Multiple Award Construction Contract (MACC)/Indefinite-Delivery Indefinite-Quantity (IDIQ) Little Rock AFB, AR
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- FA446021R0009
- Agency
- Air Mobility Command Air Force, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Place of performance
- Little Rock AFB, Arkansas 72099, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks proposals for an Indefinite-Delivery Indefinite-Quantity Multiple Award Construction Contract to provide general construction services in support of sustainment, restoration, and modernization projects at Little Rock Air Force Base, Arkansas. The Air Force Civil Engineer Squadron seeks to award multiple IDIQ contracts for new construction, alteration, repair, demolition, utilities, and design-build services. Offerors must demonstrate in-house design capabilities or access to designers. Proposals are due by various dates between June 7, 2021 and July 30, 2021. Evaluation will be based on technical qualifications, past performance, and price.
The set-aside designation is total small business. The primary NAICS code is 237990 and PSC code is S206. Work valued at $250 million to $150 million will be performed at Little Rock Air Force Base through September 2029 and include administrative, industrial, maintenance, warehouse, communications, personnel support, recreation, lodging, medical, training, and range facilities. Incumbent contractors may include large regional firms. Task orders will define specific project requirements.
Notice text
10 versions
Update #10 · Latest ·
Amendment 05 : - Updated Section L-2.3 Specific Instructions; Update Attachment 30 - Past Performance Package extend the due date on the Past Performance Questionnaire Memorandum within package to match the solicitation, incorporate Attachment 38 Questions and Answers, Update Attachment 13 Statement of work MACC, and update Attachment 32 to incorporate Questions and Answers to the RFP as Attachment 8.
This is for beta.SAM only - Attachment 36 will be removed and uploaded with the next amendment.
Amendment 04 : - Extended Proposal Submission, Updated Seed Project SOW & Schedule B, Updated Attachment 34, Sections G & L, deleted attachment 27, provided site visits sign in sheets and provide Offerors questions and Government answers.
Amendment 03 Block 3 Effective Date - is dated 23 Jun 2021 in error. It should be 21 Jun 2021. However, this still is an Amendment and the information in the amendment is accurate and will still be considered active with this solictation as of 21 Jun 2021.
Amendment 03 to Solicitation providing/adding 6-21-21:
Add an additional site visit date. The additional site visit date is Wednesday 23 Jun 2021 at 12:00 PM CDT.
Please submit name(s) for attendance by 8:00 AM 23 Jun 2021.
Questions will be due by Friday 25 Jun at 1:00 PM CDT.
Ensure to annotate when submitting name(s) for attendance on whether or not the individual has access to the base.
This amendment will also incorporate an amendment in Attachment 32 Convert Mission Planning Cell B-380 (Seed Project).
Amendment 02 to Solicitation providing/adding 6-17-21:
A. To ensure potential offerors know the PPI Tool MUST be requested as outlined in Amendment 2 and in this notice below. If not requested then the offeror will not be able to submit Past Performanc. beta.Sam will not let Attachment L-31 upload into the system.
B. Extend Past Performance submission date as outlined in the UPDATED Attachment 30.
Amendment 01 to Solcitation providing/adding 6-11-21:
A. Attachment 34 - PPI Tool Download Instructions with the prompts.
B. Revised EZSource Instructions in Section L -2.3 Part II Factor 1 - #3 to match Attachment 34 excluding prompts.
C. (Attachment 32 Seed Project) Attachment 6 - B-380 Remaining As-builts for the Seed Project RFP (Attachment 32 Seed Project)
D. Update Section J for Attachment 32 on the number of documents from 26 to 28 documents._______________________________________________________________________________________________
Update: Administrative action to Update Posting to provide the following:
A. A searchable and filliable Solicitation (SF1449)
B. Information to access the PPI tool: Please contact the CO/CS via email to request a copy of Attachment L-31 becasue BETA.SAM does not support the file type.
___________________________________________________________________________________________________
FA4460-21-R0009-Multiple Award Construction Contract (MACC)/Indefinite-Delivery Indefinite-Quantity (IDIQ) Little Rock AFB, AR Previously Posted as FA4460-21-R0005.
