PW 2027 Asphalt Resurfacing Contract 2, City Project No. 106822

Closed State & local contract opportunity Posted

Solicitation number
26-0299
State
Texas
Responses due

Opportunity facts

Jurisdiction
UNSPSC codes
Show all 33

Opportunity details come from fortworthtexas.bonfirehub.com. Updated .

About this opportunity

The City of Fort Worth is soliciting bids on PW 2027 Asphalt Resurfacing Contract 2 (City Project No. 106822) for pavement rehabilitation across twelve street segments, with bids due September 17, 2026 at 2:00 PM CST via the Bonfire portal. Prequalification is mandatory for asphalt paving heavy maintenance work valued at $1 million and over; applications must be submitted seven calendar days prior to bid opening. The small business enterprise goal is waived.

The scope encompasses approximately 49,112 square yards of 11-inch pavement pulverization, 39,112 square yards of 3-inch asphalt pavement (Superpave SP-D), 8,670 square yards of 2-inch asphalt pavement (Superpave SP-D) with 3-inch surface milling, 8,670 square yards of 4-inch asphalt base pavement Type B (DG-B), 2,500 linear feet of 7-inch curb and gutter, 786 tons of cement-lime, 5,880 square feet of 6-inch concrete driveway, 9,720 square feet of 4-inch concrete sidewalk, and 37 barrier-free ADA ramps across Ashridge Road, Ashwood Drive, Chasmier Way, Colfax Lane, Creekwood Lane, Dick Price Road, Natalie Drive, Regency Lane, Rockdale Road, Southbrook Circle, Trimble Drive, and Willow Creek Lane.

The engineer's estimate is $3.8 million with a 210-day completion timeline from Notice to Proceed. Liquidated damages are $650 per day for delays beyond the completion deadline. The contract requires performance, payment, and maintenance bonds; worker's compensation insurance certification under Texas Labor Code Section 406.096; prevailing wage compliance; and a bid bond equal to five percent of maximum bid price.

A pre-bid conference was held September 1, 2026 at 9:00 AM via web conference, with four organizations represented. Questions close September 11, 2026 at 2:00 PM CDT. Addendum No. 1 was issued September 9, 2026 and must be acknowledged in the bid submission. Bid opening is September 17, 2026; city council award is anticipated in October 2026, with construction commencement targeted for December 2026. Contact Tariqul Islam, Project Manager, at 817-392-2486 or tariqul.islam@fortworthtexas.gov.

Opportunity text

The major work will consist of the (approximate) following: * 2,500 LF 7" Curb and Gutter * 5,880 SF 6" Concrete Driveway * 9,720 SF 4" Concrete Sidewalk * 8,670 SY 2" Asphalt Pavement, Superpave SP-D * 8,670 SY 3" Surface Milling * 39,112 SY 3" Asphalt Pavement, Superpave SP-D * 8,670 SY 4" Asphalt Base Pvmt Type B (DG-B) * 49,112 SY 11" Pavement Pulverization * 786 TN CEMLIME™ * 37 EA Barrier Free ADA Ramp