 49
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
N4008520R0015
Section 00 00 00 - Procurement and Contracting Requirements
WAGE DETERMINATION
"General Decision Number: NC20200065 01/03/2020
Superseded General Decision Number: NC20190065
State: North Carolina
Construction Type: Building
Counties: Chowan, Craven, Dare, Gates, Jones, Martin and Washington Counties in North Carolina.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015.
If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate, if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2020
* PLUM0421-004 07/01/2018
Rates Fringes
PIPEFITTER (Excluding HVAC System Installation).............$ 28.00 12.01
SUNC2011-046 08/26/2011
Rates Fringes
BRICKLAYER.......................$ 19.38 8.73
CARPENTER (Drywall Hanging Only)............................$ 18.13 1.31
CARPENTER (Form Work Only).......$ 14.21 0.41
CARPENTER, Excludes Drywall Hanging, and Form Work...........$ 14.64 2.39
CEMENT MASON/CONCRETE FINISHER...$ 14.02 0.00
ELECTRICIAN......................$ 17.10 1.47
HVAC MECHANIC (HVAC Duct Installation Only)...............$ 15.58 1.53
IRONWORKER, STRUCTURAL...........$ 18.75 5.62
LABORER: Common or General......$ 10.57 0.67
LABORER: Landscape & Irrigation.......................$ 10.29 1.82
LABORER: Mason Tender-Brick/Cement/Concrete.....$ 10.00 0.00
OPERATOR:
Backhoe/Excavator/Trackhoe.......$ 14.71 2.33
OPERATOR: Crane.................$ 19.25 2.37
OPERATOR: Grader/Blade..........$ 15.71 1.49
PAINTER: Brush, Roller and Spray............................$ 14.36 1.97
PLUMBER (HVAC Unit Installation)....................$ 16.96 3.17
PLUMBER, Excludes HVAC Unit Installation.....................$ 17.34 2.09
ROOFER...........................$ 13.55 0.80
SHEET METAL WORKER, Excludes HVAC Duct and Unit Installation.....................$ 13.09 1.28
TRUCK DRIVER: Dump Truck........$ 12.50 1.21
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
Section 00 10 00 - Solicitation
INSTRUCTIONS TO OFFERORS
INSTRUCTIONS TO OFFERORS
1. GENERAL
1.1 GENERAL OVERVIEW OF PROCUREMENT PROCESS
1.2 GENERAL OVERVIEW OF CONTRACT
2. BASIS FOR AWARD
3. EVALUATION FACTORS FOR AWARD
4. PROPOSAL REQUIREMENTS
4.1 PRE-PROPOSAL CONFERENCE AND SITE VISIT (PHASE II)
4.2 PROPOSAL SUBMISSION INSTRUCTIONS
4.3 PRE-PROPOSAL INQUIRIES (PPIs)
4.4 BETA.SAM.GOV (BETASAM)
5. INCORPORATION OF TECHNICAL PROPOSAL
6. ATTACHMENTS: LOCATED ON BETA SAM
5.1 ATTACHMENT A - PRE-PROPOSAL INQUIRY LOG
5.2 ATTACHMENT B - SECNAV 5512 – BASE ACCESS FORM (Naval Station Norfolk)
5.3 ATTACHMENT C – CONSTRUCTION EXPERIENCE AND PROJECT DATA SHEET
5.4 ATTACHMENT D - SMALL BUSINESS SUBCONTRACTING RECORD
5.5 ATTACHMENT E - SMALL BUSINESS PART. AND COMMITMENT STRATEGY
5.6 ATTACHMENT F – PAST PERFORMANCE QUESTIONAIRE
5.7 ATTACHMENT G – SMALL BUSINESS SUBCONTRACTING PLAN TEMPLATE
5.8 ATTACHMENT H – ONE DAY PASS REQUEST FORM
5.9 ATTACHMENT I- PRICE PROPOSAL FORM
5.10 ATTACHMENT J- SITE VISIT MAP
1. GENERAL OVERVIEW OF PROCUREMENT PROCESS
1.1.1 This solicitation is being issued as Unrestricted Full and Open Competition.
1.1.2 The NAICS code for this procurement is 236210 and the size standard is $39,500,000
1.1.3 This acquisition will be advertised utilizing FAR Part 36, Design Bid Build Source Selection Procedures and 15 – Contracting by Negotiations resulting in a Firm Fixed Price (FFP) contract for construction services.