Little Rock Air Force Base (LRAFB) Indefinite-Delivery Indefinite-Quantity (IDIQ) Multiple Award Construction Contract (MACC) for sustainment, restoration, and modernization for general construction projects in support of the 19th Civil Engineer Squadron (19 CES). Construction projects to be performed under this MACC include, but are not limited to, new construction of buildings and structures, alteration and repair of buildings, structures, roads, grounds, roofs, specialty construction, utilities including Jet-A fuel systems, demolition of structures and building and miscellaneous construction services including hazardous material waste removal (i.e. asbestos, lead based paint, etc.). Types of facilities may include administrative, industrial, maintenance, warehouses, communications, personnel support, recreation, lodging, medical, training, ranges, roads, etc. Work may also include design/build from concept to full 100% design. In-house design capability or ready access to design capability is a must for projects under this MACC. Description of work will be identified in each individual task order.
Update #9 ·
This is for beta.SAM only - Attachment 36 will be removed and uploaded with the next amendment.
Amendment 04 : - Extended Proposal Submission, Updated Seed Project SOW & Schedule B, Updated Attachment 34, Sections G & L, deleted attachment 27, provided site visits sign in sheets and provide Offerors questions and Government answers.
Amendment 03 Block 3 Effective Date - is dated 23 Jun 2021 in error. It should be 21 Jun 2021. However, this still is an Amendment and the information in the amendment is accurate and will still be considered active with this solictation as of 21 Jun 2021.
Amendment 03 to Solicitation providing/adding 6-21-21:
Add an additional site visit date. The additional site visit date is Wednesday 23 Jun 2021 at 12:00 PM CDT.
Please submit name(s) for attendance by 8:00 AM 23 Jun 2021.
Questions will be due by Friday 25 Jun at 1:00 PM CDT.
Ensure to annotate when submitting name(s) for attendance on whether or not the individual has access to the base.
This amendment will also incorporate an amendment in Attachment 32 Convert Mission Planning Cell B-380 (Seed Project).
Amendment 02 to Solicitation providing/adding 6-17-21:
A. To ensure potential offerors know the PPI Tool MUST be requested as outlined in Amendment 2 and in this notice below. If not requested then the offeror will not be able to submit Past Performanc. beta.Sam will not let Attachment L-31 upload into the system.
B. Extend Past Performance submission date as outlined in the UPDATED Attachment 30.
Amendment 01 to Solcitation providing/adding 6-11-21:
A. Attachment 34 - PPI Tool Download Instructions with the prompts.
B. Revised EZSource Instructions in Section L -2.3 Part II Factor 1 - #3 to match Attachment 34 excluding prompts.
C. (Attachment 32 Seed Project) Attachment 6 - B-380 Remaining As-builts for the Seed Project RFP (Attachment 32 Seed Project)
D. Update Section J for Attachment 32 on the number of documents from 26 to 28 documents._______________________________________________________________________________________________
Update: Administrative action to Update Posting to provide the following:
A. A searchable and filliable Solicitation (SF1449)
B. Information to access the PPI tool: Please contact the CO/CS via email to request a copy of Attachment L-31 becasue BETA.SAM does not support the file type.
___________________________________________________________________________________________________
FA4460-21-R0009-Multiple Award Construction Contract (MACC)/Indefinite-Delivery Indefinite-Quantity (IDIQ) Little Rock AFB, AR Previously Posted as FA4460-21-R0005.
Little Rock Air Force Base (LRAFB) Indefinite-Delivery Indefinite-Quantity (IDIQ) Multiple Award Construction Contract (MACC) for sustainment, restoration, and modernization for general construction projects in support of the 19th Civil Engineer Squadron (19 CES). Construction projects to be performed under this MACC include, but are not limited to, new construction of buildings and structures, alteration and repair of buildings, structures, roads, grounds, roofs, specialty construction, utilities including Jet-A fuel systems, demolition of structures and building and miscellaneous construction services including hazardous material waste removal (i.e. asbestos, lead based paint, etc.). Types of facilities may include administrative, industrial, maintenance, warehouses, communications, personnel support, recreation, lodging, medical, training, ranges, roads, etc. Work may also include design/build from concept to full 100% design. In-house design capability or ready access to design capability is a must for projects under this MACC. Description of work will be identified in each individual task order.
Update #8 ·
Amendment 04 : - Extended Proposal Submission, Updated Seed Project SOW & Schedule B, Updated Attachment 34, Sections G & L, deleted attachment 27, provided site visits sign in sheets and provide Offerors questions and Government answers.
Amendment 03 Block 3 Effective Date - is dated 23 Jun 2021 in error. It should be 21 Jun 2021. However, this still is an Amendment and the information in the amendment is accurate and will still be considered active with this solictation as of 21 Jun 2021.
