M301.pdf
PDF 2 MB Posted
- Attached to
- Building 7 Boiler #2 Replacement
- Solicitation number
- 12-223-SOL-00177
About this file
J-1 Drawings M301
View the file
Other files
| File | Type | Posted |
|---|---|---|
| amendment 3.pdf | ||
| NCTR Air Permit.pdf | ||
| attachment 2- list of attendees.pdf | ||
| amendment 2.pdf | ||
| amendment 1.pdf | ||
| attachment 1- list of attendees.pdf | ||
| S102.pdf | ||
| M304.pdf | ||
| M402.pdf | ||
| M501.pdf | ||
| M306.pdf | ||
| M401.pdf | ||
| E103.pdf | ||
| M303.pdf | ||
| M702.pdf | ||
| M302.pdf | ||
| M203.pdf | ||
| M404.pdf | ||
| M102.pdf | ||
| M200.pdf | ||
| E106.pdf | ||
| M403.pdf | ||
| M104.pdf | ||
| M305.pdf | ||
| M202.pdf | ||
| E202.pdf | ||
| M103.pdf | ||
| M201.pdf | ||
| M101.pdf | ||
| M601.pdf | ||
| M204.pdf | ||
| E201.pdf | ||
| M703.pdf | ||
| E104.pdf | ||
| 01120018 Add 01 Specs 080312.pdf | ||
| 12-223-SOL-00177.pdf | ||
| M100.pdf | ||
| E301.pdf | ||
| S101.pdf | ||
| E101.pdf | ||
| G100.pdf | ||
| E102.pdf | ||
| E105.pdf | ||
| M701.pdf |
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BOILER
M301
M301
BOILER PLATFORM
BOILER
BOILER
NOTE:
CONTRACTOR SHALL PROVIDE ECONOMIZER PLATFORM
FOR EXISTING FIRE TUBE BOILER #1
BSE-2
6 5
GENERAL NOTES:
1. CONTRACTOR SHALL INSTALL NEW PLATFORM FOR
EXISTING FIRE TUBE BOILER ECONOMIZER, SIMILAR TO
PLATFORM SHOWN ON THIS DRAWING.
2. CONTRACTOR SHALL INCLUDE COST OF ANY PIPING
MODIFICATION REQUIRED TO INSTALL THE ECONOMIZER
PLATFORM ON EXISTING BOILER.
KEYED NOTES :
STACK ECONOMIZER.
PLATFORM FOR ECONOMIZER
BOILER PLATORM/LADDER.
BOILER STACK. REFER TO FLOOR PLANS FOR
ROUTING OF THE STACK.
INSTALL PIPING AND VALVES TO ECONOMIZER SO
THAT ACCESS TO ALL ISOLATION VALVES CAN
BE DONE EASILY AT THE ECONOMIZER PLATFORM.
CONTRACTOR SHALL PROVIDE DETAILED
DIMENSIONED PIPING LAYOUT TO ENGINEER/OWNER
FOR REVIEW BEFORE FABRICATION AND INSTALLATION.
STEAM DISCHARGE PIPE.
STEAM RELIEF PIPING.
RELIEF VALVES. REFER TO BOILER SPECIFICATION.
ISSUE DATE:
SHEET NUMBER:
PROJECT NUMBER:
5800 EVERGREEN DRIVE
LITTLE ROCK,
ARKANSAS
72205-1757
Phone: (501) 666-6776 Fax: (501) 663-8888 tme@tmecorp.com
SHEET TITLE:
ENGINEER SEAL
CORPORATE SEAL
MARK DATE DESCRIPTION
Je ffe rs on
L ab or at or ie s F oo d an d
D ru g A dm in is tr at io n
N
C T
R R d Je ffe rs on , A
R
M301
MAIN HEADER SECTIONS
06-26-12
FDA-SOI-06-00268
B ui ld in g
B oi le r
R ep la ce m en t
1 08/03/12 ADDENDUM #1
1/2" = 1’−0"
ENLARGED PLAN − BOILER AND PLATFORMS
1/2" = 1’−0"
SECTION − FRONT ELEVATION − BOILER AND PLATFORMS
1/2" = 1’−0"
SECTION − SIDE ELEVATION − BOILER AND PLATFORMS
BID SET
BOILER 2 INSTALLATION − HVAC ECONOMIZER RISER
BOILER 2 INSTALLATION − BOILER RISER