1.1.4 Magnitude of Construction: Between $25,000,000 and $100,000,000.
1.2 GENERAL OVERVIEW OF CONTRACT
Description of Work:
Constructs a one story 64,700 SF F-35 Simulator Facility that will support six (6) Mission Rehearsal Trainers/Full Mission Simulators, six (6) Deployable Mission Rehearsal Trainers, and support spaces which will include administrative, classroom, and conference space. The facility will also include space for Marine Aviation Training Systems Site (MATSS) and Night Imagining and Threat Evaluation (NITE) lab. The facility will be a reinforced concrete masonry unit building with seismic upgrades on a pile supported reinforced concrete slab on grade foundation with structural steel framing and a pre-finished insulated roof system with renewable energy features.
Structural elements will allow for the expansion of the facility in the future if required. The facility will be constructed and certified for secure handling and storage of classified material and components up to top secret/special access program facility classifications.
Information systems include telephone, computer networks such as SIPRNet and NIPRNet etc., fiber optic, cable television, security, Autonomic Logistics Information System (ALIS), energy saving electronic monitoring and control system (EMCS), and fire alarm and mass notification system.
This project will provide Anti-Terrorism/Force Protection (ATFP) features and comply with ATFP regulations, physical security and progressive collapse mitigation in accordance with DOD Minimum Anti-Terrorism Standards for Buildings.
Built-in equipment includes uninterruptible power supply, emergency generator, roll-up doors, air conditioning units, raised flooring, lockers, and training/display cases.
Special costs include Post Construction Contract Award Services (PCAS) (which includes geospatial surveys and mapping) and Special Access Program Facility (SAPF) areas.
Operations and Maintenance Support Information (OMSI) is included in this project.
Sustainable design principles and Low Impact Development (LID) will be included in the design and construction of the project in accordance with Executive Order 13423 and other laws and Executive Orders.
Site preparation includes site clearing, excavation and demolition of Building 286 for preparation for construction.
Paving and site improvements include grading, paving, curbs, sidewalks, landscaping, security fencing, trash enclosure, and storm-water management.
Electrical utilities include primary and secondary distribution systems, lighting, transformers and telecommunications infrastructure.
Mechanical utilities include heating, ventilation and air conditioning, water lines, plumbing and plumbing fixtures, sanitary sewer lines, fire protection systems and supply lines.
This project will include the demolition of the following facilities: Building #286 (1781 SM/19,176 SF), Building #4038 (3877 SM/41,731 SF), and Building #4162 (62 SM/667 SF).
All facilities are being demolished to clear the site for this project. Many of the uses will be relocated or incorporated into the project.
Facilities will be designed to meet or exceed the useful service life specified in DoD Unified Facilities Criteria.
Facilities will incorporate features that provide the lowest practical life cycle cost solutions satisfying the facility requirements with the goal of maximizing energy efficiency.
2. BASIS FOR AWARD
i. The Government reserves the right to eliminate from consideration for award any or all offers at any time prior to award of the contract; to negotiate with offerors in the competitive range;
and to award the contract to the offeror submitting the proposal determined to represent the best value—the proposal most advantageous to the Government, price and other factors considered.
ii. The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. In addition, if the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
iii. The tradeoff process is selected as appropriate for this acquisition. The Government considers it to be in its best interest to allow consideration of award to other than the lowest priced offeror or other than the highest technically rated offeror.
iv. As stated in the solicitation, all technical factors, when combined, are of equal importance to the performance confidence assessment (past performance) rating; and all technical factors and the performance confidence assessment (past performance) rating, when combined, are approximately equal to price.
v. Any proposal found to have a Deficiency in meeting the stated solicitation requirements or performance objectives will be considered ineligible for award, unless the Deficiency is corrected through discussions. Proposals may be found to have either a Significant Weakness or multiple Weaknesses that impact either the individual factor rating or the overall rating for the proposal. The evaluation report must document the evaluation board’s assessment of the identified Weakness(s) and the associated risk to successful contract performance resulting from the Weakness(s). This assessment must provide the rationale for proceeding to award without discussions.
