M104.pdf

PDF 404 KB Posted

Attached to
Building 7 Boiler #2 Replacement
Solicitation number
12-223-SOL-00177
Issued by

About this file

J-1 Drawings M104

View the file

Other files

File Type Posted
amendment 3.pdf PDF
NCTR Air Permit.pdf PDF
attachment 2- list of attendees.pdf PDF
amendment 2.pdf PDF
amendment 1.pdf PDF
attachment 1- list of attendees.pdf PDF
S102.pdf PDF
M304.pdf PDF
M402.pdf PDF
M501.pdf PDF
M306.pdf PDF
M401.pdf PDF
E103.pdf PDF
M303.pdf PDF
M702.pdf PDF
M302.pdf PDF
M203.pdf PDF
M404.pdf PDF
M102.pdf PDF
M200.pdf PDF
E106.pdf PDF
M403.pdf PDF
M305.pdf PDF
M202.pdf PDF
E202.pdf PDF
M103.pdf PDF
M201.pdf PDF
M101.pdf PDF
M601.pdf PDF
M204.pdf PDF
E201.pdf PDF
M703.pdf PDF
E104.pdf PDF
01120018 Add 01 Specs 080312.pdf PDF
12-223-SOL-00177.pdf PDF
M100.pdf PDF
E301.pdf PDF
S101.pdf PDF
M301.pdf PDF
E101.pdf PDF
G100.pdf PDF
E102.pdf PDF
E105.pdf PDF
M701.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXISTING

DA

TANK

EXISTING

FORCED

DRAFT

FAN

#1

EXISTING

BINDUCED

DRAFT

FAN

#1

8" VTR8" VTR8" VTR8" VTR8" VTR8" VTR

14"

VTR

2 2

EXISTING

DA TANK

4" SCW

24"ø

6" BFW

4 3.4 3 2.4 1.4 1

H

E

D

B

A

6" VTR

10" S100

6" S100

2" SR

1" SR

1" SR

4" S100

EXISTING

PRV-1

1" SR

4" S100

4" S100

1" SR

EXISTING

ST-1

1" D

6" VTR

PRSV-1

ST-1

ST-1

6" BFW

1" D

1" D 1" D 1" D

2" BFW

2" SR 4" S15

PRV-1 4" S15

3" PCR

1" D

1" D

1" D

1" S15

4" SCW

DOWN TO

BDHX-1 ON

FIRST FLOOR

EXISTING FORCE DRAFT FAN #2, INDUCED DRAFT

FAN #2 AND ASSOCIATED EQUIPMENT TO BE

REMOVED UNDER BOILER #2 INSTALLATION.

REMOVE EXISTING CONCRETE HOUSE KEEPING

PADS. PATCH FLOOR SLAB AND SMOOTH THE

FLOOR SURFACE.

REMOVE EXISTING STACK AND CAP EXISTING

ROOF OPENING. CONTRACTOR MUST MAINTAIN

ROOF WARRANTY.

IN FILL EXISTING HOLES IN FAN PLATFORM.

REFER TO STRUCTURAL PLANS FOR SPECIFIC

DETAILS.

EXISTING DA TANK AND ASSOCIATED SYSTEM

PIPING TO BE REMOVED REFER TO GENERAL

NOTE.

EXISTING DA TANK INSTALLED UNDER BOILER 1

INSTALLATION.

EXISTING BOILER #1 FORCED AND INDUCED

DRAFT FANS TO REMAIN.

EXISTING EXHAUST FAN TO BE REMOVED AND

EXISTING OPENING SHALL BE ENLARGED TO

INSTALL THE NEW ROOF TOP EXHAUST FAN.

ALL EXISTING CONCRETE PAD FOR DRAFT FANS

FOR BOILER # 2 TO BE REMOVED.

ADDITIVE OPTION #1: REMOVE ALL ABANDONED

PIPING ASSOCIATED WITH EXISTING ABANDONED

DEARATOR TANK.

EXISTING PIPE TO BE REMOVED AND CAPPED AT

EACH END.

8" S15

8" S15

2" SR

EXISTING

BINDUCED

DRAFT

FAN

#1

6" VTR

7 7

4" VTR9

GENERAL NOTES:

1. CONTRACTOR SHALL PROVIDE PRICING

FOR OPTIONS 1 THRU 8 AS LISTED ON

THIS DRAWING.

2. ALL EXISTING EQUIPMENT, PIPING,

VALVES TO REMAIN UNLESS OTHERWISE

NOTED.

DEMOLITION KEYED NOTES:

BOILER INSTALLATION SYSTEM SCHEDULE

PROJECT PHASE SCOPE OF WORK - MAJOR EQUIPMENT

1). INSTALL NEW FIRE TUBE BOILER #2 AND 2-STAGE ECONOMIZER.

2). INSTALL THREE NEW EXHAUST FANS.

1). REMOVE EXISTING WATER TUBE BOILER #2, ALL ASSOCIATED PIPING BACK TO MAINS, AND ALL ASSOCIATED EQUIPMENT, INDUCED DRAFT

FAN, AND COMBUSTION AIR FAN.

OPTION 1: REMOVE ABANDONED DEAERATOR TANK AND ALL ASSOCIATED PIPING.

OPTION 2: REMOVE EXISTING FEEDWATER PUMPS AND ALL ASSOCIATED FEEDWATER PIPING ABOVE SLAB.

OPTION 3: REMOVE EXISTING FEEDWATER PIPING IN TRENCH.

OPTION 4: NEW STEAM UNIT HEATERS AND ALL S15 STEAM PIPING FEEDING NEW STEAM UNIT HEATERS.

OPTION 5: REMOTE MONITORING OF THE BOILERS, SURGE TANK, AND DEAERATOR TANK AT BUILDING 50.

OPTION 6: REMOTE MONITORING OF THE BOILER CONTROL SYSTEM AT BOILER MANUFACTURE'S TECHNICAL SERVICE FACILITY.

OPTION 7: RELOCATE EXISTING FLOW METER INSTALLED ON CAMPUS STEAM CONDENSATE STEAM RETURN PIPE.

OPTION 8: PROVIDE PVC JACKET FOR ALL NON-STEAM AND STEAM CONDENSATE PIPING (I.E. FEED WATER, DOMESTIC WATER, ECONOMIZER

PIPING FOR BOTH NEW AND EXISTING BOILER).

BOILER 2

INSTALLATION

DEMOLITION

BOILER 2

INSTALLATION

NEW WORK

ADDITIVE

OPTIONS

ISSUE DATE:

SHEET NUMBER:

PROJECT NUMBER:

5800 EVERGREEN DRIVE

LITTLE ROCK,

ARKANSAS

72205-1757

Phone: (501) 666-6776 Fax: (501) 663-8888 tme@tmecorp.com

SHEET TITLE:

ENGINEER SEAL

CORPORATE SEAL

MARK DATE DESCRIPTION

Je ffe rs on

L ab or at or ie s F oo d an d

D ru g A dm in is tr at io n

N

C T

R R d Je ffe rs on , A

R

M104

BOILER 2 INSTALLATION - FAN

PLATFORM - MECHANICAL

DEMOLITION

06-26-12

FDA-SOI-06-00268

B ui ld in g

B oi le r

R ep la ce m en t

1/4" = 1’−0"

BOILER 2 INSTALLATION − FAN PLATFORM PLAN − MECHANICAL DEMOLITION

1 08/03/12 ADDENDUM #1

BID SET

File details come from the government source that posted it. Updated .