About this opportunity

Sacramento County is soliciting bids for the Winter Storm 2022-2023 Alta Mesa Road Culvert Replacement Project, a federally-funded infrastructure repair initiative located in Sacramento County. The project involves comprehensive roadway reconstruction, specifically replacing a 36" corrugated steel culvert located 1,100 feet south of Boessow Road. Key project work includes dewatering a drainage canal, excavating the existing roadway and base material, removing the current culvert, placing and compacting new base material, installing a new culvert, backfilling and rebuilding the roadway, repaving, and restriping. Contractors must possess a Class A contractor's license and submit various certifications including non-collusion declarations, debarment certifications, and equal opportunity documentation. The bid submission deadline is August 21, 2025, at 2:00 pm, with a non-mandatory pre-bid meeting scheduled for August 6, 2025, at 1:30 pm. Bidders must provide a comprehensive Water Diversion Plan for County approval and ensure upstream water flow is limited to 5 cubic feet per second.

The contract includes a 6% Disadvantaged Business Enterprise (DBE) participation goal and requires compliance with advanced clean fleet regulations, Davis-Bacon Act wage requirements, and FHWA 1273 provisions. Contractors must be currently registered with the California Department of Industrial Relations and SAM.gov, and provide certificates of reported compliance for vehicles over 8,500 lbs. The project has an estimated construction cost of $470,000, with contract duration set at 20 working days and liquidated damages of $2,800 per day for delays. Insurance requirements include $3 million in general liability coverage and $2 million in automobile liability. The contract will be awarded based on the lowest total bid, which includes a base bid and two optional bid alternatives: one for changing pipe material from corrugated steel to reinforced concrete pipe, and another for installing concrete headwall and endwall. Contractors must also comply with non-discrimination provisions covering race, color, national origin, age, sex, disability, and limited English proficiency.

Opportunity text

The work to be performed under this contract includes the furnishing of all labor, materials, and equipment for:

Project work includes dewatering the drainage canal, excavating the existing roadway and base material, removing the existing culvert, placing and compacting base material, placing a new culvert, backfilling and rebuilding the roadway, repaving, and restriping.

Other items or details not mentioned above that are required by these Special Provisions shall be performed, placed, constructed, or installed in accordance with the Standard Construction Specifications and these Special Provisions. The construction, materials, and workmanship for items of work on the plans, but not specifically mentioned in these Special Provisions are referred to the Standard Construction Specifications for conformance.