3. EVALUATION FACTORS FOR AWARD
i. The solicitation requires the evaluation of price and the following non-price factors:
Factor 1– Corporate Experience Factor 2 – Small Business Utilization Factor 3 – Safety Factor 4 – Past Performance
The distinction between Corporate Experience and Past Performance is that Corporate Experience pertains to the volume of work completed by a contractor that are comparable to the types of work described under the definition of recent, relevant projects, in terms of size, scope, and complexity. Past Performance pertains to both the relevance of recent efforts and how well a contractor has performed on the contracts.
The relative order of importance of the non-cost/price evaluation factors is the technical factors (Factors 1, 2, and 3) are of equal importance to each other, respectively, and, when combined, are equal in importance to the past performance evaluation/performance confidence assessment factor, Factor 4.
When the proposal is evaluated as a whole, the technical factors and past performance/performance confidence assessment factor combined (i.e., the non-cost/price evaluation factors) are approximately equal to price.
The importance of price will increase if the Offerors’ non-cost/price proposals are considered essentially equal in terms of overall quality, or if price is so high as to significantly diminish the value of a non-cost/price proposal’s superiority to the Government. Award will be made to the responsible Offeror(s) whose offer conforms to the solicitation and represents the best value to the Government, price and non-price factors considered.
ii. Basis of Evaluation and Submittal Requirements for Each Factor.
(a) Price:
(1) Solicitation Submittal Requirements:
The offeror shall submit one (1) original, marked “Original”, and one (1) copy, marked “Copy”, in a separate three ring binder (1/2 inch minimum) with the following:
Include a cover page with Solicitation Number, Solicitation
Title, Prime Contractor Name, Address, Phone Number, Fax Number, DUNS Number, Cage Code, Point of Contact, and E-mail Address;
Completed SF 1442 signed with all amendments acknowledged;
Price Proposal Form;
Copy of Representation and Certifications and proof of registration in System for Award Management (SAM);
Confirmation of filing of Veterans’ Employment and Training (VETS) VETS- 4212 for the 2019 filing cycle;
Bid Guarantee in accordance with FAR Clause 52.228-1 – Bid Guarantee (amount shall be at least 20 percent of the proposed price, but shall not exceed $3 million); and
Responsibility Determination Information (see below).
Small Business Subcontracting Plan
The offeror is required to submit a complete Price Proposal Form that includes completion of all contract line item numbers (CLINs).
In the event of a discrepancy between the original and copies, the original version of the proposal will govern. Furthermore, any price information within the technical proposal (non-price proposal) will not be considered. Likewise, any technical/non-price information within the price proposal will not be considered.
ADDITIONAL INFORMATION TO BE SUBMITTED WITH PRICE
PROPOSAL PACKAGE:
RESPONSIBILITY DETERMINATION INFORMATION – In order to be eligible for award, the offeror must be determined responsible in accordance with FAR Part 9, specifically FAR 9.104-1, General Standards. In a separate tab, the offeror shall provide the following information in the price proposal package:
One (1) signed bank reference demonstrating adequate financial resources. If offeror’s firm has a line of credit – provide information on how many figures offeror can borrow against the line of credit (i.e. medium 6 figures – exact line of credit is not required).
The offeror shall provide the latest three complete fiscal year financial statements for the prime contractor, certified by an independent accounting firm, if practicable, or signed by an authorized officer of the organization.
Submit evidence of availability of working/operating capital, which will be used for the performance of the resultant contract. For Joint Venture arrangements, submit the latest three complete fiscal year financial statements for each company in the Joint Venture and discuss the financial responsibilities among the companies. The Government may also utilize Dun & Bradstreet reports to evaluate the financial capacity of the offeror.
Description of offeror’s facilities and equipment.
Other offeror’s work presently under contract.
Small Business Subcontracting Plan (reference FAR 52.219-9 Alt II and
DFARS 252.219- 7003).
