7-00 45 11 Bidders Prequalifications.doc

DOC document 272 KB Posted

Attached to
PW 2027 Asphalt Resurfacing Contract 2, City Project No. 106822
Solicitation number
26-0299
Issued by
Tarrant County, Texas

About this file

This is a Bidders Prequalifications document issued by the City of Fort Worth, Texas for the 2027 Asphalt Resurfacing Contract 2 (City Project No. 106822). The project involves substantial pavement work including approximately 2,500 linear feet of curb and gutter, 5,880 square feet of concrete driveway, 9,720 square feet of concrete sidewalk, 8,670 square yards of 2-inch asphalt pavement, 39,112 square yards of 3-inch asphalt pavement, 49,112 square yards of pavement pulverization, 786 tons of cement-lime, and 37 barrier-free ADA ramps. Bidders or their designated subcontractors must be prequalified or have applied for prequalification by the City prior to submitting bids. Prequalification applications must be submitted seven calendar days prior to the bid opening date, with bidders or subcontractors who are not prequalified at the time bids are opened subject to bid rejection. The City will establish a bid limit for each contractor based on technical evaluation and financial analysis.

The prequalification process requires submission of audited or reviewed financial statements prepared by an independent certified public accounting firm, certified copies of organizational documents, completed prequalification applications including Texas Taxpayer Identification Number and DUNS number, and resumes reflecting construction experience of firm principals. Financial statements must demonstrate positive net working capital, with bidding capacity calculated by multiplying positive net working capital by a factor of ten. Financial statements must be no more than one year old and remain on file with the City for 16 months. Bidders must provide a minimum of five references for related work and submit an equipment schedule detailing all equipment under contractor control relevant to the prequalified work type. The City retains sole authority to approve, reject, suspend, or modify any prequalification based on demonstrated financial ability and performance, with approved contractors eligible to perform prequalified work types until the expiration date stated in their prequalification letter.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

00 45 11 - 1

BIDDERS PREQUALIFICATIONS

2027 ASPHALT RESURFACING CONTRACT 2

CITY PROJECT NO. 106822

CITY OF FORT WORTH

STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS

Revised August 13, 2021

1 SECTION 00 45 11

BIDDERS PREQUALIFICATIONS

1. Summary. A Bidder or their designated subcontractors are required to be prequalified or
have applied for prequalification by the City for the work types requiring prequalification
prior to submitting bids. To be considered for award of contract the Bidder must submit
Section 00 45 12, PREQUALIFICATION STATEMENT for the work type(s) listed with
their Bid. Any contractor or subcontractor who is not prequalified for the work type(s) listed
must submit Section 00 45 13, PREQUALIFICATION APPLICATION in accordance with
the requirements below. The information must be submitted seven (7) days prior to the

date of the opening of bids. Subcontractors must follow the same timelines as contractors

for obtaining prequalification review. Bidders or Subcontractors who are not prequalified at
the time bids are opened and reviewed may cause the bid to be rejected.
The prequalification process will establish a bid limit based on a technical evaluation and
financial analysis of the contractor. For example, a contractor wishing to submit bids on
projects to be opened on the 7th of April must file the information by the 31st day of March
in order to eligible to work on these projects. In order to facilitate the approval of a Bidder’s
Prequalification Application, the following must accompany the submission.
a.A complete set of audited or reviewed financial statements.
(1)Classified Balance Sheet
(2)Income Statement
(3)Statement of Cash Flows
(4)Statement of Retained Earnings
(5)Notes to the Financial Statements, if any
b. A certified copy of the firm’s organizational documents (Corporate Charter, Articles
of Incorporation, Articles of Organization, Certificate of Formation, LLC
Regulations, and Certificate of Limited Partnership Agreement).
c.A completed Bidder Prequalification Application.
(1)The firm’s Texas Taxpayer Identification Number as issued by the Texas
Comptroller of Public Accounts. To obtain a Texas Taxpayer Identification
number visit the Texas Comptroller of Public Accounts online at the
following web address www.window.state.tx.us/taxpermit/ and fill out the
application to apply for your Texas tax ID.
(2)The firm’s e-mail address and fax number.
(3)The firm’s DUNS number as issued by Dun & Bradstreet. This number
is used by the City for required reporting on Federal Aid projects. The DUNS
number may be obtained at www.dnb.com.
d. Resumes reflecting the construction experience of the principles of the firm for firms
submitting their initial prequalification. These resumes should include the size and
scope of the work performed.
e.Other information as requested by the City.
2. Prequalification Requirements
a.Financial Statements. Financial statement submission must be provided in
accordance with the following:
(1)The City requires that the original Financial Statement or a certified copy
be submitted for consideration.
(2)To be satisfactory, the financial statements must be audited or reviewed
by an independent, certified public accounting firm registered and in
good standing in any state. Current Texas statues also require that
accounting firms performing audits or reviews on business entities within
the State of Texas be properly licensed or registered with the Texas State
Board of Public Accountancy.
(3)The accounting firm should state in the audit report or review whether
the contractor is an individual, corporation, or limited liability company.
(4)Financial Statements must be presented in U.S. dollars at the current rate
of exchange of the Balance Sheet date.
(5)The City will not recognize any certified public accountant as
independent who is not, in fact, independent.
(6)The accountant’s opinion on the financial statements of the contracting
company should state that the audit or review has been conducted in
accordance with auditing standards generally accepted in the United
States of America. This must be stated in the accounting firm’s opinion.
It should: (1) express an unqualified opinion, or (2) express a qualified
opinion on the statements taken as a whole.
(7)The City reserves the right to require a new statement at any time.
(8)The financial statement must be prepared as of the last day of any month,
not more than one year old and must be on file with the City 16 months
thereafter, in accordance with Paragraph 1.
(9)The City will determine a contractor’s bidding capacity for the purposes
of awarding contracts. Bidding capacity is determined by multiplying the
positive net working capital (working capital = current assets – current
liabilities) by a factor of 10. Only those statements reflecting a positive
net working capital position will be considered satisfactory for
prequalification purposes.
(10) In the case that a bidding date falls within the time a new financial
statement is being prepared, the previous statement shall be updated with
proper verification.
b. Bidder Prequalification Application. A Bidder Prequalification Application must be
submitted along with audited or reviewed financial statements by firms wishing to be
eligible to bid on all classes of construction and maintenance projects. Incomplete

Applications will be rejected.

(1)In those schedules where there is nothing to report, the notation of
“None” or “N/A” should be inserted.
(2)A minimum of five (5) references of related work must be provided.
(3)Submission of an equipment schedule which indicates equipment under
the control of the Contractor and which is related to the type of work for
which the Contactor is seeking prequalification. The schedule must
include the manufacturer, model and general common description of
each piece of equipment. Abbreviations or means of describing
equipment other than provided above will not be accepted.
3. Eligibility for Award of Contract
a.The City shall be the sole judge as to a contractor’s prequalification.
b. The City may reject, suspend, or modify any prequalification for failure by the
contractor to demonstrate acceptable financial ability or performance.
c.The City will issue a letter as to the status of the prequalification approval.
d. If a contractor has a valid prequalification letter, the contractor will be eligible to
perform the prequalified work types until the expiration date stated in the letter.

8 END OF SECTION