Amendment 03 to Solicitation providing/adding 6-21-21:
Add an additional site visit date. The additional site visit date is Wednesday 23 Jun 2021 at 12:00 PM CDT.
Please submit name(s) for attendance by 8:00 AM 23 Jun 2021.
Questions will be due by Friday 25 Jun at 1:00 PM CDT.
Ensure to annotate when submitting name(s) for attendance on whether or not the individual has access to the base.
This amendment will also incorporate an amendment in Attachment 32 Convert Mission Planning Cell B-380 (Seed Project).
Amendment 02 to Solicitation providing/adding 6-17-21:
A. To ensure potential offerors know the PPI Tool MUST be requested as outlined in Amendment 2 and in this notice below. If not requested then the offeror will not be able to submit Past Performanc. beta.Sam will not let Attachment L-31 upload into the system.
B. Extend Past Performance submission date as outlined in the UPDATED Attachment 30.
Amendment 01 to Solcitation providing/adding 6-11-21:
A. Attachment 34 - PPI Tool Download Instructions with the prompts.
B. Revised EZSource Instructions in Section L -2.3 Part II Factor 1 - #3 to match Attachment 34 excluding prompts.
C. (Attachment 32 Seed Project) Attachment 6 - B-380 Remaining As-builts for the Seed Project RFP (Attachment 32 Seed Project)
D. Update Section J for Attachment 32 on the number of documents from 26 to 28 documents._______________________________________________________________________________________________
Update: Administrative action to Update Posting to provide the following:
A. A searchable and filliable Solicitation (SF1449)
B. Information to access the PPI tool: Please contact the CO/CS via email to request a copy of Attachment L-31 becasue BETA.SAM does not support the file type.
___________________________________________________________________________________________________
FA4460-21-R0009-Multiple Award Construction Contract (MACC)/Indefinite-Delivery Indefinite-Quantity (IDIQ) Little Rock AFB, AR Previously Posted as FA4460-21-R0005.
Little Rock Air Force Base (LRAFB) Indefinite-Delivery Indefinite-Quantity (IDIQ) Multiple Award Construction Contract (MACC) for sustainment, restoration, and modernization for general construction projects in support of the 19th Civil Engineer Squadron (19 CES). Construction projects to be performed under this MACC include, but are not limited to, new construction of buildings and structures, alteration and repair of buildings, structures, roads, grounds, roofs, specialty construction, utilities including Jet-A fuel systems, demolition of structures and building and miscellaneous construction services including hazardous material waste removal (i.e. asbestos, lead based paint, etc.). Types of facilities may include administrative, industrial, maintenance, warehouses, communications, personnel support, recreation, lodging, medical, training, ranges, roads, etc. Work may also include design/build from concept to full 100% design. In-house design capability or ready access to design capability is a must for projects under this MACC. Description of work will be identified in each individual task order.
Update #7 ·
Amendment 03 Block 3 Effective Date - is dated 23 Jun 2021 in error. It should be 21 Jun 2021. However, this still is an Amendment and the information in the amendment is accurate and will still be considered active with this solictation as of 21 Jun 2021.
Amendment 03 to Solicitation providing/adding 6-21-21:
Add an additional site visit date. The additional site visit date is Wednesday 23 Jun 2021 at 12:00 PM CDT.
Please submit name(s) for attendance by 8:00 AM 23 Jun 2021.
Questions will be due by Friday 25 Jun at 1:00 PM CDT.
Ensure to annotate when submitting name(s) for attendance on whether or not the individual has access to the base.
This amendment will also incorporate an amendment in Attachment 32 Convert Mission Planning Cell B-380 (Seed Project).
Amendment 02 to Solicitation providing/adding 6-17-21:
A. To ensure potential offerors know the PPI Tool MUST be requested as outlined in Amendment 2 and in this notice below. If not requested then the offeror will not be able to submit Past Performanc. beta.Sam will not let Attachment L-31 upload into the system.
B. Extend Past Performance submission date as outlined in the UPDATED Attachment 30.
Amendment 01 to Solcitation providing/adding 6-11-21:
A. Attachment 34 - PPI Tool Download Instructions with the prompts.
B. Revised EZSource Instructions in Section L -2.3 Part II Factor 1 - #3 to match Attachment 34 excluding prompts.
C. (Attachment 32 Seed Project) Attachment 6 - B-380 Remaining As-builts for the Seed Project RFP (Attachment 32 Seed Project)
D. Update Section J for Attachment 32 on the number of documents from 26 to 28 documents._______________________________________________________________________________________________
Update: Administrative action to Update Posting to provide the following:
A. A searchable and filliable Solicitation (SF1449)
B. Information to access the PPI tool: Please contact the CO/CS via email to request a copy of Attachment L-31 becasue BETA.SAM does not support the file type.