NAVFAC's command-wide small business subcontracting targets are shown below. These may be higher or lower than percentages that would represent realistic, challenging small business subcontracting goals for this acquisition. Offerors representing as other than small businesses shall establish small business subcontracting plan goals and shall document in their subcontracting plans the basis for all proposed goals. Plans shall be submitted with initial offers.
SB 40%
SDB 5%
HUBZone SB 3%
WOSB 9%
SDVOSB 3%
Small businesses identified by name shall be listed in small business subcontracting plans submitted pursuant to FAR 52.219-9 in order to facilitate compliance with DFARS 252.219- 7003(e).
See the Small Business Subcontracting Plan Template (Attachment E) for format.
Although required to be submitted with offeror’s price proposal, this information will not be evaluated as part of the price proposal. This information forms the basis of your firm’s responsibility determination should your firm be considered for award. Proposal packages from unsuccessful offerors will not be returned to the offeror, but shall be destroyed by the Contracting Officer. No certificate of destruction will be issued.
(2) Basis of Evaluation:
The Government will evaluate price based on the total price. Total price consists of the basic requirements and all option items (see attached Price Proposal Form). The Government intends to evaluate all options and has included the provision FAR 52.217-5, Evaluation of Options (JUL 1990) in Section 00600 of the solicitation. In accordance with FAR 52.217-5, Evaluation of Options, will not obligate the Government to exercise the option(s). Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:
(i) Comparison of proposed prices received in response to the RFP.
(ii) Comparison of proposed prices with the IGCE.
(iii) Comparison of proposed prices with available historical information.
(iv) Comparison of market survey results.
(b) Non-Price Factors:
Non-price binder: The offeror shall submit one (1) original, marked “Original”, and three (3) copies, marked “Copy”, each in a separate three ring binder with the following:
Cover page with Solicitation Number, Solicitation Title, Prime Contractor Name, Address, Phone Number, Fax Number, DUNS, Cage Code, Point of Contact, Phone Number, and Email Address;
8 ½ x 11 paper, 12-point font;
Refer to individual factors for page limitations. Pages that exceed indicated page limitations shall not be evaluated;
Additionally, include an electronic version of the non-price proposals on CD- ROM.
As with the price proposal, in the event of a discrepancy between the original and copies (or CD- ROM), the original version of the proposal will govern. Furthermore, any price information within the technical proposal (non-price proposal) will not be considered.
Likewise, any technical/non-price information within the price proposal will not be considered.
(1) Factor 1, Corporate Experience:
(i) Solicitation Submittal Requirements: The offeror shall submit the following information:
Submit a minimum of two (2) and a maximum of five (5) relevant construction projects for the offeror that best demonstrates your experience on relevant projects that are similar in size, scope, and complexity to the RFP. The Government will not consider more than five projects and will review only the first five projects if more are submitted.
For purposes of this evaluation, a relevant project is further defined as:
Size: A single building with a cumulative square footage of 40,000 SF or greater and a final construction cost of $15 million or greater.
Scope: New construction of a simulator facility. Renovations are not permitted.
Note: Additions comprised of a new footprint will only be considered New Construction for the purposes of this evaluation if the new footprint meets the above Size/Scope and at least one element of Complexity as stated below.
Complexity: While also meeting the Size and Scope requirements set out above, the following Complexity requirements shall be met collectively by the projects submitted, i.e., each submitted project does not require demonstrated experience with all of the following components, but, collectively, experience with all of the Complexity elements below must be established throughout the submitted relevant projects or the proposal will be found Unacceptable. Furthermore, each project must meet the above-defined Size and Scope and, at least, one of the following complexity requirements:
a) Experience constructing reinforced concrete, steel, and CMU construction projects on a deep foundation;
b) Experience constructing a facility with multiple high bays.
Projects submitted shall be completed within ten (10) years prior to the date of issuance of the RFP or will be considered Not Relevant. If the offeror does not clearly state the project completion date, the SSEB may determine that the project is Not Relevant.
A project is defined as a construction project performed under a single task order or contract. For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project; rather offerors shall submit the work performed under a task order as a project.
Ensure that the project description clearly identifies whether the project is new construction, retrofit, or expansion, and addresses and clearly demonstrates how the project meets the Size, Scope, and Complexity requirements as delineated above, and provides the final construction cost. The absence of any such information, or if the information provided does not clearly address these requirements, may result in a rating of UNACCEPTABLE.
