Amendment 0002 Extend Proposal Due Date.pdf
PDF 652 KB Posted
- Solicitation number
- N4008520R0015
About this file
This document provides an amendment to a solicitation for the design and construction of an F-35 training and simulator facility at Marine Corps Air Station Cherry Point in North Carolina. The amendment extends the proposal due date from April 9, 2020 to April 30, 2020 at 2:00pm Eastern time in response to the impacts of the COVID-19 pandemic. It provides responses to 21 questions from potential offerors seeking clarification on various requirements for structural components, fire protection systems, contaminated soil handling, and commissioning responsibilities. The Naval Facilities Engineering Command is seeking proposals for a fixed-price contract with a magnitude between $25-100 million to design and construct the training facility in accordance with plans and specifications. The NAICS code is 236210 and small businesses qualify up to $39.5 million.
View the file
Other files
Show 40 more
Latest 50 of 69 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
**** PROPOSAL DUE DATE HAS CHANGED****
The purpose of this amendment is to:
1. Extend the proposal due date from 09 April 2020 to 30 April 2020 at 2:00pm.
2. Provide responses to PPIs.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 7
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 31-Mar-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N4008520R0015
X 9B. DATED (SEE ITEM 11)
12-Mar-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
31-Mar-2020
CODE
NAVFAC MID ATLANTIC
ACQUISITION CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008520R0015
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 00002
Questio n No.
Date Recei ved
REFERENCE QUESTION GOVERNMENT RESPONSE Poste d on Amen d No.
Page Section Para.
1 3/18/
13 Factor 1 5 Factor 1, Corporate Experience states “Scope: New construction of a simulator facility”. Will similar complex construction types be viewed as relevant such as active hospitals which have Operating Rooms or CT Scans, IT Facilities, or Laboratories with heavy coordination between with owner or contractor provided prefabricated equipment (similar to simulators) be considered as relevant experience?
Each submitted project must meet the Size and Scope requirements and, at least, one of the listed complexity requirements.
Propose according to the
RFP.
2 3/24/
With the virus and everyone trying yo work from home subcontractors are asking for 3 week extension will this be possible?
Please see Amendment
3 3/24/
RFP Given the current crippling effect the COVID19 Pandemic has placed on the entire country, General Contractors, Subcontractors, and Vendors are all subject to it. Some are having to work from home, others aren't allowed to work or can't access files/information they need, and at best, those that are working are not able to operate at full speed in terms of estimating, take-offs, pricing efforts, etc. Please consider a two week bid extension from April 9th to April 23rd to allow the necessary time for the market to propose on this project in unforeseen and uncontrollable circumstances.
Please see Amendment
4 3/24/
S-513 Joist reinforcing detail is given on C3/S-513, please indicate where this is need on the structural drawings as this detail is not referenced.
Joist hanger detail C3/S- 513 is provided as an option for locations where hanging loads fall between joist locations.
5 3/24/
05 12 00 05 12 00-2.6.2 clarifies zinc rich primer for all structural steel. This is a significant cost premium over standard primer, especially on non-exposed structural steel. Please confirm it is required.
Standard shop primer may be used for interior, non-exposed structural steel.
6 3/24/
05 12 00 AISC certified erector and fabricator are required per 05 12 00-
1.3. Please consider
removing the AISC certified erector requirement for additional competition.
AISC certifications may be waived provided a similar certification and QC program is being followed. Refer to IBC 2015 Section 1704.2.5 for additional special inspection requirements in lieu of approved detailed fabrication and quality control procedures.
7 3/24/
21 00 00 Please confirm that no clean agent fire suppression systems are required in any rooms such as server rooms, simulator areas, etc.
Confirmed. Clean agent system is not required for this project.
8 3/24/
21 30 00 Please confirm which start method will be required on the controller for the fire pump, and if a transfer switch is needed.
Refer to Specification 21 30 00, section 2.7.1 for start method and ATS requirements.
9 3/24/
M-603 The Duct Silencer Schedule on M-603 has lines for DS-13 and DS-14 with no information listed next to it. Please confirm only DS-1 through DS- 6 is applicable.
Only DS-1 through DS-6 are required. DS-13 and DS-14 were printed by error and can be disregarded.
10 3/24/
RFP Item 1.2
Under item 1.2 General Overview of Contract - Description of Work it is noted, "The facility will be a reinforced concrete masonry unit building with seismic upgrades on a pile supported reinforced concrete slab on grade foundation." The structural plans do not show a pile foundation, the geotechnical report does not recommend one, and there is not a specification for a pile
Confirmed. Piles are not anticipated for this project.
foundation. Please confirm that there will NOT be a pile foundation required.
12 3/24/
C-008, C-009
Plans C-008 and C-009 indicate contaminated soils located within the limits of construction (and confirmed in CLIN 0001AF). The water table in this area will likely be encountered during construction.
Due to the contaminated soils, the water will also be contaminated and will need to be treated and legally disposed
of. Please provide a quantity and unit price line item on the bid form for treatment of contaminated water.
Provide bid as specified. 0002
14 3/24/
01 45
00.00 20
1.5.2 The Quality Control
spec reads that a commissioning authority is to be provided for the project in 1.5.2.1.
Spec 01 91 00.15 22,
1.1 very clearly notes the CxA will be provided by the Gov't.
Please confirm these are the same firm/person, and will be provided by the Gov't.
CxA is to be provided by govt.
15 3/25/
1 Solicitati on
In light of “Stay at Home Orders” issued across multiple states, counties and cities, and the uncertainty resulting from the national emergency declared as a result of the COVID-19 Pandemic. Our operations, and that of the subcontractor market, have been severely impacted. For this reason we are requesting a 2 week extension of this bid.
Please see Amendment
16 3/25/
Due to Amendment 0001 cancelling the site visit, will the demolition contractors have the opportunity to visit the jobsite to view the three buildings to be demolished? Will there be an opportunity for general contractors and any other subcontractors to visit the jobsite?
Due to COVID-19 pandemic and the increasing state and local governments issuing “shelter in place” policies, there will no longer be a site visit for this solicitation. Please utilize the drawings and specifications when preparing your proposal.
17 3/25/
A4/A52
Please provide a specification for the pre-cast concrete sills at the windows as shown on detail A4/A526.
Refer to specification 04 20 00, section 2.2.4.
18 3/25/
Is the general contractor to submit pricing as shown on pages 25-27 of 29 of the RFP, with Item No's 0001, 0002, 0003, 0004, 0005, 0006 and 0007 or is the general contractor to submit pricing as shown in Document 00 22 13.00 20 - Supplementary Instructions to
Please use Attachment I- Price Proposal Form
Offerors with CLIN
0001AA, 0001AB,
0001AC, 0001AD,
0001AE, 0001AF,
0002, 0003, 0004, 0005, 0006 and 0007?
Please clarify the bid form.
19 3/26/
With the virus and everyone trying yo work from home subcontractors are asking for 3 week extension will this be possible?
Please see Amendment
20 3/26/
Will there be any Blast requirements on the glazing as non shown?
Blast rating is not required.
21 3/26/
Please consider pushing the bid date on this Solicitation at least one week to 16 April. There is quite a bit of work bidding right now at Cherry Point and Camp Lejeune and everyone is a bit displaced. A short extension would help this bid considerably. Thank you.
Please see Amendment
(End of Summary of Changes)