___________________________________________________________________________________________________
FA4460-21-R0009-Multiple Award Construction Contract (MACC)/Indefinite-Delivery Indefinite-Quantity (IDIQ) Little Rock AFB, AR Previously Posted as FA4460-21-R0005.
Little Rock Air Force Base (LRAFB) Indefinite-Delivery Indefinite-Quantity (IDIQ) Multiple Award Construction Contract (MACC) for sustainment, restoration, and modernization for general construction projects in support of the 19th Civil Engineer Squadron (19 CES). Construction projects to be performed under this MACC include, but are not limited to, new construction of buildings and structures, alteration and repair of buildings, structures, roads, grounds, roofs, specialty construction, utilities including Jet-A fuel systems, demolition of structures and building and miscellaneous construction services including hazardous material waste removal (i.e. asbestos, lead based paint, etc.). Types of facilities may include administrative, industrial, maintenance, warehouses, communications, personnel support, recreation, lodging, medical, training, ranges, roads, etc. Work may also include design/build from concept to full 100% design. In-house design capability or ready access to design capability is a must for projects under this MACC. Description of work will be identified in each individual task order.
Update #6 ·
Amendment 03 to Solicitation providing/adding 6-23-21:
Add an additional site visit date. The additional site visit date is Wednesday 23 Jun 2021 at 12:00 PM CDT.
Please submit name(s) for attendance by 8:00 AM 23 Jun 2021.
Questions will be due by Friday 25 Jun at 1:00 PM CDT.
Ensure to annotate when submitting name(s) for attendance on whether or not the individual has access to the base.
This amendment will also incorporate an amendment in Attachment 32 Convert Mission Planning Cell B-380 (Seed Project).
Amendment 02 to Solicitation providing/adding 6-17-21:
A. To ensure potential offerors know the PPI Tool MUST be requested as outlined in Amendment 2 and in this notice below. If not requested then the offeror will not be able to submit Past Performanc. beta.Sam will not let Attachment L-31 upload into the system.
B. Extend Past Performance submission date as outlined in the UPDATED Attachment 30.
Amendment 01 to Solcitation providing/adding 6-11-21:
A. Attachment 34 - PPI Tool Download Instructions with the prompts.
B. Revised EZSource Instructions in Section L -2.3 Part II Factor 1 - #3 to match Attachment 34 excluding prompts.
C. (Attachment 32 Seed Project) Attachment 6 - B-380 Remaining As-builts for the Seed Project RFP (Attachment 32 Seed Project)
D. Update Section J for Attachment 32 on the number of documents from 26 to 28 documents._______________________________________________________________________________________________
Update: Administrative action to Update Posting to provide the following:
A. A searchable and filliable Solicitation (SF1449)
B. Information to access the PPI tool: Please contact the CO/CS via email to request a copy of Attachment L-31 becasue BETA.SAM does not support the file type.
___________________________________________________________________________________________________
FA4460-21-R0009-Multiple Award Construction Contract (MACC)/Indefinite-Delivery Indefinite-Quantity (IDIQ) Little Rock AFB, AR Previously Posted as FA4460-21-R0005.
Little Rock Air Force Base (LRAFB) Indefinite-Delivery Indefinite-Quantity (IDIQ) Multiple Award Construction Contract (MACC) for sustainment, restoration, and modernization for general construction projects in support of the 19th Civil Engineer Squadron (19 CES). Construction projects to be performed under this MACC include, but are not limited to, new construction of buildings and structures, alteration and repair of buildings, structures, roads, grounds, roofs, specialty construction, utilities including Jet-A fuel systems, demolition of structures and building and miscellaneous construction services including hazardous material waste removal (i.e. asbestos, lead based paint, etc.). Types of facilities may include administrative, industrial, maintenance, warehouses, communications, personnel support, recreation, lodging, medical, training, ranges, roads, etc. Work may also include design/build from concept to full 100% design. In-house design capability or ready access to design capability is a must for projects under this MACC. Description of work will be identified in each individual task order.