The attached Construction Experience Project Data Sheet (Attachment C) is MANDATORY and SHALL be used to submit project information, including the project square footage, for each project. Except as specifically requested, the Government will not consider information submitted in addition to this form nor will the Government consider information submitted via any other medium. Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed one (1) double-sided page (or two (2) single-sided pages). Information beyond this page limit will not be considered.
For all submitted projects, the description of the project shall clearly describe the scope of work performed and the relevancy to the project requirements of this RFP (i.e.: unique features, area, construction methods) as defined above by Size, Scope, and Complexity. The Government may determine that the project is not relevant if the offeror does not clearly demonstrate how each project meets the Size, Scope, and Complexity requirements. In addition, the description should also address any sustainable features for the project, including specific descriptions of those features. Provide applicable documentation on projects that were validated and/or certified through U.S. Green Building Council (USGBC) or the equivalent organization or process.
If the offeror is a Joint Venture (JV), relevant project experience must be submitted for projects completed by the Joint Venture entity. However, if the Joint Venture does not have shared experience, projects should be submitted for all Joint Venture members. Offerors who fail to submit experience for all Joint Venture members may be rated lower. Offerors are still limited to a total of five (5) projects combined.
If an offeror is utilizing experience information of affiliates/subsidiaries/parent/LLC/LTD member companies (name is not exactly as stated on the SF1442), the proposal shall clearly demonstrate and explain as to how the affiliate/subsidiary/parent firm will have meaningful involvement in the performance of the contract.
Experience of proposed subcontractors will not be considered. Likewise, the Offeror’s experience as a subcontractor will not be considered.
(ii) Basis of Evaluation:
The basis of evaluation will include the offeror’s demonstrated experience and depth of experience in performing relevant construction projects as defined above in the solicitation submittal requirements. The assessment of the offeror’s relevant experience will be used as a means of evaluating the capability of the offeror to successfully meet the requirements of the RFP. The Government will only review five projects. Any projects submitted in excess of the first five will not be considered.
Relevant projects that demonstrate experience with sustainable features may be considered more favorably than those that do not demonstrate experience with sustainable features.
Relevant projects that demonstrate experience with a Sensitive Compartmented Information Facility (SCIF) may be considered more favorably than those that do not demonstrate experience with SCIF.
(2) Factor 2, Small Business Utilization:
This Factor assesses both the historical achievements in utilizing small business concerns as subcontractors and proposed small business participation and commitment strategies.
(i) Solicitation Submittal Requirements:
1. Achievements: All offerors shall provide a narrative (limited to two pages) to describe their achievements in supporting the Government’s policy to provide maximum practicable opportunities for small business (SB), veteran-owned small business (VOSB), service-disabled veteran-owned small business (SDVOSB), historically underutilized business zone (HUBZone) small business, small disadvantaged business (SDB), and women-owned small business (WOSB) concerns to participate as subcontractors consistent with efficient contract performance. In support of narrative submissions:
a. All offerors shall submit small business subcontracting information associated with each project cited under the Corporate Experience Factor in the format provided in Attachment C, Small Business Subcontracting Record.
b. Offerors representing as other than small businesses shall also provide copies of the most current individual subcontracting reports (ISRs) associated with each project cited under the Corporate Experience Factor if a small business subcontracting plan was required by the contract. If such projects were completed under specific task orders, provide ISRs for the overall contract. For cited projects with state and local government agencies, provide similar subcontracting performance reports if required by the contracts. When not specifically addressed in the ISR or similar report, offerors shall provide explanations for all instances of failures to meet dollar or percentage goals in individual subcontracting plans.
Notes: The Government reserves the right to consider achievements information on other recent, relevant projects from all available sources.
Offerors utilizing achievements information of team members or key subcontractors shall clearly demonstrate how these companies will have meaningful involvement in the management of the subcontracting program for this acquisition. If not, such achievement information will not be considered under this factor. If the offeror is a new joint venture, partnership or other entity consisting of more than one company, provide achievements information for each individual business entity(ies) that will be responsible for managing the subcontracting program and clearly describe those responsibilities.
Failure to provide ISRs or any other requested information must be fully explained and may negatively impact your evaluation.
2. Small Business Participation and Commitment: All offerors shall submit a small business participation and commitment strategy including all data elements shown in Attachment E, Small Business Participation and Commitment Strategy.
a. Identify in terms of dollar value and percentage of the total acquisition the extent of work the offeror will self-perform as the prime contractor. If submitting an offer as a joint venture, identify the percentage of work each member will be responsible for and indicate the size status of each member (e.g. small business, woman-owned small business, other than small business).
b. Include supplemental narratives (limited to five pages) to address other elements of the offeror’s strategy such as binding agreements covering post award roles for execution of the contract and specific initiatives and tools that will be employed under the contract to enhance small businesses opportunities to both participate in this acquisition and build capabilities to support future NAVFAC acquisitions.
c. The anticipated prime and first tier overall small business participation rate for this acquisition (i.e. work to be performed by small businesses as the prime and/or subcontractors) is 20% of the contract value. Offerors are encouraged to exceed this percentage and seek meaningful levels of participation in each of the small business socioeconomic programs listed in Attachment E consistent with efficient contract performance. Offerors shall explain in their participation and commitment strategies how proposed participation rates were established. The small business participation and commitment strategy must be in agreement with any required small business subcontracting plan and will be made a part of the contract upon award.
Offerors will be evaluated on the extent to which their proposals and other performance information available to the Government demonstrate a history of successfully supporting Government policies concerning utilization of small business concerns as subcontractors including, when applicable, achievements against established small business subcontracting plan goals. Offerors will also be evaluated on the levels of small business participation proposed and the degree of commitment to use named sources. The anticipated benefits of proposed initiatives and tools to enhance small business participation and capabilities will be considered. The Government will assess proposal realism and the likelihood of success in achieving the small business objectives of this acquisition.
Attachment D – Small Business Subcontracting Record Attachment E – Small Business Participation and Commitment Strategy
(3) Factor 3, Safety:
The Offeror shall submit a narrative that fully describes the safety management system that they will use to oversee the safety compliance and performance of self-performed and sub-contractor performed work and the Offeror’s method for qualifying, evaluating, selecting all tiers of sub- contractors. The narrative shall include:
(1) Experience Modification Rate (EMR): The Offeror must include three previous calendar years’ worth of data (2017, 2018, 2019). This rate compares company’s annual losses in insurance claims against its policy premiums. The Offeror may submit an insurance company-provided equivalent rate if no EMR exists. If there is no EMR premium, for any year, the Offeror must affirmatively state so and explain why. Any extenuating circumstances that affect the EMR and negative trends should be addressed as part of the element.
(2) OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART) Rates: The Offeror must submit three previous calendar years’ worth of data (2017, 2018, 2019). If the OSHA DART and TRC rates cannot be submitted for any year, the Offeror must affirmatively state so and explain why. Any extenuating circumstances that affected the OSHA DART rate data negatively should be addressed as part of this element.
(3) OSHA Total Recordable Case (TRC) Rate: The Offeror must submit three previous complete calendar years’ worth of data (2017, 2018, and 2019).
If an offeror cannot submit OSHA TRC rates for any year, the offeror must affirmatively state so and an explanation must be provided. Any extenuating circumstances that affected the OSHA TRC rate data negatively must be addressed as part of this factor submission.
(4) Technical Approach for Safety: The technical approach to safety narrative shall be limited to one (1) double-sided page (or two (2) single-sided pages), and must address all items below.
1. The offeror shall describe the plan for safety that will be implemented to evaluate safety performance of potential subcontractors as part of the selection process for all levels of subcontractors.
2. The offeror shall submit a narrative that fully describes the safety management system that they will use to oversee the safety compliance and performance of self-performed and subcontractor performed work.
3. The offeror shall describe any innovative methods that will be employed to ensure and monitor safe work practices at self-performed and/or all subcontractor levels.
4. The offeror shall describe their methodology to execute an effective program that facilitates sound mishap prevention techniques and processes, employee reporting of unsafe conditions, unsafe activities, and near-miss mishaps.
Information beyond this page limit will not be considered.