Update #5 ·
Amendment 2 - to Solicitation providing/adding 6-17-21:
A. To ensure potential offerors know the PPI Tool MUST be requested as outlined in Amendment 2 and in this notice below. If not requested then the offeror will not be able to submit Past Performanc. beta.Sam will not let Attachment L-31 upload into the system.
B. Extend Past Performance submission date as outlined in the UPDATED Attachment 30.
Amendment 01 to Solcitation providing/adding 6-11-21:
A. Attachment 34 - PPI Tool Download Instructions with the prompts.
B. Revised EZSource Instructions in Section L -2.3 Part II Factor 1 - #3 to match Attachment 34 excluding prompts.
C. (Attachment 32 Seed Project) Attachment 6 - B-380 Remaining As-builts for the Seed Project RFP (Attachment 32 Seed Project)
D. Update Section J for Attachment 32 on the number of documents from 26 to 28 documents._______________________________________________________________________________________________
Update: Administrative action to Update Posting to provide the following:
A. A searchable and filliable Solicitation (SF1449)
B. Information to access the PPI tool: Please contact the CO/CS via email to request a copy of Attachment L-31 becasue BETA.SAM does not support the file type.
___________________________________________________________________________________________________
FA4460-21-R0009-Multiple Award Construction Contract (MACC)/Indefinite-Delivery Indefinite-Quantity (IDIQ) Little Rock AFB, AR Previously Posted as FA4460-21-R0005.
Little Rock Air Force Base (LRAFB) Indefinite-Delivery Indefinite-Quantity (IDIQ) Multiple Award Construction Contract (MACC) for sustainment, restoration, and modernization for general construction projects in support of the 19th Civil Engineer Squadron (19 CES). Construction projects to be performed under this MACC include, but are not limited to, new construction of buildings and structures, alteration and repair of buildings, structures, roads, grounds, roofs, specialty construction, utilities including Jet-A fuel systems, demolition of structures and building and miscellaneous construction services including hazardous material waste removal (i.e. asbestos, lead based paint, etc.). Types of facilities may include administrative, industrial, maintenance, warehouses, communications, personnel support, recreation, lodging, medical, training, ranges, roads, etc. Work may also include design/build from concept to full 100% design. In-house design capability or ready access to design capability is a must for projects under this MACC. Description of work will be identified in each individual task order.
Update #4 ·
Amendment 01 to Solcitation providing/adding 6-11-21:
A. Attachment 34 - PPI Tool Download Instructions with the prompts.
B. Revised EZSource Instructions in Section L -2.3 Part II Factor 1 - #3 to match Attachment 34 excluding prompts.
C. (Attachment 32 Seed Project) Attachment 6 - B-380 Remaining As-builts for the Seed Project RFP (Attachment 32 Seed Project)
D. Update Section J for Attachment 32 on the number of documents from 26 to 28 documents._______________________________________________________________________________________________
Update: Administrative action to Update Posting to provide the following:
A. A searchable and filliable Solicitation (SF1449)
B. Information to access the PPI tool: Please contact the CO/CS via email to request a copy of Attachment L-31 becasue BETA.SAM does not support the file type.
___________________________________________________________________________________________________
FA4460-21-R0009-Multiple Award Construction Contract (MACC)/Indefinite-Delivery Indefinite-Quantity (IDIQ) Little Rock AFB, AR Previously Posted as FA4460-21-R0005.
Little Rock Air Force Base (LRAFB) Indefinite-Delivery Indefinite-Quantity (IDIQ) Multiple Award Construction Contract (MACC) for sustainment, restoration, and modernization for general construction projects in support of the 19th Civil Engineer Squadron (19 CES). Construction projects to be performed under this MACC include, but are not limited to, new construction of buildings and structures, alteration and repair of buildings, structures, roads, grounds, roofs, specialty construction, utilities including Jet-A fuel systems, demolition of structures and building and miscellaneous construction services including hazardous material waste removal (i.e. asbestos, lead based paint, etc.). Types of facilities may include administrative, industrial, maintenance, warehouses, communications, personnel support, recreation, lodging, medical, training, ranges, roads, etc. Work may also include design/build from concept to full 100% design. In-house design capability or ready access to design capability is a must for projects under this MACC. Description of work will be identified in each individual task order.
Update #3 ·
Update: Administrative action to Update Posting to provide the following:
A. A searchable and filliable Solicitation (SF1449)
B. Information to access the PPI tool: Please contact the CO/CS via email to request a copy of Attachment L-31 becasue BETA.SAM does not support the file type.