Note: The narrative shall be limited to two pages. For a partnership or joint venture, the submittal requirements are required for each contractor who is part of the partnership or joint venture; however, only one safety narrative is required. Safety narratives for joint ventures may be up to four pages in length.
(ii) Basis of Evaluation: The evaluation will collectively consider the following:
- Experience Modification Rate (EMR)
- OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART)
- Total Recordable Case (TRC) Rates
- Offeror Technical Approach to Safety
- Other sources of information available to the Government
(1) Experience Modification Rate (EMR): For the three previous complete calendar years (2017, 2018, 2019), the offeror will submit EMR. If no EMR exists, the offeror may submit an insurance company-provided equivalent rate explaining why not. If an insurance company-provided equivalent rate is provided, it will be treated the same as an EMR. Any extenuating circumstances that affected the EMR and negative trends must be addressed as part of this selection factor. The board will evaluate the EMR to determine if the offeror has demonstrated a history of safe work practices taking into account any negative trends and extenuating circumstances that impact the rating.
(2) OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART) Rates: For the three previous complete calendar years (2017, 2018, 2019), the offeror will submit their OSHA DART, as defined by the U.S. Department of Labor, Occupational Safety and Health Administration. If unable to submit OSHA DART rates, the offeror must affirmatively state so, and an explanation must be provided. Any extenuating circumstances that affected the OSHA DART rate data and negative trends must be addressed as part of this element. The board will evaluate the OSHA DART rates to determine if the offeror has demonstrated a history of safe work practices taking into account any upward trends and extenuating circumstances that impact rates.
(3) OSHA Total Recordable Case (TRC) Rates: For the three previous complete calendar years, the offeror will submit their OSHA TRC rates, as defined by the U.S. Department of Labor, Occupational Safety and Health Administration.
If unable to submit OSHA TRC rates, the offeror must affirmatively state so, and an explanation must be provided. Any extenuating circumstances that affected the OSHA TRC rate data and negative trends must be addressed as part of this element. The board will evaluate the OSHA TRC rates to determine if the offeror has demonstrated a history of safe work practices taking into account any upward trends and extenuating circumstances that impact rates.
(4) Technical Approach to Safety: The offeror will describe their plan to evaluate their safety performance and that of potential subcontractors. Also, describe any innovative methods that the offeror will employ to ensure and monitor safe work practices at all subcontractor levels. The Safety Narrative shall be limited to two pages. The board will evaluate the narrative to determine the degree to which subcontractor safety performance will be considered in the selection of all levels of subcontractors on the upcoming project. The board will evaluate the narrative to determine the degree to which innovations are being proposed that may enhance safety on this procurement and validate the contractor has addressed methodology to be used in the execution of an effective program that facilitates sound mishap prevention techniques/processes, employee reporting of unsafe conditions, unsafe activities, and near-miss mishaps.
(5) Other Sources of Information Available to the Government: Other sources for safety may include but are not limited to OSHA data, NAVFAC’s Contractor Incident Reporting System (CIRS) in Enterprise Safety Applications Management System (ESAMS), Contractor Performance Assessment Reporting System (CPARS) and other related databases.
(c) Past Performance
(1) Factor 4, Past Performance:
IF A COMPLETED CPARS EVALUATION IS AVAILABLE, IT SHALL BE
SUBMITTED WITH THE PROPOSAL. IF THERE IS NOT A COMPLETED CPARS
EVALUATION, the Past Performance Questionnaire (PPQ) included in the solicitation is provided for the offeror or its team members to submit to the client for each project the offeror includes in its proposal for Factor 1 – Corporate Experience. AN OFFEROR SHALL NOT SUBMIT A
PPQ WHEN A COMPLETED CPARS IS AVAILABLE.
IF A CPARS EVALUATION IS NOT AVAILABLE, the offeror must ensure correct phone numbers and email addresses are provided for the client point of contact. Completed PPQs should be submitted with your proposal. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror must complete and submit with the proposal the first page of the PPQ (Attachment D) with contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government's point of contact, Ms. Crystal
Chatmon, via email at crystal.chatmon@navy.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs or CPARS previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.
In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS) using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owner representative(s), and any other known sources not provided by the offeror.
While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with…