___________________________________________________________________________________________________
FA4460-21-R0009-Multiple Award Construction Contract (MACC)/Indefinite-Delivery Indefinite-Quantity (IDIQ) Little Rock AFB, AR Previously Posted as FA4460-21-R0005.
Little Rock Air Force Base (LRAFB) Indefinite-Delivery Indefinite-Quantity (IDIQ) Multiple Award Construction Contract (MACC) for sustainment, restoration, and modernization for general construction projects in support of the 19th Civil Engineer Squadron (19 CES). Construction projects to be performed under this MACC include, but are not limited to, new construction of buildings and structures, alteration and repair of buildings, structures, roads, grounds, roofs, specialty construction, utilities including Jet-A fuel systems, demolition of structures and building and miscellaneous construction services including hazardous material waste removal (i.e. asbestos, lead based paint, etc.). Types of facilities may include administrative, industrial, maintenance, warehouses, communications, personnel support, recreation, lodging, medical, training, ranges, roads, etc. Work may also include design/build from concept to full 100% design. In-house design capability or ready access to design capability is a must for projects under this MACC. Description of work will be identified in each individual task order.
Update #2 ·
AMENDMENT 0001: Administrative action to provide the following:
A. A searchable and filliable Solicitation (SF1449)
B. Information to access the PPI tool: Please contact the CO/CS via email to request a copy of Attachment L-31 becasue BETA.SAM does not support the file type. Here's is the link to the PPI tool info page as well: .https://usaf.dps.mil/teams/PK-Central/AFCC/records_contract/EZ/SitePages/PPI%20Tool.aspx.
___________________________________________________________________________________________________
FA4460-21-R0009-Multiple Award Construction Contract (MACC)/Indefinite-Delivery Indefinite-Quantity (IDIQ) Little Rock AFB, AR Previously Posted as FA4460-21-R0005.
Little Rock Air Force Base (LRAFB) Indefinite-Delivery Indefinite-Quantity (IDIQ) Multiple Award Construction Contract (MACC) for sustainment, restoration, and modernization for general construction projects in support of the 19th Civil Engineer Squadron (19 CES). Construction projects to be performed under this MACC include, but are not limited to, new construction of buildings and structures, alteration and repair of buildings, structures, roads, grounds, roofs, specialty construction, utilities including Jet-A fuel systems, demolition of structures and building and miscellaneous construction services including hazardous material waste removal (i.e. asbestos, lead based paint, etc.). Types of facilities may include administrative, industrial, maintenance, warehouses, communications, personnel support, recreation, lodging, medical, training, ranges, roads, etc. Work may also include design/build from concept to full 100% design. In-house design capability or ready access to design capability is a must for projects under this MACC. Description of work will be identified in each individual task order.
Update #1 ·
FA4460-21-R0009-Multiple Award Construction Contract (MACC)/Indefinite-Delivery Indefinite-Quantity (IDIQ) Little Rock AFB, AR Previously Posted as FA4460-21-R0005.
Little Rock Air Force Base (LRAFB) Indefinite-Delivery Indefinite-Quantity (IDIQ) Multiple Award Construction Contract (MACC) for sustainment, restoration, and modernization for general construction projects in support of the 19th Civil Engineer Squadron (19 CES). Construction projects to be performed under this MACC include, but are not limited to, new construction of buildings and structures, alteration and repair of buildings, structures, roads, grounds, roofs, specialty construction, utilities including Jet-A fuel systems, demolition of structures and building and miscellaneous construction services including hazardous material waste removal (i.e. asbestos, lead based paint, etc.). Types of facilities may include administrative, industrial, maintenance, warehouses, communications, personnel support, recreation, lodging, medical, training, ranges, roads, etc. Work may also include design/build from concept to full 100% design. In-house design capability or ready access to design capability is a must for projects under this MACC. Description of work will be identified in each individual task order.
Attachments
Show all 50
This notice has more attachments on GovTribe.
Notice history
| Notice | Type | Posted |
|---|---|---|
| Multiple Award Construction Contract (MACC)/Indefinite-Delivery Indefinite-Quantity (IDIQ) Little Rock AFB, AR | Award Notice | |
| Multiple Award Construction Contract (MACC)/Indefinite-Delivery Indefinite-Quantity (IDIQ) Little Rock AFB, AR | Solicitation | |
| Multiple Award Construction Contract (MACC)/Indefinite-Delivery Indefinite-Quantity (IDIQ) Little Rock AFB, AR | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity